43-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf
PDF 90 KB Posted
- Solicitation number
- Not on record
- Issued by
- Bucks County, Pennsylvania
About this file
This is a Narrative Construction Schedule specification document for Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification outlines the contractor's requirement to prepare, maintain, and revise a detailed construction project schedule that monitors progress and duration of project operations. The contractor must submit an initial schedule prior to construction commencement, based on the anticipated Notice to Proceed Date, which outlines the anticipated start dates for milling and paving operations for both base bid and alternate bid roadway work. The schedule submission must include minimum requirements such as activity descriptions and locations, duration in working days, start and finish calendar dates, and a workday calendar indicating work days and non-work days, number of shifts per day, and hours per shift. The schedule must demonstrate necessary interdependencies through sufficient activity detail and be accompanied by a narrative description. The Engineer will review and respond to the detailed schedule and supporting documentation within ten calendar days of receipt.
Owner may elect to withhold progress payments until an acceptable schedule is submitted and approved. If the contractor fails to submit the schedule prior to construction start, the contractor will be required to attend a scheduling meeting to prepare an acceptable schedule, with the Owner retaining the right to withhold progress payments until scheduling is completed. This scheduling requirement applies to all phases of work including milling, base repair, leveling course, manhole rim adjustments, inlet design and replacements, wearing course work, and ADA/PennDOT compliant curb ramp installation with associated sidewalks, curbing, utility adjustments, and sign work, all in accordance with PennDOT Publication 408 and Township Standards.
View the file
Other files
Show 40 more
Latest 50 of 75 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NARRATIVE CONSTRUCTION SCHEDULE
01 32 16-1
SECTION 01 32 16
NARRATIVE CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work Of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date of milling and paving operations for each base bid and alternate bid roadway prior to the start of construction. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
Activity description & location;
Duration of activity, in working days; and Start and finish calendar dates of activities.
D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION