This is a technical specification document for bituminous material price adjustment provisions issued by the Pennsylvania Department of Transportation (PennDOT) for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program. The specification applies to projects utilizing more than 100 tons of asphalt cement in bituminous materials placed according to PennDOT Publication 408, Section 110.04. The price adjustment mechanism covers all bituminous materials specified for placement, including asphalt cement residue contained in emulsions or cut backs. The project encompasses milling, base repair, leveling courses, manhole rim adjustments, inlet design and replacements, wearing courses along various roads within Bristol Township, and ADA/PennDOT compliant curb ramp installations with associated sidewalks, curbing, utility adjustments, and sign work, with specific quantities defined in the project exhibits.
The price adjustment formula is based on a monthly index price for asphalt cement (PG 64S-22) compiled from producers serving Pennsylvania's eastern region, with no adjustment made when the ratio of current to baseline price falls between 0.90 and 1.10. When the ratio falls below 0.90, the Owner receives an automatic price rebate; when it exceeds 1.10, the Contractor receives a price increase. Both adjustments are calculated using the quantity of bitumen in the placed mixture and the baseline index price from the proposal. Equivalent tonnage calculations vary based on whether materials are placed on a square yard, gallons per square yard, or gallon basis, with design specifications obtained from approved Job Mix Formula reports. Cumulative price adjustments under $500 are disregarded, though partial payments may be made if unpaid accrued increases exceed $10,000 or annually. The Owner retains the right to inspect Contractor and subcontractor records for asphalt cement pricing verification, and no price adjustment applies to extra work unless specifically approved.
View the file
Other files
Show 40 more
Latest 50 of 75 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BITUMINOUS MATERIAL PRICE ADJUSTMENT
01 26 73-1
SECTION 01 26 73
PART 1 GENERAL
1.01 DESCRIPTION OF WORK
A. These requirements provide for a price adjustment, in the form of a payment to Contractor or a rebate to Owner, for fluctuations in the cost of asphalt cement used in the bituminous materials placed as part of the construction work specified in PennDOT Publication 408, Section 110.04. Applicable contract items include any bituminous materials specified in Section 110.04 of Publication 408.
B. These price adjustment provisions apply only to projects where more than 100 tons of asphalt cement, including asphalt cement residue contained in emulsions or cut backs, will be used in the bituminous materials specified or indicated for placement. The Pennsylvania Department of Transportation posts monthly index prices for asphalt cement (PG 64S-22) using price data obtained, on the last Wednesday of the preceding month, from a survey of producers who do business in Pennsylvania. Data provided by producers serving the eastern portion of the state is averaged to compute the index price for Zone 1 (Districts 3-0, 4-0, 5-0, 6-0, and 8-0).
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 PRICE ADJUSTMENT CRITERIA AND CONDITIONS
A. No Price Adjustment
1. When the ratio IP/IB falls within the range of 0.90 to 1.10, no price adjustment will be made for any bituminous material placed during the relevant month.
B. Price Rebate
1. When the ratio IP/IB is calculated to be less than 0.90, Owner will receive an automatic price rebate determined according to the following formula:
P.R. = (0.90 – IP/IB) (Q) (IB) where:
P.R. = Price Rebate IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed
C. Price Increase
1. When the ratio IP/IB is calculated to be greater than 1.10, Contractor will receive a price increase determined according to the following formula:
P.I. = (IP/IB – 1.10) (Q) (IB) where:
P.I. = Price Increase IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed
D. Equivalent Tonnage.
1. Square Yard Basis. For bituminous mixtures placed on a square yard basis, the equivalent tonnage is computed as follows:
Bituminous Mixture Tonnage Placed = (0.000375) (A) (D) (d) where:
A = Surface Area (square yards) D = Design Depth (inches) d = Design Density* (pounds per cubic feet)
01 26 73-2
• The Design Density will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Design Density will be the “Lab Density” listed on the applicable JMF. The Design Density (i.e. Lab Density) obtained from Form TR-448A will be converted to the proper units by multiplying by the density of water,
62.4 pounds per cubic foot.
• ** The Percent Bitumen will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Percent Bitumen will be the “Virgin AC%” listed on the applicable JMF.
2. Gallons per Square Yard Basis. For bituminous material placed on a gallons per square yard basis according to specification, and residue content according to Bulletin 25, the equivalent tonnage is computed as follows:
Bitumen Tonnage = (0.004164) (A) (a) (g) where:
A = Surface Area (square yards) a = Actual Residue Application Rate (gallons per square yard) g = Specific Gravity of Bituminous Material
3. Gallon Basis. For bituminous material placed on a gallon basis, the equivalent tonnage is computed as follows:
Bitumen Tonnage = (0.004164) (g) (p) (No. of gallons) where:
g = Specific Gravity of Bituminous Material p = % Asphalt in Emulsion
E. Expiration of Contract Time.
1. If bituminous materials or mixtures are placed after expiration of contract time and liquidated damages are chargeable, the value for IP used to compute the price adjustment will be either the price index at the time of actual placement or the price index at the time contract time expired, whichever is less.
F. Approval.
1. Should the price index at time of placement, IP, indicate an increase of 50% or more over the price index in the proposal, IB, do not furnish bituminous material for the project without prior written approval.
G. Payment/Rebate.
1. The price adjustment will be paid, or rebated, upon approval of a work order to be prepared after completion of all work. Cumulative price adjustments amounting to less than $500 will be disregarded. Upon written request by Contractor, partial payments may be made, before total completion, when the unpaid accrued price increase exceeds $10,000 or once every 12 months.
H. Inspection of Records.
1. Owner reserves the right to inspect the records of Contractor and its subcontractors and material suppliers to ascertain actual pricing and cost information for the asphalt cement used in the bituminous materials incorporated in the work.
I. Extra Work.
1. If applicable items of work, as specified herein, are added to the contract as extra work, no price adjustment will be made for fluctuations in the cost of asphalt cement used in any bituminous materials placed in the performance of the extra work, unless otherwise approved.
END OF SECTION