46-Sec 01 26 73 - BITUMINOUS MATERIAL PRICE ADJUSTMENT.pdf

PDF 123 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for bituminous material price adjustment provisions issued by the Pennsylvania Department of Transportation (PennDOT) for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program. The specification applies to projects utilizing more than 100 tons of asphalt cement in bituminous materials placed according to PennDOT Publication 408, Section 110.04. The price adjustment mechanism covers all bituminous materials specified for placement, including asphalt cement residue contained in emulsions or cut backs. The project encompasses milling, base repair, leveling courses, manhole rim adjustments, inlet design and replacements, wearing courses along various roads within Bristol Township, and ADA/PennDOT compliant curb ramp installations with associated sidewalks, curbing, utility adjustments, and sign work, with specific quantities defined in the project exhibits.

The price adjustment formula is based on a monthly index price for asphalt cement (PG 64S-22) compiled from producers serving Pennsylvania's eastern region, with no adjustment made when the ratio of current to baseline price falls between 0.90 and 1.10. When the ratio falls below 0.90, the Owner receives an automatic price rebate; when it exceeds 1.10, the Contractor receives a price increase. Both adjustments are calculated using the quantity of bitumen in the placed mixture and the baseline index price from the proposal. Equivalent tonnage calculations vary based on whether materials are placed on a square yard, gallons per square yard, or gallon basis, with design specifications obtained from approved Job Mix Formula reports. Cumulative price adjustments under $500 are disregarded, though partial payments may be made if unpaid accrued increases exceed $10,000 or annually. The Owner retains the right to inspect Contractor and subcontractor records for asphalt cement pricing verification, and no price adjustment applies to extra work unless specifically approved.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BITUMINOUS MATERIAL PRICE ADJUSTMENT

01 26 73-1

SECTION 01 26 73

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. These requirements provide for a price adjustment, in the form of a payment to Contractor or a rebate to Owner, for fluctuations in the cost of asphalt cement used in the bituminous materials placed as part of the construction work specified in PennDOT Publication 408, Section 110.04. Applicable contract items include any bituminous materials specified in Section 110.04 of Publication 408.

B. These price adjustment provisions apply only to projects where more than 100 tons of asphalt cement, including asphalt cement residue contained in emulsions or cut backs, will be used in the bituminous materials specified or indicated for placement. The Pennsylvania Department of Transportation posts monthly index prices for asphalt cement (PG 64S-22) using price data obtained, on the last Wednesday of the preceding month, from a survey of producers who do business in Pennsylvania. Data provided by producers serving the eastern portion of the state is averaged to compute the index price for Zone 1 (Districts 3-0, 4-0, 5-0, 6-0, and 8-0).

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01 PRICE ADJUSTMENT CRITERIA AND CONDITIONS

A. No Price Adjustment

1. When the ratio IP/IB falls within the range of 0.90 to 1.10, no price adjustment will be made for any bituminous material placed during the relevant month.

B. Price Rebate

1. When the ratio IP/IB is calculated to be less than 0.90, Owner will receive an automatic price rebate determined according to the following formula:

P.R. = (0.90 – IP/IB) (Q) (IB) where:

P.R. = Price Rebate IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed

C. Price Increase

1. When the ratio IP/IB is calculated to be greater than 1.10, Contractor will receive a price increase determined according to the following formula:

P.I. = (IP/IB – 1.10) (Q) (IB) where:

P.I. = Price Increase IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed

D. Equivalent Tonnage.

1. Square Yard Basis. For bituminous mixtures placed on a square yard basis, the equivalent tonnage is computed as follows:

Bituminous Mixture Tonnage Placed = (0.000375) (A) (D) (d) where:

A = Surface Area (square yards) D = Design Depth (inches) d = Design Density* (pounds per cubic feet)

01 26 73-2

• The Design Density will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Design Density will be the “Lab Density” listed on the applicable JMF. The Design Density (i.e. Lab Density) obtained from Form TR-448A will be converted to the proper units by multiplying by the density of water,

62.4 pounds per cubic foot.

• ** The Percent Bitumen will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Percent Bitumen will be the “Virgin AC%” listed on the applicable JMF.

2. Gallons per Square Yard Basis. For bituminous material placed on a gallons per square yard basis according to specification, and residue content according to Bulletin 25, the equivalent tonnage is computed as follows:

Bitumen Tonnage = (0.004164) (A) (a) (g) where:

A = Surface Area (square yards) a = Actual Residue Application Rate (gallons per square yard) g = Specific Gravity of Bituminous Material

3. Gallon Basis. For bituminous material placed on a gallon basis, the equivalent tonnage is computed as follows:

Bitumen Tonnage = (0.004164) (g) (p) (No. of gallons) where:

g = Specific Gravity of Bituminous Material p = % Asphalt in Emulsion

E. Expiration of Contract Time.

1. If bituminous materials or mixtures are placed after expiration of contract time and liquidated damages are chargeable, the value for IP used to compute the price adjustment will be either the price index at the time of actual placement or the price index at the time contract time expired, whichever is less.

F. Approval.

1. Should the price index at time of placement, IP, indicate an increase of 50% or more over the price index in the proposal, IB, do not furnish bituminous material for the project without prior written approval.

G. Payment/Rebate.

1. The price adjustment will be paid, or rebated, upon approval of a work order to be prepared after completion of all work. Cumulative price adjustments amounting to less than $500 will be disregarded. Upon written request by Contractor, partial payments may be made, before total completion, when the unpaid accrued price increase exceeds $10,000 or once every 12 months.

H. Inspection of Records.

1. Owner reserves the right to inspect the records of Contractor and its subcontractors and material suppliers to ascertain actual pricing and cost information for the asphalt cement used in the bituminous materials incorporated in the work.

I. Extra Work.

1. If applicable items of work, as specified herein, are added to the contract as extra work, no price adjustment will be made for fluctuations in the cost of asphalt cement used in any bituminous materials placed in the performance of the extra work, unless otherwise approved.

END OF SECTION