3819P22114A09_c1v1_FY26_TGI.pdf
PDF 104 KB Posted
- Solicitation number
- N6264925RA059-0008
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 05-MAR-2025, focused on replacing the furnace light and camera wall box assembly of the 1A Boiler Boiler Combustion Monitoring System (BCMS). The task involves removing existing castable refractory and wall box assemblies, and installing new components in the Fire Room, with specific requirements for materials including carbon steel wall box assemblies, castable refractory, and gaskets. The work is scheduled to start on 7/21/2026 and complete by 11/21/2027, with the South Regional Maintenance Center (SRF-JRMC) providing government-furnished material and services such as crane rigging, utility services, safety inspections, and on-site support. The instruction includes detailed technical specifications, material references, and notes on potential hazards like asbestos and lead.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
05-MAR-2025 1008
20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR BCMS AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: (BIRMIS) F/O – REPLACE FURNACE LIGHT AND CAMERA WALL BOX ASSY OF 1A BOILER BCMS
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 5
EM02L194
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
SOEJIMA, DAISUKE 234 3152434480 27-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
IZUMI, NORIAKI 234 3152432243 05-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM02-L194
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
221A1114
1. SCOPE/PURPOSE:
1.1 Title: Furnace Light and Furnace Camera Wall Box Assembly of 1A Boiler Boiler Combustion Monitoring System (BCMS);
replace
1.2 Location of Work:
1.2.1 Fire Room (8-76-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), Boiler, Main Propulsion, 1A
Mfr: Foster Wheeler Corp Mfr ID: N/A Design Pressure: 705 PSIG Max Operating Pressure: 655 PSIG
APL: 021550096
TGI Short Form
05-MAR-2025 1008
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR BCMS AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: (BIRMIS) F/O – REPLACE FURNACE LIGHT AND CAMERA WALL BOX ASSY OF 1A BOILER BCMS
FOUO Pg 2 of 5
CU PHASE DESCRIPTION (Cont.)
1.3.1.1 Quantity (One EA), Wall Box Assembly, Furnace Light, BCMS, 1A Boiler Casing Material: Carbon Steel, ASTM A-36, 0.1875 Inch Thickness Wall Box Mounting Plate Material: Carbon Steel, ASTM A-36, 0.1875 Inch Thickness Remarks: See Ref. No. 3 for details
1.3.1.2 Quantity (One EA), Wall Box Assembly, Furnace Camera, BCMS, 1A Boiler Casing Material: Carbon Steel, ASTM A-36, 0.1875 Inch Thickness Wall Box Mounting Plate Material: Carbon Steel, ASTM A-36, 0.1875 Inch Thickness Remarks: See Ref. No. 3 for details
1.3.2 Quantity (10 SF), Castable Refractory, Wall Box Tube, 1A Boiler Material: Castable Refractory, Fireclay Specification: MIL-C-717 See Item No. F-7 of Ref. No. 3
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.5.2 Potential Lead Hazard
1.6 Contractor work start date: 7/21/2026
1.7 Contractor work completion date: 11/21/2027
2 PROCEDURE:
2.1 Remove existing castable refractory listed in 1.3.2, using Ref. No. 3 for guidance.
2.1.1 Contact C106R for disposal of known/suspected radiation substance waste.
2.1.1.1 Ensure radiation substance waste is not mixed with other hazardous/industrial waste.
2.1.1.2 Properly segregate, package, and label all known/suspected radiation substance waste.
2.1.1.3 Accumulate radiation substance waste in compatible 55 gallon drums. 55 gallon drums must be prepared by the contractor and the government must not return the drums after disposal.
2.1.1.4 Contact C106R to request coordination of disposal of accumulated radiation substance waste.
2.2 Remove each existing and install new wall box assembly listed in 1.3.1.1 and 1.3.1.2 with baffle tile to prevent damage in accordance with Ref. No .3 and Ref. No .4, using Ref. No. 5 for guidance.
2.2.1 Fabricate and install new gasket conforming to GRAPH-LOCK 3125SS, MIL-DTL-24696.
2.2.2 Accomplish the requirements of 009-12 of Ref. No. One, including Table 2, Column A, Lines One through 7.
05-MAR-2025 1008
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR BCMS AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: (BIRMIS) F/O – REPLACE FURNACE LIGHT AND CAMERA WALL BOX ASSY OF 1A BOILER BCMS
FOUO Pg 3 of 5
CU PHASE DESCRIPTION (Cont.)
2.3 Install each new castable refractory listed in 1.3.2, using Ref. No. 3 for guidance
2.4 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.5 Notes:
2.5.1 Planner: Code 234 D.SOEJIMA, 243-2242
Planner: Code 234 M.HOSODA, 243-4572 Planner: Code 233 K.UCHIMURA, 080-9350-1432
2.5.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598.
2.5.3 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1A Boiler report dated 17 OCT 2024, Line items “C-09 and D64I-01”.
2.5.4 Removal and installation boiler outer casing exterior insulation and lagging will be covered by TGI No. 3819P22101A01.
(KTR TGI)
2.5.5 Asbestos abatement work of outer casing will be covered by TGI No. 3819P22103A01. (KTR TGI)
2.5.6 JCN EM02-L194 is related to this TGI.
2.6 Government Furnished Material (GFM):
2.6.1 SRF-JRMC will provide GFM listed in the Material List.
2.7 SRF-JRMC will provide the following service work: (TGI No. 3819P22114S10)
2.7.1 [C740] Crane and crane rigging service.
2.7.2 [X99E] Utility service, electrical.
2.7.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.7.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.7.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.7.6 [C281] Provide on-sight support for 1A boiler repair work.
2.7.7 [C133] QA inspection for (G) symbol(s).
05-MAR-2025 1008
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR BCMS AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: (BIRMIS) F/O – REPLACE FURNACE LIGHT AND CAMERA WALL BOX ASSY OF 1A BOILER BCMS
FOUO Pg 4 of 5
OTHER SPECIAL REQUIREMENTS:
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 LI FY-25 Local Standard Items - ORG N 2 NSI FY-25 NAVSEA Standard Items - ORG N
3 DWG 200-8468764 BOILER COMBUSTION
MONITORING SYSTEM
(BCMS) BOILER
MODIFICATIONS
- Y ALL
4 TM S9221-DT-MMO-
BOILER COMBUSTION
MONITORING SYSTEM,
BCMS
2 N
5 TM S9086-GY-STM-
010/CH-221
Boilers 8 N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 INSL HRs 22/KE PC N
2.2 BLRM HRs, WELD HRs, INSL HRs, ELEC HRs, RGRS HRs, PNTR
HRs, QA HRs
22/KE PC N
2.3 INSL HRs 22/KE PC N
2.4 PNTR HRs, QA HRs 22/KE PC N
Boiler Work CFM for marine chemist cost, fire watch cost, lead sampling/analysis cost, and misc such as electrode, saw blades, wheel, gases, fastener, painting material, plastic bag/sheet and other consumable.
22/MQ CS N
Lagging Work CFM for asbestos sampler and analysis cost, paint, tyvek suit, gallon drum, enclosing/covering materials and other consumable.
22/MQ CS N
Electrical Work CFM for fasteners, insulation tape, plastic bags, and other consumable.
22/MQ CS N
Process Funding Document 10/CT OM N
Version-1: Change to correct revision of Ref. No. 3 [C234 N.Izumi, 03/05/2025] -/-/N.
/ V-01 N
MATERIAL LIST
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
1 8468764
ICN: 3819P22114 KEY OP: A09
05-MAR-2025 1008
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1A BLR BCMS AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: (BIRMIS) F/O – REPLACE FURNACE LIGHT AND CAMERA WALL BOX ASSY OF 1A BOILER BCMS
FOUO Pg 5 of 5
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 F-9 1 M WALL BOX ASSEMBLY, WALL
BOX ASSEMBLY MOUNTINGS
FURNACE LENS LENGTH:
914MM/36 INCHES
VIEWING DIRECTION: DIRECT
MATERIAL: CARBON STEEL
DWG: 200-8468764 REV"-"
ITEM NO. F-9 AND F-10
MFR P/N: 6515A36-900
C-234, D.SOEJIMA 243-4480
ORDERED FOR KTR
9B NA 4 N 2/EA
002 M PLATE,METAL, C234
D.SOEJIMA 243-4480
ORDER FOR KTR
PLATE METAL, ASTM-A36
6' X 10' X 3/16"
9B 9515 002671176 NA 4 N 50525046 1/PM
003 M PLATE,METAL, C234
D.SOEJIMA 243-4480
ORDER FOR KTR
PLATE,METAL, 7FTX10FT X 1/4
THK
9B 9515 009526280 NA 4 N 50525064 1/PM
004 M GASKET MATERIAL,SHE,
ORIG: C234 D.SOEJIMA, 243-
ORDERED FOR KTR
9B 5330 015287656 NA 4 N 50525115 1/SH
100 M CASTABLE MIX,REFRAC,
CASTABLE REFRACTORY,
DENSE HIGH ALUMINAM
MATERIAL, (60% AL203),
CONVENTIONAL, 3000
DEGREE F,
BRAND NAME: MIZZOU
CASTABLE, SPEC: MIL-C-717,
CASTABLE SHALL BE PACKED
IN SEALED PLASTIC
CONTAINER(55LB), CASTABLE
PACKED IN PAPER BAG IS
NOT ACCEPTABLE,
ORIG: C234 M. HOSODA, 243-
ORDERED FOR KTR
9B TAHO 001536816 NA 4 Y 50435161 4/DR
101 M CEMENT,INSULATION,H, HIGH
TEMP CEMENT
ORIG: C234 M. HOSODA, 243-
ORDERED FOR KTR
9B 5640 002722995 NA 4 Y 50435168 2/BG
103 M CASTABLE MIX,REFRAC, FC-
ORIG: C234 M. HOSODA, 243-
ORDERED FOR KTR
9B HOLD 007891749 NA 4 Y 50435157 1/DR
104 M MORTAR,REFRACTORY,
MORTAR, DRY, MIL-M-15842
CLASS-1, 55LB/BG,
ORIT: C234 M. HOSODA, 243-
ORDERED FOR KTR
9B HOLD 001536811 NA 4 Y 50455570 2/BG