About this file

This document contains a solicitation for a multiple award indefinite-delivery indefinite-quantity task order contract for construction, repair, alteration, design-build, and abatement services. The solicitation seeks to award up to six contracts per zone in thirteen zones across five states to provide general construction services for federal buildings. Services will be required on an as-needed basis for individual task orders ranging from $2,000 to $3,500,000. The maximum order value is $1,000,000 for small projects pools, $4,000,000 for large projects pools, and $5,000,000 for contracts in both pools. The base term is one year with four one-year options, for a potential five-year contract length. The solicitation sets aside this opportunity exclusively for small businesses and will use best value tradeoff source selection evaluating technical merit and price to award contracts.

View the file

Other files

File Type Posted
10 Round 9 SF30 Amendment 47 2022 08 03.pdf PDF
10 Round 9 Zonal Agreement Louisiana 2022 3 31.pdf PDF
10 SF30 Amendment 46 2022 03 31.pdf PDF
10 Past Performance Questionnaire 2022 03 01.pdf PDF
10 SF30 Amendment 44 2022 03 14.pdf PDF
Pre Proposal Conference Agenda 2022 03 10.pdf PDF
Hypothetical Project A SOW 2019 09 20-2.pdf PDF
10 Round 9 Zonal Agreement Louisiana 2022 3 01.pdf PDF
10 Solicitation Response Form.xlsx XLSX spreadsheet
10 Amendment 43 Form 1442 2022 03 02.pdf PDF
Questions and Answers to Date-2.pdf PDF
Hypothetical Project B Drawing 2019 09 20-2.pdf PDF
10 Louisiana Solicitation 2022 03 02.pdf PDF
10 GSA527-21 2022 03 01.pdf PDF
10 Zonal IDIQ SOW 2022 03 01.pdf PDF
Pricing Proposal Form 2022 xx xx.xlsx XLSX spreadsheet
10 Courthouse Carpet Policy 2019 09 20.pdf PDF
Hypothetical Project A Drawings 2019 09 20-2.pdf PDF
10 Project Proposal Format 2019 08 07-2.pdf PDF
10 Zonal Map.pdf PDF
10 Subcontractor Consent Template 2022 03 01.docx DOCX document
Hypothetical Project B SOW 2019 09 20-2.pdf PDF
10 Form C301 2022 03 01.pdf PDF
10 GSA Region 7 Field Offices 2022 03 01.pdf PDF
10 SF30 Amendment 42 2021 09 22.pdf PDF
10 SF30 Amendment 41 2021 07 22.pdf PDF
10 SF30 Amendment 40 2021 01 27.pdf PDF
Houston Zone Questions and Answers.pdf PDF
Houston Pre-Proposal Conference Agenda 2021 01 06.pdf PDF
10 Solicitation Response Form 2021 01 12.xlsx XLSX spreadsheet
10 47PH0818R0004 Amendment 39 SF30.pdf PDF
Pricing Proposal Form 2020 12 17.xlsx XLSX spreadsheet
GSA Region 7 Field Offices 2019 09 20.pdf PDF
10 Round 8 Zonal Agreement Houston 2020 12 17 MD.pdf PDF
Hypothetical Project B SOW 2019 09 20.pdf PDF
05 Houston WDs - Combined - 2020 12 16.pdf PDF
10 Project Proposal Format 2019 08 07.pdf PDF
Questions and Answers to Date.pdf PDF
Form 1442 2020 12 21.pdf PDF
10 Solicitation Response Form 2020 12 17.xlsx XLSX spreadsheet
Form GSA527 2019 09 20.pdf PDF
10 Form C301 2019 07 03.pdf PDF
Courthouse Carpet Policy 2019 09 20.pdf PDF
10 Round 8 Zonal Map 2019 01 06.pdf PDF
10 Round 8 Zonal IDIQ SOW 2020 12 03.pdf PDF
10 Past Performance Questionnaire 2020 12 17.pdf PDF
10 Subcontractor consent template 2020 12 17.docx DOCX document
Hypothetical Project B Drawing 2019 09 20.pdf PDF
Hypothetical Project A Drawings 2019 09 20.pdf PDF
Hypothetical Project A SOW 2019 09 20.pdf PDF
Show 40 more

Latest 50 of 338 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

R10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

7PQA

Matthew Deptuch

Amendment 45 adds the updated Questions and Answers document as an attachment to the Louisiana Solicitation.

GSA PBS 7PQA

ACQUISITION MANAGEMENT DIVISION - PROGRAM

SUPPORT BRANCH

819 TAYLOR ST RM 12B01

FORT WORTH, TX 76102

47PH0818R0004

1 4

03/21/2022

07/14/2018

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Louisiana Zone On-ramping Questions:

Multiple Award Indefinite-Delivery Indefinite-Quantity (IDIQ) Task Order Contract for

Construction, Repair, and Alteration, with Design-Build and incidental Abatement for GSA/PBS

Region 7, Solicitation: 47PH0818R0004

Q1: Why is GSA on-ramping?

A1: GSA has determined the need to bring on additional contractors for the Large and Small

Projects Pools to increase competition.

Q2: If there is a current contractor that has a contract in the Louisiana Zone are they required to submit another proposal?

A2: No, current IDIQ contractor holders in the Louisiana Zone are not required to submit another proposal to maintain their IDIQ contract. Current contract holders in the Louisiana Zone may bid on a project pool that they don’t currently have a contract in.

Q3: Are contractors that have a current contract in the Louisiana zone allowed to submit a proposal for the projects pool they do not have an award for?

A3: Yes.

Q4: Are you going to post the Slide Deck?

Q4: No, all the information on the slides is in the solicitation.

Q5: There does not appear to be a Past Performance Questionnaire (PPQ) provided for

Amendment 43 for solicitation no. 47PH0818R0004 on the SAM.gov site. Please advise if a

Past Performance Questionnaire for Amendment 43 will be provided, and when we can expect to have that critical document?

A5: Amendment 44 was posted to www.sam.gov that adds the Past Performance Questionnaire

(PPQ).

Q6: Will the hypothetical projects be built?

A6: No, they are hypothetical projects.

Q7: Will a full-time employee be required to be on each site during the course of the IDIQ?

A7: Per FAR 52.236-6 Superintendence by the Contractor: “At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.”

Q8-21: Reference the Hypothetical Projects

Q8: Has the area been tested for substances requiring abatement?

See below.

Q9: Are the two chambers and associated areas assumed to be occupied?

See below.

Q10: Will all furniture, fixtures, equipment, personal items, etc. be removed from the spaces by

Owner?

See below.

Q11: What is the wall surface in the restrooms where the paper towel dispenser is currently?

Repairs to wall where dispenser is removed.

See below.

Q12: What is the manufacturer make/style of the existing plastic laminate on the casework

(existing base cabinets) that is to be matched? What is the category (standard, premium, custom)?

See below.

PAGE OF PAGES

2 4

Q13: Please confirm there is only minor work in the restrooms (paper towel dispenser relocation and medicine cabinet installation).

See below.

Q14: Please confirm no work related to existing lighting and/or controls.

See below.

Q15: Are these drawings and Scope of Work considered complete for construction?

16 Will a job trailer and/or construction temporary toilets be required, in the event of extended construction?

See below.

Q17: Is there space on site for materials?

See below.

Q18: Is the cost of the carpet pad separate from the square yard price for carpet provided in the carpet policy? Is adhesive included in the square yard price?

See below.

Q19: Is there a Basis of Design for the carpet similar to the one provided for LVT?

See below.

Q20: Is contractor responsible for anything related to alternate/temporary space during construction?

See below.

Q21: For Hypothetical Project A Drawings, please confirm room dimensions. Example, at B605, Galley/Copy Files, Item 13 calls to install 12’ – 9” of cabinetry on east wall, however, wall length is scaling at 9’-0”.

See below.

A8-21: "Per the Solicitation Section II.D(2) Hypothetical Projects, "This factor evaluates each

Offeror’s ability to interpret the requirements of hypothetical project(s) and incorporate those requirements into complete, reasonable, and technically sound hypothetical project schedule(s), submittals, and price proposal(s)...." Therefore, as part of the evaluation, it is the offeror's duty to determine from the documents provided, the best approach to the Hypothetical Projects.

Q22: What is the anticipated extent of abatement in general on projects?

A22: We do not have a projection of the anticipated extent of abatement in general on projects;

however, at any time you can go to https://hallways.cap.gsa.gov/app/#/ to access the Acquisition

Gateway, click on “Tools”, click on “Forecast of Contracting Opportunities.” This database is continually updated with potential projects.

Q23: In reference to Re-solicitation of Louisiana Construction IDIQ, would awardees be able to participate in Border El Paso Zone IDIQ Task Orders? Our company offers commercial construction services, and we are interested in participating in the Border El Paso Zone work.

A23: Potentially, yes. The primary zone for this contract is the Louisiana Zone and the other 12 zones in GSA Region 7 are considered secondary zones. Per Agreement Section III.R.(2), a TO

CO can determine it is in the best interest of the Government to compete any project among all eligible IDIQ contractors in just the primary zone, or in the primary zone and one or more secondary zones. Additionally, per the Agreement Section III.R.(2), contractors in the Louisiana

Zone are required to submit timely, good-faith competitive proposals for at least seventy-five

(75%) of the number of TO RFPs issued per year in a required county or parish for which a firm has sufficient bonding at the time the RFP is issued, if there is sufficient MOL remaining in the current performance period for the IDIQ is required.

3 4

Q24: Do the anticipated projects have damage beyond normal wear and tear?

A24: Due to the wide variety of projects that are anticipated for this zone, it is in the realm of possibility that a future project will have damage beyond normal wear and tear.

Q25: Are there specific activities required to be performed during “other than normal” working hours?

A25: Depending on the location, type of work, etc., the Task Order Contracting Officer will specify in the Task Order Request for Proposal (RFP) if there are specific activities required to be performed during “other than normal” working hours.

Q26: For a task order, will stamped/signed drawings be required?

A26: Stamped/signed drawings are required for Design-Build, or as stated in the Statement of

Work (SOW).

4 4