This document contains an amendment to an invitation for bid for facility renovation, improvements, and repairs at the Long Island National Cemetery. The amendment provides responses to contractor questions, clarifying that 300 inlet structures, 300 infiltration vaults, and 50 manholes require jetting and vacuuming, totaling approximately 400 cubic yards of material disposal. Additionally, 2,400 linear feet of storm pipe will require jetting. Low voltage equipment is to be provided by the mechanical contractor. The existing fire alarm monitoring company is identified. The opportunity remains available through the Department of Veterans Affairs National Cemetery Administration, with bids due on February 23, 2024.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 6
A0004
815CM3041
36C786
Department of Veterans Affairs
National Cemetery Administration
Contracting Services
18434 Joplin Road
Triangle VA 22172
36C786
Department of Veterans Affairs
National Cemetery Administration
Contracting Services
18434 Joplin Road
Triangle VA 22172
To all Offerors/Bidders
36C78624B0005
02-13-2024
A0004
X
X
** HOUR & DATE for Receipt of Offers is EXTENDED to:
X 1
AMENDMENT (A0004) | Long Island National Cemetery | Facility Renovation, Improvements & Repairs | Project #815CM3041
The Purpose of Amendment (A0004) is to Notify the Public of the Government's Responses to RFI #04.
1.) The Virtual Bid Opening Date & Time is still 23 February 2024 @ 1300; (1:00 P.M.) EST
NOTE: Please See Attachments for Content
**All Factors & Content of This IFB Solicitations remains the Same**
Sheryl Palacio-Davis
Contracting Officer
A.1 AMENDMENT A0004 FOR IFB SOLICITATION DESCRIPTION FOR
LONG ISLAND NATIONAL CEMETERY
AMENDMENT (A0004), IS THE GOVERNMENT’S RESPONSES TO BOTH
RFI #04
PROJECT LOCATION: LONG ISLAND NATIONAL CEMETERY
Long Island National Cemetery
2040 Wellwood Avenue
Farmingdale, New York, 11735
PROJECT TITLE: Facility Renovation, Improvements, and Repairs
PROJECT NUMBER: 815CM3041
STATEMENT OF WORK SUMMARY:
▪ Contractor shall furnish all tools, labor, materials, equipment, and professional supervision to perform work described in the Statement of Work (SOW), Specification & Drawings, for the Facility Renovation, Improvements, and Repairs, located at the Long Island National
Cemetery, NY.
▪ Suffolk County) in the State of New York.
CONTINUATION PAGE
AMENDMENT A0004: Is the Government’s Responses to
RFI #4
LONG ISLAND NATIONAL CEMETERY | IFB Solicitation No. 36C78624B0005 | Project No.
815CM3041 | Facility Renovation, Improvements, and Repairs.
▪ CEMETERY’S ADDRESS:
Long Island National Cemetery 2040 Wellwood Avenue Farmingdale, New York, 11735
1 Scope 14 – The attached scope states to jet/vacuum all curb inlets, pipes and infiltration vaults. The existing catch basin, piping and vaults are not clearly identified on the plans and in order to bid for this to be a fair bid it should not be left open to interpretation. Please provide a total amount of structures that require cleaning, a total LF of piping, and a total amount of “infiltration vaults”.
300 – 3’x3’ inlet structures to be jetted and vacuumed with a total of 100 cubic yards of material to be disposed of. Material can be dumped in spoils area at the cemetery.
300 – 8’ diameter infiltration vaults to be jetted and vacuumed with a total of 280 cubic yards of material to be disposed of. Material can be dumped in spoils area at the cemetery.
50 – 4’ diameter man holes to be jetted and vacuumed with a total of 25 cubic yards of material to be disposed of. Material can be dumped in spoils area at the cemetery.
2,400 total linear feet of storm pipe to be jetted.
Contractor is to assume the quantities above for their construction cost proposal.
Proposal shall clearly indicate unit costs for this work which will include general contractor’s costs/overhead and profit markups. Quantities to be verified by contractor during construction operations, contract modifications may be required based on actual work required/completed.
2 “Infiltration Vaults” – please provide more detail. What is the size of the existing vaults and how many are there? At the site there is no way to access such vaults and this information is crucial to estimating the amount of disposal of material required to be removed.
See answer to question 1 above.
3 Project Manual, General Requirements, Page 20, Section D: Irrigation Wells – This section of the spec book asks that the work involving the Irrigation Well be subdivided into 27 different line item costs. There is nothing shown on the actual bid sheets showing these line items separated. Are we required to provide this breakdown? If we are required to include this breakdown, does failing to provide the breakdown disqualify the bid? Please advise.
Cost detail required for this high cost work to ensure well driller qualification and all associated work is included in the cost proposal, See Specification section 01 00 02, paragraph 1.2-A.1.d.
4 The drawings call for a tie into the existing fire alarm system but don’t specify what that existing system is. Could you provide a name & contact info?
The fire monitoring company is Secure it Securities Corp.
10 Yorkshire Dr Suffern, NY 10901 Office: (845) 445-6444
5 Is the low-voltage equipment provided by the electrical contractor or a separate vendor for security or telecom? We will need the manufacturer and catalog numbers to provide a quote if we are providing it, as they are not listed in the drawings/spec There are the attached pages we are referring to; we need to know “Is the electrical contractor providing the low voltage equipment or is that by a separate security, telecom vendor? If we are providing, the drawings/specs don’t list a manufacturer or catalog numbers. We will need this info to quote.”
From Sheet M-100, question refers to
“LOW VOLTAGE INDOOR UNIT” referenced below is referring to the indoor (evaporator) ductless split system unit. This shall be provided and installed by the mechanical contractor. The manufacturer is scheduled as Daikin with approved equals listed in the General Notes of the schedule.
From Sheet E-001, Question refers to
“LOW VOLTAGE” referenced below is part of the legend for the switch modifiers clarifying the type of switches that are used for controlling lighting fixtures.
However, all controls for lighting fixtures in the project are line voltage.
From Sheet E-001, Question also refers to
“LOW-VOLTAGE” referenced below refers to circuit breakers that are rated for
600V or less. However, this project has no electronic circuit breakers requiring adjustment and this general note does not apply.
NOTE: Please see attachment.
A.2 OTHER ATTACHMENTS
See attached document: RFI 04 - Long Island National Cemetery - FY-24.
END OF DOCUMENT