About this file

This solicitation requests proposals for multiple indefinite delivery indefinite quantity construction contracts for facilities in Region 7. Services include general construction, repair, alteration, design-build, and incidental abatement. The region is organized into thirteen zones, with awards made for up to two zones at a time. Task orders will range from $2,000 to $3,500,000 under a maximum order limitation of $1,000,000 for small projects and $4,000,000 for large projects, or $5,000,000 for both. The base term is one year with four one-year options, for a potential five-year period of performance. The solicitation will utilize best value source selection based on technical merit and price, with technical factors significantly more important than price. Awards will be made to up to six contractors per zone.

View the file

Other files

File Type Posted
10 Round 9 SF30 Amendment 47 2022 08 03.pdf PDF
10 Round 9 Zonal Agreement Louisiana 2022 3 31.pdf PDF
10 SF30 Amendment 46 2022 03 31.pdf PDF
10 SF30 Amendment 45 2022 03 21 .pdf PDF
10 Past Performance Questionnaire 2022 03 01.pdf PDF
10 SF30 Amendment 44 2022 03 14.pdf PDF
Pre Proposal Conference Agenda 2022 03 10.pdf PDF
Hypothetical Project A SOW 2019 09 20-2.pdf PDF
10 Round 9 Zonal Agreement Louisiana 2022 3 01.pdf PDF
10 Solicitation Response Form.xlsx XLSX spreadsheet
10 Amendment 43 Form 1442 2022 03 02.pdf PDF
Questions and Answers to Date-2.pdf PDF
Hypothetical Project B Drawing 2019 09 20-2.pdf PDF
10 Louisiana Solicitation 2022 03 02.pdf PDF
10 GSA527-21 2022 03 01.pdf PDF
10 Zonal IDIQ SOW 2022 03 01.pdf PDF
Pricing Proposal Form 2022 xx xx.xlsx XLSX spreadsheet
10 Courthouse Carpet Policy 2019 09 20.pdf PDF
Hypothetical Project A Drawings 2019 09 20-2.pdf PDF
10 Project Proposal Format 2019 08 07-2.pdf PDF
10 Zonal Map.pdf PDF
10 Subcontractor Consent Template 2022 03 01.docx DOCX document
Hypothetical Project B SOW 2019 09 20-2.pdf PDF
10 Form C301 2022 03 01.pdf PDF
10 GSA Region 7 Field Offices 2022 03 01.pdf PDF
10 SF30 Amendment 42 2021 09 22.pdf PDF
10 SF30 Amendment 41 2021 07 22.pdf PDF
10 SF30 Amendment 40 2021 01 27.pdf PDF
Houston Zone Questions and Answers.pdf PDF
Houston Pre-Proposal Conference Agenda 2021 01 06.pdf PDF
10 Solicitation Response Form 2021 01 12.xlsx XLSX spreadsheet
10 47PH0818R0004 Amendment 39 SF30.pdf PDF
Pricing Proposal Form 2020 12 17.xlsx XLSX spreadsheet
GSA Region 7 Field Offices 2019 09 20.pdf PDF
10 Round 8 Zonal Agreement Houston 2020 12 17 MD.pdf PDF
Hypothetical Project B SOW 2019 09 20.pdf PDF
05 Houston WDs - Combined - 2020 12 16.pdf PDF
Questions and Answers to Date.pdf PDF
Form 1442 2020 12 21.pdf PDF
10 Solicitation Response Form 2020 12 17.xlsx XLSX spreadsheet
Form GSA527 2019 09 20.pdf PDF
10 Form C301 2019 07 03.pdf PDF
Courthouse Carpet Policy 2019 09 20.pdf PDF
10 Round 8 Zonal Map 2019 01 06.pdf PDF
10 Round 8 Zonal IDIQ SOW 2020 12 03.pdf PDF
10 Past Performance Questionnaire 2020 12 17.pdf PDF
10 Subcontractor consent template 2020 12 17.docx DOCX document
Hypothetical Project B Drawing 2019 09 20.pdf PDF
Hypothetical Project A Drawings 2019 09 20.pdf PDF
Hypothetical Project A SOW 2019 09 20.pdf PDF
Show 40 more

Latest 50 of 338 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task Order Price Proposal Format Instructions Contractors must use RSMeans line items (such as hardcopy, online version, other software, etc.) to prepare task order proposals using the Facilities Construction and Facilities Maintenance & Repair Open Titles.

To ensure consistency in the way proposals are provided, create price proposals in the following format...

LeeAWhite Typewritten Text See more explanatory notes on last page

Include on Proposal • Division line number

• Description of what is included in the line item

• Quantity

• Unit of measure

• Total Material cost

• Total Labor cost

• Total Material +

Labor

• Contractor’s divisional factor

• General Contractor’s totals by division

Note: Overhead, indirect costs and profit are already included in the divisional factors and should not be listed as separate line items. The factors should be calculated against the RSMeans Bare Cost, using the zip code of the project location.

Custom inputs not contained in the RSMeans database can be included as Non-scheduled items

SA

M

PL

E

O N

LY

LeeAWhite Typewritten Text RSMeans

LeeAWhite Typewritten Text Bare

LeeAWhite Typewritten Text Cost

LeeAWhite Stamp

Include on Proposal • Division line number

• Description of what is included in the line item

• Quantity

• Unit of measure

• Total Material cost

• Total Labor cost

• Total Material +

Labor

• Contractor’s divisional factor

• General Contractor’s totals by division

Note: The RSMeans factors which are initially proposed for the basic IDIQ should be used in the hypothetical project price proposal(s), even if the RSMeans factors are later changed through discussions.

SA

M

PL

E

O N

LY

LeeAWhite Typewritten Text RSMeans

LeeAWhite Typewritten Text Bare

LeeAWhite Typewritten Text Cost

LeeAWhite Stamp

LeeAWhite Rectangle

Rectangle

SAMPLE ONLY

Stamp

LeeAWhite Typewritten Text See explanatory notes on next page