This solicitation describes a construction project. The Department of Veterans Affairs National Cemetery Administration is seeking a contractor to perform Facility Renovation, Improvements, and Repairs at the Long Island National Cemetery in Farmingdale, New York. The project scope includes committal service shelter renovations, public restroom restoration, columbarium plaza repairs, irrigation well installation, pump house renovation, signage demolition and repairs, monument demolition and repairs, flower station demolition and repairs, maintenance building renovations, public information center work, cortege lane repairs, bronze plaque restoration, and director's lodge renovations. The contractor will furnish all labor, materials, equipment, and supervision to complete the work described in the specification and drawings by the specified completion date.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Issued for Construction
LONG ISLAND NATIONAL CEMETERY
Facil ity Renovation Project Number 815CM3041
Final Construction Documents
May 22, 2023
Prime Consultant:
Walker Federal Services, LLC
Subconsultants:
Charlotte Engineers Principal Engineering, Inc.
Hydro Designs, Inc.
ECS Mid−Atlantic, LLC
R&R Construction Services, Inc.
WFS
Long Island National Cemetery Final Construction Documents
Facility Renovation May 22, 2023
815CM3041 ISSUED FOR CONSTRUCTION
SIGNATURE PAGE 1
SIGNATURE PAGE
Architecture
Walker Federal Services, LLC.
I, Fan Wang, hereby certify that the following documents were prepared by me or under my direct supervision, and that I am a duly licensed Professional
Engineer under the laws of the State of New York: 04 05 31, 05 50 00, 06 10
00, 06 20 00, 07 22 00, 07 31 13, 07 31 26, 07 71 00, 07 72 00, 07 92 00, 08
11 13, 08 14 00, 08 41 13, 08 71 00, 08 80 00, 09 06 00, 09 22 16, 09 29 00, 09 51 00, 09 65 13, 09 65 19, 09 68 00, 09 91 00, 10 21 13, 10 28 00, 10 44
13, 12 24 00
MEP Engineering
Charlotte Engineers
I, John Callahan, Jr. , hereby certify that the following documents were prepared by me or under my direct supervision, and that I am a duly licensed
Professional Engineer under the laws of the State of New York: 22 05 11, 22
05 12, 22 05 19, 22 05 23, 22 05 33, 22 07 11, 22 11 00, 22 13 00, 22 34 00, 22 40 00, 23 05 11, 23 05 12, 23 05 41, 23 05 93, 23 07 11, 23 09 23, 23 11
23, 23 23 00, 23 31 00, 23 34 00, 23 37 00, 23 81 00, 23 81 43, 23 82 39, 23
83 23, 26 05 11, 26 05 19, 26 05 26, 26 05 33, 26 05 41, 26 05 73, 26 08 00, 26 22 00, 26 24 13, 26 24 16, 26 27 26, 26 29 11, 26 29 21, 26 41 00, 26 51
00, 26 56 00, 27 05 00, 27 05 26, 27 05 33, 27 08 00, 27 10 00, 27 11 00, 27
51 23, 28 05 00, 28 05 13, 28 05 26, 28 05 28.33, 28 08 00, 28 23 00, 28 31 00
Civil, Structural Engineering, Landscape Architecture
Principal Engineering, Inc.
I, Andre C. Monnot, hereby certify that the following documents were prepared by me or under my direct supervision, and that I am a duly licensed
Professional Engineer under the laws of the State of New York: 01 00 02, 01
32 16.13, 01 33 23, 01 42 19, 01 45 29, 01 56 39, 01 57 19, 01 74 19, 01 81
13, 02 41 00, 03 30 53, 10 14 00, 31 20 00, 32 05 23, 32 12 16, 32 13 90, 32
17 10, 32 31 19, 32 33 00, 32 90 00
Irrigation Consulting
Hydro Designs, Inc.
I, Michael Krones, hereby certify that the following documents were prepared by me or under my direct supervision: 33 10 00, 33 21 00
-This page intentionally left blank-
TABLE OF CONTENTS 00 01 10 - 1
SECTION 00 01 10 - TABLE OF CONTENTS
00 00 00 Cover Page
00 00 01 Signature Page
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets
01 00 02 General Requirements
01 32 16.13 Network Analysis Schedules
01 33 23 Shop Drawings, Product Data, and Samples
01 42 19 Reference Standards
01 45 29 Testing Laboratory Services
01 56 39 Temporary Tree and Plant Protection
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management
01 81 13 Sustainable Construction Requirements
02 41 00 Demolition and Site Clearing
02 82 11 Traditional Asbestos Abatement
02 82 13.31 Asbestos Transite-type Abatement
02 83 33.13 Lead-Based Paint Removal
03 05 00 Integral Waterproofing of Concrete
03 30 53 Cast-In-Place Concrete - Short Form
03 90 00 Concrete Restoration and Cleaning
04 03 10 Historic Masonry Cleaning
04 03 22 Historic Brick Unit Masonry Repair
04 03 23 Historic Brick Unit Masonry Repointing
04 20 00 Unit Masonry
04 43 00 Natural Stone Veneer
04 72 00 Cast Stone Masonry
05 03 72 Historic Decorative Metal Repair
05 50 00 Metal Fabrications
05 51 20 Aluminum Metal Canopy and Railings
05 73 00 Decorative Metal Railings
06 03 12 Historic Wood Repair
06 10 00 Rough Carpentry
06 15 33 Wood Patio Decking
TABLE OF CONTENTS 00 01 10 - 2
06 20 00 Finish Carpentry
07 01 50.19 Preparation for Reroofing
07 21 00 Thermal Insulation
07 31 13 Asphalt Shingles
07 31 26 Slate Shingles
07 60 00 Flashing and Sheet Metal
07 72 00 Roof Accessories
07 72 53 Snow Guards
07 92 00 Joint Sealants
08 03 14 Historic Treatment of Wood Doors
08 11 13 Hollow Metal Doors and Frames
08 14 00 Interior Wood Doors
08 33 23 Overhead Coiling Doors
08 41 13 Aluminum Framed Entrances and Storefronts
08 52 00 Wood Windows
08 71 00 Door Hardware
08 80 00 Glazing
08 90 00 Louvers and Vents
09 22 16 Non Structural Metal Framing
09 29 00 Gypsum Board
09 30 13 Ceramic Tiling
09 51 00 Acoustical Ceiling
09 65 13 Resilient Base and Accessories
09 65 19 Resilient Tile Flooring
09 91 00 Painting
10 14 00 Exterior Signage
10 14 05 Interior Signage
10 21 13 Toilet Compartments
10 28 00 Toilet and Bath Accessories
10 44 13 Fire Extinguisher Cabinets
10 56 13 Steel Shelving
12 24 00 Window Shades
12 36 61.16 Solid Surface Countertops
22 05 11 Common Work Results for Plumbing
22 05 12 General Motor Requirements for Plumbing Equipment
TABLE OF CONTENTS 00 01 10 - 3
22 05 19 Meters and Gages for Plumbing Piping
22 05 23 General-Duty Valves for Plumbing Piping
22 05 33 Heat Tracing for Plumbing Piping
22 07 11 Plumbing Insulation
22 11 00 Facility Water Distribution
22 13 00 Facility Sanitary and Vent Piping
22 34 00 Fuel-Fired Domestic Water Heaters
22 40 00 Plumbing Fixtures
23 05 11 Common Work Results for HVAC
23 05 12 General Motor Requirements for HVAC Equipment
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
23 05 93 Testing, Adjusting, and Balancing for HVAC
23 07 11 HVAC Insulation
23 09 23 Direct-Digital Control System for HVAC
23 11 23 Natural Gas
23 23 00 Refrigerant Piping
23 31 00 HVAC Ducts and Casings
23 34 00 HVAC Fans
23 37 00 Air Outlets and Inlets
23 52 25 Low-pressure Water Heating Boilers
23 81 00 Unitary HVAC Equipment
23 81 43 Air-Source Unitary Heat Pumps
23 82 39 Unit Heaters
23 83 23 Radiant Heating Electric Panels
26 05 11 Requirements for Electrical Installations
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33 Raceway and Boxes for Electrical Systems
26 05 41 Underground Electrical Construction
26 05 73 Overcurrent Protective Device Coordination Study
26 22 00 Low-Voltage Transformers
26 24 16 Panelboards
26 27 26 Wiring Devices
26 29 11 Motor Controllers
26 29 21 Enclosed Switches and Circuit Breakers
26 41 00 Facility Lightning Protection
26 51 00 Interior Lighting
26 56 00 Exterior Lighting
TABLE OF CONTENTS 00 01 10 - 4
27 05 00 Common Work Results for Communications
27 05 26 Grounding and Bonding for Communications Systems
27 05 33 Conduits and Backboxes for Communications Systems
27 10 00 Structured Cabling
27 11 00 Communications Equipment Room Fittings
27 51 23 Intercommunication and Program Systems
28 23 00 Video Surveillance
28 31 00 Fire Detection and Alarm
31 20 00 Earth Moving
32 05 23 Cement and Concrete for Exterior Improvements
32 12 16 Asphalt Paving
32 17 10 Pavement Markings
32 13 90 Cast Iron Detectable Warning Plates
32 31 19 Decorative Metal Fences
32 33 00 Site Furnishings
32 90 00 Planting
33 01 10.81 Water Supply Well Abandonment
33 10 00 Water Utilities
33 11 13 Potable Water Supply Wells
33 21 00 Water Supply Well - Pumping & Control
Appendix I Geotechnical Report, May 20, 2022
Appendix II Hazardous Material Survey, July 28, 2021
Appendix III Irrigation Supply Well Desktop Evaluation, January 21, 2022
LIST OF DRAWINGS 00 01 15 - 1
SECTION 00 01 15 - LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
GENERAL
1 GI-101 COVER SHEET
2 GI-102 INDEX OF SHEETS
3 GI-103 GENERAL NOTES
4 GI-104 OVERALL SITE PLAN
5 GI-105 OVERALL SITE PLAN
SITE
SURVEY
6 VF-101 EXISTING CONDITIONS SURVEY
7 VF-102 EXISTING CONDITIONS SURVEY
8 VF-103 EXISTING CONDITIONS SURVEY
9 VF-104 EXISTING CONDITIONS SURVEY
10 VF-105 EXISTING CONDITIONS SURVEY
11 VF-201 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
12 VF-202 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
13 VF-203 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
14 VF-204 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
15 VF-205 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
16 VF-206 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
17 VF-207 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
18 VF-208 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
19 VF-209 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
20 VF-210 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
21 VF-211 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
22 VF-212 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
23 VF-213 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
24 VF-214 EXISTING CONDITIONS SURVEY - ENLARGEMENTS
EROSION AND SEDIMENT CONTROL
25 CE-101 EROSION AND SEDIMENT CONTROL PLAN - CORTEGE LANE
26 CE-201 EROSION AND SEDIMENT CONTROL DETAILS
DEMOLITION
27 CD-101 DEMOLITION PLAN - CORTEGE LANE
28 CD-102 DEMOLITION PLAN
PAVEMENT
29 CP-101 PAVEMENT REPAIR PLAN - NORTH
30 CP-102 PAVEMENT REPAIR PLAN - WEST
31 CP-103 PAVEMENT REPAIR PLAN - EAST
32 CP-104 PAVEMENT REPAIR PLAN - SOUTH WEST
33 CP-105 PAVEMENT REPAIR PLAN - SOUTH EAST
34 CP-201 PAVING PLAN AND PROFILE - CORTEGE LANE
35 CP-202 PAVING PLAN AND SECTION - GATE 5 DRIVE APRON
LIST OF DRAWINGS 00 01 15 - 2
36 CP-301 PAVING DETAILS
37 CP-302 PAVING DETAILS
GRADING AND DRAINAGE
38 CG-101 GRADING AND DRAINAGE PLAN - CORTEGE LANE
39 CG-102 GRADING PLAN - LODGE
40 CG-103 GRADING PLAN - RESTROOM BUILDING
41 CG-104 GRADING PLAN - WATER WELL
STORMWATER MANAGEMENT
42 CS-101 STORMWATER MANAGEMENT PLAN
43 CS-201 STORMWATER MANAGEMENT DETAILS
SITE DEMOLITION
44 LD-101 SITE DEMOLITION PLAN
45 LD-102 SITE DEMOLITION PLAN
46 LD-103 SITE DEMOLITION PLAN
47 LD-104 SITE DEMOLITION PLAN
48 LD-105 SITE DEMOLITION PLAN
49 LD-201 SITE DEMOLITION PHOTOGRAPHS
SITE DEVELOPMENT
50 LS-101 SITE DEVELOPMENT PLAN
51 LS-102 SITE DEVELOPMENT PLAN
52 LS-103 SITE DEVELOPMENT PLAN
53 LS-104 SITE DEVELOPMENT PLAN
54 LS-105 SITE DEVELOPMENT PLAN
55 LS-201 SITE DEVELOPMENT PLAN - SITE SIGNAGE
56 LS-202 SITE DEVELOPMENT PLAN - SITE SIGNAGE
57 LS-203 SITE DEVELOPMENT PLAN - SITE SIGNAGE
58 LS-204 SITE DEVELOPMENT PLAN - SITE SIGNAGE
59 LS-205 SITE DEVELOPMENT PLAN - SITE SIGNAGE
60 LS-301 SITE DEVELOPMENT PLAN - ENLARGEMENTS
61 LS-302 SITE DEVELOPMENT PLAN - ENLARGEMENTS
62 LS-303 SITE DEVELOPMENT PLAN - ENLARGEMENTS
63 LS-304 SITE DEVELOPMENT PLAN - ENLARGEMENTS
64 LS-305 SITE DEVELOPMENT PLAN - ENLARGEMENTS
65 LS-306 SITE DEVELOPMENT PLAN - ENLARGEMENTS
66 LS-307 SITE DEVELOPMENT PLAN - ENLARGEMENTS
67 LS-308 SITE DEVELOPMENT PLAN - ENLARGEMENTS
68 LS-309 SITE DEVELOPMENT PLAN - ENLARGEMENTS
69 LS-310 SITE DEVELOPMENT PLAN - ENLARGEMENTS
70 LS-401 SITE DEVELOPMENT PLAN - DETAILS
71 LS-402 SITE DEVELOPMENT PLAN - DETAILS
72 LS-403 SITE DEVELOPMENT PLAN - DETAILS
73 LS-404 SITE DEVELOPMENT PLAN - DETAILS
74 LS-405 SITE DEVELOPMENT PLAN - DETAILS
75 LS-406 SITE DEVELOPMENT PLAN - DETAILS
76 LS-407 SITE DEVELOPMENT PLAN - DETAILS
77 LS-408 SITE DEVELOPMENT PLAN - DETAILS
LIST OF DRAWINGS 00 01 15 - 3
78 LS-409 SITE DEVELOPMENT PLAN - DETAILS
79 LS-410 SITE DEVELOPMENT PLAN - DETAILS
80 LS-411 SITE DEVELOPMENT PLAN - DETAILS
81 LS-412 SITE DEVELOPMENT PLAN - DETAILS
82 LS-413 SITE DEVELOPMENT PLAN - DETAILS
83 LS-414 SITE DEVELOPMENT PLAN - DETAILS
84 LS-415 SITE DEVELOPMENT PLAN - DETAILS
PLANTING
85 LP-101 PLANTING PLAN
86 LP-201 PLANT DETAILS & PLANT SCHEDULE
IRRIGATION WATER WELL
87 I-101 IRRIGATION WATER WELL - SITE PLAN
88 I-401 IRRIGATION PUMP HOUSE - 1972 MECHANICAL
89 I-501 IRRIGATION WATER WELL - DETAILS
ARCHITECTURAL
GENERAL
90 A-001 ARCHITECTURAL ABBREVIATIONS AND SYMBOLS
91 A-101 BUILDING CODE ANALYSIS AND LIFE SAFETY PLAN: DIRECTOR'S LODGE
92 A-102 BUILDING CODE ANALYSIS AND LIFE SAFETY PLAN: RESTROOM BUILDING
93 A-103 BUILDING CODE ANALYSIS AND LIFE SAFETY PLAN: MAINTENANCE BUILDING
94 A-104 BUILDING CODE ANALYSIS AND LIFE SAFETY PLAN: PUMP HOUSE
95 A-105 BUILDING CODE ANALYSIS AND LIFE SAFETY PLAN: PUBLIC INFORMATION CENTER
DEMOLITION
96 AD-111 DIRECTOR'S LODGE: BASEMENT FLOOR AND CEILING DEMOLITION PLANS
97 AD-112 DIRECTOR'S LODGE: GROUND LEVEL FLOOR AND CEILING DEMOLITION PLANS
98 AD-113 DIRECTOR'S LODGE: SECOND, ATTIC AND ROOF LEVELS DEMOLITION PLANS
99 AD-131 DIRECTOR’S LODGE: SOUTH, EAST, WEST EXTERIOR ELEVATIONS DEMOLITION
100 AD-132 DIRECTOR’S LODGE: NORTH ELEVATION DEMOLITION
101 AD-211 PUBLIC INFORMATION CENTER: FLOOR AND CEILING DEMOLITION PLANS
102 AD-231 PUBLIC INFORMATION CENTER: EXTERIOR ELEVATIONS DEMOLITION
103 AD-311 PUBLIC RESTROOMS: DEMOLITION FLOOR, CEILING & ROOF PLANS
104 AD-331 PUBLIC RESTROOMS: DEMOLITION ELEVATIONS
105 AD-411 MAINTENANCE BUILDING: DEMOLITION FLOOR PLAN
106 AD-412 MAINTENANCE BUILDING: DEMOLITION CEILING PLAN
107 AD-413 MAINTENANCE BUILDING: DEMOLITION ROOF PLAN
108 AD-431 MAINTENANCE BUILDING: DEMOLITION ELEVATIONS
109 AD-511 PUMP HOUSE: DEMOLITION FLOOR AND ROOF PLANS
110 AD-522 PUMP HOUSE: DEMOLITION ELEVATIONS
111 AD-611 COMMITTAL SHELTER A: FLOOR, CEILING AND ROOF DEMOLITION PLANS
112 AD-612 COMMITTAL SHELTER B: FLOOR, CEILING AND ROOF DEMOLITION PLANS
113 AD-631 COMMITTAL SHELTER A: EXTERIOR ELEVATIONS DEMOLITION
114 AD-632 COMMITTAL SHELTER B: EXTERIOR ELEVATIONS DEMOLITION
115 AD-701 COLUMBARIUM PLAZA A: DEMOLITION ELEVATIONS
116 AD-702 COLUMBARIUM PLAZA A: DEMOLITION DETAILS
DIRECTOR'S LODGE
117 AE-111 DIRECTOR'S LODGE: BASEMENT LEVEL FLOOR AND CEILING PLANS
LIST OF DRAWINGS 00 01 15 - 4
118 AE-112 DIRECTOR'S LODGE: GROUND FLOOR PLAN
119 AE-113 DIRECTOR'S LODGE: GROUND LEVEL CEILING PLAN
120 AE-114 DIRECTOR'S LODGE: SECOND & ATTIC LEVEL FLOOR & CEILING PLANS
121 AE-115 DIRECTOR'S LODGE: ENLARGED INTERIOR PLANS AND ELEVATIONS
122 AE-116 DIRECTOR'S LODGE: ENLARGED RAMP DECK PLAN AND ELEVATIONS
123 AE-117 DIRECTOR'S LODGE: DECK AND RAMP DETAILS
124 AE-118 DIRECTOR'S LODGE: STAIR DETAILS
PUBLIC INFORMATION CENTER
125 AE-211 PUBLIC INFORMATION CENTER: BASEMENT AND ROOF PLANS
126 AE-212 PUBLIC INFORMATION CENTER: GROUND LEVEL FLOOR AND CEILING PLANS
127 AE-213 PUBLIC INFORMATION CENTER: FURNITURE AND FINISH PLANS
128 AE-221 PUBLIC INFORMATION CENTER: ENLARGED INTERIOR PLANS AND ELEVATIONS
129 AE-231 PUBLIC INFORMATION CENTER: EXTERIOR ELEVATIONS
130 AE-232 PUBLIC INFORMATION CENTER: EXTERIOR RAMP AND CANOPY ENLARGED PLANS
131 AE-233 PUBLIC INFORMATION CENTER: EXTERIOR RAMP AND CANOPY ENLARGED DETAILS
PUBLIC RESTROOMS
132 AE-311 PUBLIC RESTROOMS: FLOOR PLAN
133 AE-312 PUBLIC RESTROOMS: CEILING, ROOF & FINISH PLANS
134 AE-321 PUBLIC RESTROOMS: INTERIOR ELEVATIONS
135 AE-331 PUBLIC RESTROOMS: EXTERIOR ELEVATIONS
MAINTENANCE BUILDING
136 AE-411 MAINTENANCE BUILDING: FLOOR PLAN
137 AE-421 MAINTENANCE BUILDING: REFLECTED CEILING PLAN
138 AE-422 MAINTENANCE BUILDING: ROOF PLAN
139 AE-423 MAINTENANCE BUILDING: EXTERIOR ELEVATIONS
140 AE-431 MAINTENANCE BUILDING: INTERIOR ELEVATIONS
PUMP HOUSE
141 AE-511 PUMP HOUSE: BASEMENT & GROUND LEVELS FLOOR PLANS
142 AE-512 PUMP HOUSE: ROOF - PLAN, ELEVATIONS & ROOF REPAIR DETAIL
143 AE-521 PUMP HOUSE: BASEMENT & GROUND LEVELS REFLECTED CEILING PLANS
144 AE-531 PUMP HOUSE: EXTERIOR ELEVATIONS
COMMITTAL SERVICE SHELTERS A & B
145 AE-611 COMMITTAL SHELTER A: FLOOR, CEILING AND ROOF PLANS
146 AE-612 COMMITTAL SHELTER B: FLOOR, CEILING AND ROOF PLANS
147 AE-621 COMMITTAL SHELTER A & B: INTERIOR ELEVATIONS
148 AE-622 COMMITTAL SHELTER DETAILS
149 AE-631 COMMITTAL SHELTER A: EXTERIOR ELEVATIONS
150 AE-632 COMMITTAL SHELTER B: EXTERIOR ELEVATIONS
DETAILS
151 AE-800 DETAILS: GENERAL
152 AE-801 DETAILS: GENERAL
153 AE-802 SCHEDULES: DOORS
154 AE-803 SCHEDULES: DOOR & WINDOW DETAILS
155 AE-804 SCHEDULES: PARTITION TYPES AND WINDOW
156 AE-805 SCHEDULES: FINISHES, RESTROOM ACCESSORIES AND EQUIPMENT
FINISH BOARDS
LIST OF DRAWINGS 00 01 15 - 5
157 AE-901 DIRECTOR'S LODGE: BASEMENT FINISHES
158 AE-902 DIRECTOR'S LODGE: GROUND LEVEL FINISHES
159 AE-903 DIRECTOR'S LODGE: BATHROOMS FINISHES
160 AE-904 DIRECTOR'S LODGE: RAMP AND DECK FINISHES
161 AE-905 PUBLIC INFORMATION CENTER: FINISHES
162 AE-906 RESTROOM BUILDING: FINISHES
MECHANICAL
GENERAL
163 M-001 ABBREVIATIONS AND SYMBOLS
164 M-002 MECHANICAL - DETAILS
165 M-100 MECHANICAL SCHEDULES - DIRECTOR'S LODGE
DEMOLITION
166 MD-110 DIRECTOR'S LODGE - BASEMENT LEVEL - EAST - FLOOR PLAN - DEMOLITION
167 MD-111 DIRECTORS LODGE - BASEMENT LEVEL - WEST - FLOOR PLAN - DEMOLITION
168 MD-112 DIRECTORS LODGE - GROUND LEVEL - EAST - FLOOR PLAN - DEMOLITION
169 MD-113 DIRECTORS LODGE - GROUND LEVEL - WEST - FLOOR PLAN - DEMOLITION
170 MD-114 DIRECTORS LODGE - SECOND LEVEL - FLOOR PLAN - DEMOLITION
171 MD-115 DIRECTORS LODGE - ATTIC - FLOOR PLAN - DEMOLITION
172 MD-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - FLOOR PLAN - DEMOLITION
173 MD-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - FLOOR PLAN
174 MD-311 PUBLIC RESTROOMS - FLOOR PLAN - DEMOLITION
175 MD-312 PUBLIC RESTROOMS - ROOF PLAN - MECHANICAL DEMOLITION
176 MD-411 MAINTENANCE BUILDING - FLOOR PLAN - DEMOLITION
177 MD-412 MAINTENANCE BUILDING - ROOF PLAN - DEMOLITION
178 MD-511 PUMP HOUSE - BASEMENT & GROUND LEVEL - FLOOR PLAN - DEMOLITION
HVAC
179 MH-111 DIRECTORS LODGE - BASEMENT LEVEL - FLOOR PLAN - WEST - HVAC
180 MH-112 DIRECTORS LODGE - GROUND LEVEL - FLOOR PLAN - EAST - HVAC
181 MH-113 DIRECTORS LODGE - GROUND LEVEL - FLOOR PLAN - WEST - HVAC
182 MH-114 DIRECTORS LODGE - SECOND LEVEL - FLOOR PLAN - HVAC
183 MH-115 DIRECTORS LODGE - ATTIC LEVEL - FLOOR PLAN - HVAC
184 MH-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - MECHANICAL - HVAC
185 MH-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - FLOOR PLAN - HVAC
186 MH-212 PUBLIC INFORMATION CENTER - ROOF PLAN - HVAC
187 MH-311 PUBLIC RESTROOMS - GROUND LEVEL - FLOOR PLAN - HVAC
188 MH-312 PUBLIC RESTROOMS - ROOF PLAN - HHVAC
189 MH-411 MAINTENANCE BUILDING - GROUND FLOOR - FLOOR PLAN - HVAC
190 MH-412 MAINTENANCE BUILDING - ROOF PLAN - HVAC
191 MH-511 PUMP HOUSE - BASEMENT, GROUND AND ROOF - FLOOR PLAN - HVAC
MECHANICAL PIPING
192 MP-110 DIRECTORS LODGE - BASEMENT LEVEL - FLOOR PLAN - EAST - PIPING
193 MP-111 DIRECTORS LODGE - BASEMENT LEVEL - FLOOR PLAN - WEST - PIPING
194 MP-112 DIRECTORS LODGE - GROUND LEVEL - FLOOR PLAN - EAST - PIPING
195 MP-113 DIRECTORS LODGE - GROUND LEVEL - FLOOR PLAN - WEST - PIPING
196 MP-114 DIRECTORS LODGE - SECOND LEVEL- FLOOR PLAN - PIPING
197 MP-311 PUBLIC RESTROOMS - GROUND LEVEL - FLOOR PLAN - PIPING
LIST OF DRAWINGS 00 01 15 - 6
198 MP-411 MAINTENANCE BUILDING - GROUND LEVEL - FLOOR PLAN - PIPING
ELECTRICAL
GENERAL
199 E-001 SYMBOLS, LEGENDS, NOTES, AND DRAWING INDEX
200 E-002 DETAILS
201 E-003 LIGHTNING DETAILS
202 E-004 LUMINAIRE SCHEDULE AND RISER DIAGRAM - DIRECTOR'S LODGE
203 E-005 LUMINAIRE SCHEDULE AND RISER DIAGRAM - PUBLIC INFORMATION CENTER
204 E-006 LUMINAIRE SCHEDULE AND RISER DIAGRAM - PUBLIC RESTROOMS
205 E-007 LUMINAIRE SCHEDULE AND RISER DIAGRAM - MAINTENANCE BUILDING
206 E-008 LUMINAIRE SCHEDULE AND RISER DIAGRAM - PUMP HOUSE
207 E-009 LUMINAIRE SCHEDULE AND RISER DIAGRAM - COMMITTAL SHELTERS
208 E-010 OVERALL SITE PLAN
DEMOLITION
209 ED-110 DIRECTOR'S LODGE - BASEMENT LEVEL - EAST - DEMOLITION
210 ED-111 DIRECTORS LODGE - BASEMENT LEVEL - -WEST - DEMOLITION
211 ED-112 DIRECTORS LODGE - GROUND LEVEL - EAST - DEMOLITION
212 ED-113 DIRECTORS LODGE - GROUND LEVEL - WEST - DEMOLITION
213 ED-114 DIRECTORS LODGE - SECOND LEVEL - DEMOLITION
214 ED-115 DIRECTORS LODGE - ATTIC LEVEL - DEMOLITION
215 ED-116 DIRECTORS LODGE - ROOF PLAN-EAST - DEMOLITION
216 ED-117 DIRECTORS LODGE - ROOF PLAN-WEST - DEMOLITION
217 ED-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - DEMOLITION
218 ED-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - DEMOLITION
219 ED-212 PUBLIC INFORMATION CENTER - ROOF PLAN - DEMOLITION
220 ED-311 PUBLIC RESTROOMS - GROUND LEVEL - DEMOLITION
221 ED-312 PUBLIC RESTROOMS - ROOF PLAN - DEMOLITION
222 ED-411 MAINTENANCE BUILDING - GROUND LEVEL - DEMOLITION
223 ED-412 MAINTENANCE BUILDING - ROOF PLAN - DEMOLITION
224 ED-510 PUMP HOUSE - BASEMENT & GROUND LEVEL - DEMOLITION
225 ED-611 COMMITTAL SHELTER A - DEMOLITION
226 ED-612 COMMITTAL SHELTER B - DEMOLITION
LIGHTING
227 EL-110 DIRECTORS LODGE - BASEMENT LEVEL - EAST - LIGHTING
228 EL-111 DIRECTORS LODGE - BASEMENT LEVEL - WEST - LIGHTING
229 EL-112 DIRECTORS LODGE - GROUND LEVEL - EAST - LIGHTING
230 EL-113 DIRECTORS LODGE - GROUND LEVEL - WEST - LIGHTING
231 EL-114 DIRECTORS LODGE - SECOND LEVEL - LIGHTING
232 EL-115 DIRECTORS LODGE - ATTIC LEVEL - LIGHTING
233 EL-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - LIGHTING
234 EL-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - LIGHTING
235 EL-311 PUBLIC RESTROOMS - GROUND LEVEL - LIGHTING
236 EL-411 MAINTENANCE BUILDING - GROUND LEVEL - LIGHTING
237 EL-510 PUMP HOUSE - BASEMENT & GROUND LEVEL - LIGHTING
238 EL-611 COMMITTAL SHELTER A - LIGHTING
239 EL-612 COMMITTAL SHELTER B - LIGHTING
LIST OF DRAWINGS 00 01 15 - 7
POWER
240 EP-110 DIRECTORS LODGE - BASEMENT LEVEL - EAST - POWER
241 EP-111 DIRECTORS LODGE - BASEMENT LEVEL - WEST - POWER
242 EP-112 DIRECTORS LODGE - GROUND LEVEL - EAST - POWER
243 EP-113 DIRECTORS LODGE - GROUND LEVEL - WEST - POWER
244 EP-114 DIRECTORS LODGE - SECOND LEVEL - POWER
245 EP-115 DIRECTORS LODGE - ATTIC LEVEL - POWER
246 EP-116 DIRECTORS LODGE - ROOF PLAN-EAST - POWER
247 EP-117 DIRECTORS LODGE - ROOF PLAN-WEST - POWER
248 EP-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - POWER
249 EP-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - POWER
250 EP-212 PUBLIC INFORMATION CENTER - ROOF PLAN - POWER
251 EP-311 PUBLIC RESTROOMS - GROUND LEVEL - POWER
252 EP-312 PUBLIC RESTROOMS - ROOF PLAN - POWER
253 EP-313 PUBLIC RESTROOMS - TEMPORARY POWER
254 EP-411 MAINTENANCE BUILDING - GROUND LEVEL - NORTH - POWER
255 EP-412 MAINTENANCE BUILDING - GROUND LEVEL - EAST - POWER
256 EP-413 MAINTENANCE BUILDING - GROUND LEVEL - WEST - POWER
257 EP-414 MAINTENANCE BUILDING - ROOF PLAN - POWER
258 EP-510 PUMP HOUSE - BASEMENT LEVEL & GROUND LEVEL & ROOF - POWER
259 EP-611 COMMITTAL SHELTER A - GROUND LEVEL - POWER
260 EP-612 COMMITTAL SHELTER B - GROUND LEVEL - POWER
261 EP-711 IRRIGATION WELL - POWER
TELECOMMUNICATIONS
262 ET-110 DIRECTOR'S LODGE - BASEMENT LEVEL - EAST - TELECOMMUNICATIONS
263 ET-111 DIRECTOR'S LODGE - BASEMENT LEVEL - WEST - TELECOMMUNICATIONS
264 ET-112 DIRECTOR'S LODGE - GROUND LEVEL - EAST - TELECOMMUNICATIONS
265 ET-113 DIRECTOR'S LODGE - GROUND LEVEL - WEST - TELECOMMUNICATIONS
266 ET-114 DIRECTOR'S LODGE - SECOND LEVEL - TELECOMMUNICATIONS
267 ET-210 PUBLIC INFORMATION CENTER - BASEMENT LEVEL - TELECOMMUNICATIONS
268 ET-211 PUBLIC INFORMATION CENTER - GROUND LEVEL - TELECOMMUNICATIONS
269 ET-311 PUBLIC RESTROOMS - GROUND LEVEL - TELECOMMUNICATIONS
PLUMBING
GENERAL
270 P-001 PLUMBING - ABBREVIATIONS, SCHEDULES AND SYMBOLS
271 P-002 PLUMBING - DETAILS
DEMOLITION
272 PD-110 DIRECTORS LODGE - PLUMBING - BASEMENT LEVEL - FLOOR PLAN EAST - DEMOLITION
273 PD-111 DIRECTORS LODGE - PLUMBING - BASEMENT LEVEL - FLOOR PLAN WEST - DEMOLITION
274 PD-112 DIRECTORS LODGE - PLUMBING - GROUND LEVEL - FLOOR PLAN EAST - DEMOLITION
275 PD-113 DIRECTORS LODGE - PLUMBING - GROUND LEVEL - FLOOR PLAN WEST - DEMOLITION
276 PD-114 DIRECTORS LODGE - PLUMBING - SECOND LEVEL - FLOOR PLAN - DEMOLITION
277 PD-211 PUBLIC INFORMATION CENTER - PLUMBING - GROUND LEVEL - FLOOR PLAN - DEMOLITION
278 PD-311 PUBLIC RESTROOMS - PLUMBING - GROUND LEVEL - FLOOR PLAN - DEMOLITION
NEW WORK
279 PP-110 DIRECTORS LODGE - PLUMBING - BASEMENT LEVEL - FLOOR PLAN EAST
LIST OF DRAWINGS 00 01 15 - 8
280 PP-111 DIRECTORS LODGE - PLUMBING - BASEMENT LEVEL - FLOOR PLAN WEST
281 PP-112 DIRECTORS LODGE - PLUMBING - GROUND LEVEL - FLOOR PLAN EAST
282 PP-113 DIRECTORS LODGE - PLUMBING - GROUND LEVEL - FLOOR PLAN WEST
283 PP-114 DIRECTORS LODGE - PLUMBING - SECOND LEVEL - FLOOR PLAN
284 PP-211 PUBLIC INFORMATION CENTER - PLUMBING - GROUND LEVEL - FLOOR PLAN - GRAVITY
285 PP-212 PUBLIC INFORMATION CENTER - PLUMBING - GROUND LEVEL - FLOOR PLAN - PRESSURE
286 PP-311 PUBLIC RESTROOMS - PLUMBING - GROUND LEVEL - FLOOR PLAN - GRAVITY
287 PP-312 PUBLIC RESTROOMS - PLUMBING - GROUND LEVEL - FLOOR PLAN - PRESSURE
288 PP-313 PUBLIC RESTROOMS - TEMPORARY PLUMBING
FIRE ALARM
289 FA-001 SYMBOLS, NOTES, ABBREVIATIONS, AND DRAWING INDEX
290 FA-002 DETAILS AND MATRIX
291 FA-110 DIRECTORS LODGE - BASEMENT & GROUND LEVEL - FIRE ALARM
292 FA-111 DIRECTORS LODGE - SECOND & ATTIC LEVEL - FIRE ALARM
STRUCTURAL
293 S-101 STRUCTURAL NOTES
294 S-201 STRUCTURAL DETAILS
295 S-202 STRUCTURAL DETAILS
296 S-203 STRUCTURAL DETAILS
END OF SECTION 00 01 15
i
SECTION 01 00 02 - GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 FIRE SAFETY
1.5 OPERATIONS AND STORAGE AREAS
1.6 ALTERATIONS
1.7 DISPOSAL AND RETENTION
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
1.9 RESTORATION
1.10 PHYSICAL DATA
1.11 PROFESSIONAL SURVEYING SERVICES
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 USE OF ROADWAYS
1.15 RE FIELD OFFICE
1.16 TEMPORARY TOILETS
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
1.18 INSTRUCTIONS
1.19 GOVERNMENT-FURNISHED PROPERTY
1.20 CONSTRUCTION SIGN
1.21 SAFETY SIGN
1.22 CONSTRUCTION DIGITAL IMAGES
1.23 FINAL ELEVATION PHOTOGRAPHS
1.24 HISTORIC PRESERVATION
1.25 PROJECT HEALTH AND SAFETY PLAN
ii
This page intentionally blank
GENERAL REQUIREMENTS 01 00 02 - 1
SECTION 01 00 02 - GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Facility Renovation, Improvements, and Repairs, Project Number
815CM3041, Long Island National Cemetery, Farmingdale, New York, as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Cemetery Director.
D. All Testing Laboratory services will be retained and paid for by the Contractor (see Spec Section
01 45 29, Testing Laboratory Services). However, the Department of Veterans Affairs may elect to retain its own Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the COR and be identified by name and employer. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a OSHA certified
“competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Performance of all work shown on the plans and described in the specifications.
1. Base Bid:
a. Committal Service Shelters A and B renovation.
GENERAL REQUIREMENTS 01 00 02 - 2
b. Public Restroom/Comfort Station restoration and renovation, including adjacent sidewalks and temporary modular public restroom building(s).
c. Columbarium Plaza A repairs and improvements, including adjacent new benches and bench pads.
d. Irrigation Well, including tie-in to existing water distributions system, adjacent rails, and decommissioning existing well. Provide the following subdivided line item cost units:
Item Description Unit
1 Mobilization and Demobilization Lump Sum
2 All-Weather Pad and Pad Preparation Lump Sum
3 Well Installation Plan & Pre-Drilling Submittals Lump Sum
4 Geologist Oversight / Logging / Formation Sampling Per Day
5 34-inch Borehole Drilling (0–50 feet) Linear Foot
6 26-inch Borehole Drilling (50–300 feet) Linear Foot
7 26-inch Borehole Drilling (300+ feet) Linear Foot
8 Furnish and Install 27-inch Steel Surface Casing Linear Foot
9 Furnish and Install 18-inch Steel Production Casing Linear Foot
Furnish and Install 18-inch Stainless Steel Wire-Wrap Well Screen
(includes E-309 cathodic protection at junction with production casing) Linear Foot
11 Furnish and Install 18-inch Stainless Steel Screen Sump Casing Linear Foot
12 Furnish and Install 1.25-inch Stainless Steel Water Level Measuring Tube Linear Foot
Furnish and Install Neat Cement Grout Annular Seal
(includes grouting 27-inch and 18-inch casing) Linear Foot
Furnish and Install Bentonite Grout Annular Seal
(includes grouting 18-inch casing) Linear Foot
Furnish and Install Filter Sand Pack
(includes placement around 18" screen/casing) Linear Foot
Drilling Fluid, Formation Sample, and Sand Pack Testing Lump Sum
16 Furnish and Install Centralizers at 60-foot Interval Per Set
17 Geophysical Logging Lump Sum
18 Well Development with Rig Hour
19 Install/Remove Test Pump Lump Sum
20 Well Development with Test Pump Hour
21 Well Disinfection Lump Sum
Step-Drawdown Pumping Test (includes furnishing and installing testing equipment and discharge piping) Hour
23 Constant-Rate Pumping Test Hour
24 Water Quality Sampling Lump Sum
25 Mud/Cuttings/Debris Disposal Lump Sum
26 Well Survey Lump Sum
Final Submittals (Borehole Log, Installation Diagram, Well Completion Report, Well Development Records, Geophysical Logs, Hydrogeologic Report, Test
Results, Project Photographs, Survey Maps)
Lump Sum
e. Pump House renovation.
GENERAL REQUIREMENTS 01 00 02 - 3
f. Cemetery Signage, including demolition of indicated existing signs, finished grade repairs, and turf repairs. Excludes SC.x Cortege signage.
g. Section Monuments, including demolition of existing monuments, finished grade repairs, and turf repairs.
h. Flower Watering Stations, including demolition of indicated hydrants, posts/bollards, pads, and appurtenances.
i. Maintenance Building Renovations.
j. Public Information Center, including related railings and stair/ramp entries.
k. Cortege Lanes, including existing pavement milling/overlay, curb & gutter, SC.x
Cortege signage.
l. Bronze Plaques restoration.
m. Director’s Lodge renovations, including entry steps/railings, adjacent sidewalks, finished grade repairs, turf repair, deck replacement, planter replacement, and new plantings.
n. Road and Stormwater repairs, excluding those associated with Cortege Lanes, above.
B. Provide the following with bid submission:
1. Narrative Plan Of Hazardous Materials Work, signed and dated by the general contractor's project manager and an officer in the company, witnessed by a state-certified notary public.
Include how contractor will handle the hazardous materials. Include a written acknowledgement that contractor has reviewed the entirety of the contract documents, including all items relevant and potentially relevant to hazardous materials, that Plan and fees include all work required under the contract documents, whether directly or indirectly by reference such as nationally- and industry- recognized standards and the rules, regulations, and laws of local, state, and federal authorities having jurisdiction.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. After award of contract, sets of drawings may be made by the Contractor, at Contractor's expense, from digital files furnished by the Issuing Office.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
B. Security Procedures:
GENERAL REQUIREMENTS 01 00 02 - 4
1. General Contractor’s employees shall not enter the site without following the procedures approved by the COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days notice to the COR so that appropriate arrangements can be provided for the Cemetery employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR. No photography of open graves, funerals, and related activities and services, or visitors is allowed at any time.
4. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval of the COR.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project site after construction hours when theft or vandalism warrants.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information.”
2. The General Contractor is responsible for safekeeping of all drawings, project manual, and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos, or photographs and drawings may be marked “Law
Enforcement Sensitive” or “Sensitive Unclassified.” Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the COR upon request.
GENERAL REQUIREMENTS 01 00 02 - 5
4. These security documents shall not be removed or transmitted from the project site without the written approval of COR.
5. All paper waste or electronic media such as CD’s shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify COR immediately when there is a loss or compromise of “sensitive information.”
7. All electronic information shall be stored in a specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other
Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and
Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR
1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s
GENERAL REQUIREMENTS 01 00 02 - 6
beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc. Documentation shall be provided to the COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police, and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Construction Partitions:
1. Install and maintain temporary construction partitions to provide smoke-tight separations between interior construction areas and adjoining occupied interior areas. Construct partitions of gypsum board or treated plywood (flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire retardant treated wood or metal steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door openings, install Class C, ¾ hour fire/smoke rated doors with self-closing devices.
2. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials.
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29
CFR 1926, NFPA 241 and NFPA 70.
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with COR/Cemetery Director.
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily.
Report findings and corrective actions weekly to COR.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR
1926, NFPA 241 and NFPA 30.
GENERAL REQUIREMENTS 01 00 02 - 7
K. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Request interruptions in accordance with Article, OPERATIONS AND STORAGE
AREAS, and coordinate with COR. All existing or temporary fire protection systems (fire alarms) located in construction areas shall be tested as coordinated with the Cemetery. Parameters for the testing and results of any tests performed shall be recorded by the Cemetery and copies provided to the COR.
L. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with COR.
M. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA
51B. Coordinate with COR. Designate Contractor's responsible project-site fire prevention program manager to permit hot work. Coordinate with COR.
L. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly.
Coordinate with, and report findings and corrective actions weekly to COR.
M. Smoking: Smoking is prohibited in all areas and buildings of the site.
N. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily and/site weekly and as directed by COR.
O. Perform other construction, alteration and demolition operations in accordance with 29 CFR
1926.
1.6 OPERATIONS AND STORAGE AREAS
A. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the
Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, at the Contractor’s own expense and liability, arrange authorized use and improvement of adjacent private property for site access and storage. Following completion of
GENERAL REQUIREMENTS 01 00 02 - 8
Work, Contractor shall return private property used by Contractor to previous condition, as determined and accepted by private property’s owner.
D. The Contractor shallCOR not use Cemetery roads at any time, except as specifically authorized by COR.COR.
E. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any
Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
F. Working space and space available on Government property for storing materials shall be as determined by the COR with agreement of the Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the COR in agreement of the Cemetery.
G. Workers are subject to rules of the Cemetery applicable to their conduct.
H. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including funeral and interment services, operations of utility services, fire protection systems, and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Cemetery in quantities sufficient for not more than two work days. Provide unobstructed access to the Cemetery areas required to remain in operation.
3. Where access by Cemetery personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing: To ensure such executions, the Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each Bid
Item or portion thereof. In addition, the Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each Bid Item or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to the Cemetery
Director, COR and Contractor.
GENERAL REQUIREMENTS 01 00 02 - 9
. The Director’s Lodge and Maintenance Building will be occupied during performance of work;
but immediate areas of alterations will be vacated.
1. Take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. Permit access to Cemetery personnel through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by
Cemetery Staff so that Cemetery operations will continue during the construction period.
I. Construction Fence: Before construction operations begin, the Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction areas indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).
Bottom of fences shall extend to 25mm( one inch) above grade. The temporary fencing shall encompass the construction work area(s) to secure materials and equipment and to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by COR.
J. When a building is turned over to Contractor, Contractor shall accept entire responsibility therefore.
1. The Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. The Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, the Contractor shall make arrangements for pre-inspection of the site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from the
Contractor's employee.
J. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing utility systems, they shall be cut and
GENERAL REQUIREMENTS 01 00 02 - 10
capped at suitable places where shown; or, in absence of such indication, where directed by
COR. All such actions shall be coordinated with the Utility Company involved.
1. No utility service may be interrupted without prior approval of COR.
2. The Contractor shall submit a request to interrupt any such services to both COR and the
Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery.
Interruption time approved by the Cemetery and COR may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of
COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes, and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped, or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
L. To minimize interference of construction activities with flow of Cemetery traffic, comply with the following:
1. Keep roads, walks, and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and, standing construction equipment and vehicles.
Wherever Work affects existing roads, at least one lane must be open to traffic at all times.
Provide safety signage, barricades, and object markers to alert motorists and pedestrians of
GENERAL REQUIREMENTS 01 00 02 - 11
lane closures. Provide flaggers during Cemetery Hours at closures near Gates 1-5 and other congested areas, as directed by COR.
2. Method and scheduling of required cutting, altering, and removal of existing roads, walks, and entrances must be approved by the COR.
M. Coordination of Construction with Cemetery Director: The burial activities at a National
Cemetery shall take precedence over construction activities. The Contractor shall cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in actual burial areas.
Construction noise during the committal services shall not disturb the service. Trucks, equipment, and workers shall not pass through or near the service area during this period.
1. The Contractor is required to discontinue work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veterans Day and/or Federal holidays, to permit
Contractor to clean up all areas of operation adjacent to existing cemetery burial sections before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials, and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of buildings and areas in which alterations will occur and anticipated routes of access, and furnish a signed report, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls, and other surfaces not required to be altered throughout affected areas.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage, and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is
GENERAL REQUIREMENTS 01 00 02 - 12
impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the…