About this file
This document contains mechanical plans and specifications for data center infrastructure upgrades at the Audie L Murphy VA Medical Center in San Antonio, Texas. The plans call for installing new mechanical equipment including computer room air conditioners, fire suppression systems, and plumbing fixtures to support the data center. Specific requirements include ducting new CRAC units into an overhead return air plenum, providing nozzle coverage for a clean agent fire suppression system, connecting new chilled water lines to existing mains, and rerouting exhaust ducts. Sprinklers must be installed per NFPA 13 and 75 standards. A single butterfly valve with monitor switches will control the sprinkler piping serving the data center.
The related federal contract opportunity is solicitation number 36C77623B0064 for infrastructure upgrades at the San Antonio VA Medical Center, set aside for Service-Disabled Veteran-Owned Small Businesses. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas. The required construction work includes the mechanical system upgrades described in the plans and specifications.
View the file
Other files for this federal contract opportunity
Show all 50
EHRM San Antonio Infrastructure Upgrades Construction (SDVOSB Set-Aside and 236220 NAICS) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T
T
T
T
T
T
T
T
EACH RACK HAS A DUCT
CONNECTION OFF THE TOP.
DUCT FROM THE
CONNECTION INTO THE
BOTTOM OF THE
OVERHEAD RETURN DUCT.
DUCT SHALL MATCH THE
RACK CONNECTION SIZE.
(TYP. ALL RACKS)
CRAC UNIT HAS A DUCT FLANGE ON
THE TOP OF THE UNIT. DUCT FROM
THE CONNECTION INTO THE BOTTOM
OF THE OVERHEAD RETURN DUCT
PLENUM. DUCT SHALL MATCH THE
CRAC CONNECTION SIZE. (TYP. 4)
CLEAN AGENT FIRE SUPPRESSION SYSTEM.
BASIS OF DESIGN CLEAN AGENT IS NOVEC 1230
WITH SYSTEM DESIGN BY ANSUL. BY PROVIDE
NOZZLE COVERAGE IN THE NEW DATA CENTER
PER NFPA 2001. REFER TO SPECIFICATION 21 22
00 FOR SYSTEM REQUIREMENTS. REFER TO
ELECTRICAL PLANS FOR MANUAL ACTIVATION
STATION LOCATION.
x
12x10 x
CD-1
6/125
CD-1
8/160
(TYP. 10)
8x8 TD
RG-1
RG-1
RG-1
x
2"CWS
2"CWR
"C
W S
"C
W R
/2 "C
W S
/2 "C
W R
2"CWR
2"CWS
"C
W S
"C
W R
2 1/2"CWR
2 1/2"CWS
3"CWR
3"CWS
CONNECT NEW CHILLED WATER
SUPPLY AND RETURN TO
EXISTING MAINS IN THIS SHAFT.
72x24 x x x
72x24
PROVIDE SPRINKLER COVERAGE IN THE DATA
CENTER PER NFPA 13 AND 75 REQUIREMENTS.
SPRINKLERS SHALL BE STANDARD RESPONSE
WITH PROTECTION GUARDS. DATA CENTER SHALL
BE CLASSIFIED AS LIGHT HAZARD.SPRINKLERS IN
THE DATA CENTER SHALL BE SERVED FROM A
SINGLE MAIN WITH A NEW BUTTERFLY VALVE AND
ASSOCIATED MONITOR SWITCH WIRED TO THE
FIRE ALARM SYSTEM. REFER TO SHEET NOTE 1
FOR BUTTERFLY VALVE REQUIREMENTS.
18x12 TD
BCU-1
x
20x16
12x10
8x10
TAB-3
TAB-4
TAB-2
TAB-1
10x8
14x10 TD
CD-1
6/160
(TYP.2)
CD-1
10/195
"C
W S
"C
W R
"C
W S
"C
W R x
REROUTE EXAUST UNDER
EXISTING LARGE EXHAUST
DUCTS.
EXHAUST DUCT UP TO
SAME BOTTOM OF DUCT
ELEVATION AS THE
ADJACENT EXISTING LARGE
EXHAUST DUCTS.
RG-1 RG-1
REUSE EXISTING
SUPPYL DUCT
PENETRATION
FD
FD
9 10
L.3
M
10.19.1
GA
GB
L
REVISE EXISTING SPRINKLER
LAYOUT AND PIPING IN THIS
AREA AS NECESSARY TO
PROVIDE SPRINKLER
COVERAGE PER NFPA 13.
NUMBER AND ADDRESS
SUITE NO.
CITY, STATE ZIP CODE
P: 555.555.555 F: 555.555.5555 www.imegcorp.com
PROJECT #22006633.00
DESIGN DEVELOPMENT SUBMISSION
N O T F O R C O N S T R U C T I O N
5 5 10 15 20
1/8" = 1'-0"
FEETSCALE
P L A
N N
O R
T H
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FINAL BID DOCUMENTS
100%
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMP
321 4 5 6 7 8 9 10
B
IM
/A u d ie L
M u rp h y V
A M e d ic a l C e n te r
(S A
M
E P
T
.0
V A
-S a n A n to n io
T
X -E
H R
M
C .r v t
/2
/2
:0
:3
P
M
MN424
1ST FLOOR - DATA CENTER - MECHANICAL -
ENLARGED NEW WORK PLANS
Awen Solutions Group
4196 Merchant Plaza, Suite 711
Woodbridge, VA 22192
06/09/2023
EHRM INFRASTRUCTURE
UPGRADES 1
Audie L Murphy VA Medical Center (San Antonio) 7400 Merton Minter, San Antonio, TX 78229
671-22-700
KEY PLAN
1/4" = 1'-0"
1ST FLOOR PLAN - DATA CENTER/IT OFFICE - MECHANICAL - ENLARGMENT
SHEET NOTES:
1. DATA CENTER SPRINKLER PIPING BUTTERFLY
VALVE SHALL BE PER THE FOLLOWING:
A. INDICATING BUTTERFLY VALVE, NORMALLY
OPEN, 175 PSI WWP, GROOVED TYPE,
DUCTILE IRON BODY WITH PROTECTIVE
COATING, ELECTROLESS NICKEL OR EPDM
COATED DUCTILE IRON DISC, STAINLESS
STEEL STEM AND SCREWS, CAST OR
DUCTILE IRON HANDWHEEL, EPDM SEAT,
INDICATOR FLAG, FACTORY MOUNTED
INTEGRAL MONITOR SWITCHES, UL/FM.
B. LUGGED OR WAFER VALVES ARE
ACCEPTABLE PROVIDED THEY HAVE THE
FEATURES LISTED ABOVE.
C. ACCEPTABLE MANUFACTURER/MODEL:
NIBCO GD-4765-8N, VICTAULIC SERIES 705,
TYCO BFV-300, KENNEDY G300, GLOBE
GLR300G, REL-BFG-300.
2. REFER TO ELECTRICAL DRAWINGS FOR EPO
BUTTON LOCATION.
04/28/2023
KEYNOTES:
1. NEW SINK SK-1:
A. EXTEND 1/2" COLD WATER, 1/2" HOT
WATER, 1 1/2" VENT, 1 1/2" SAN FROM SINK
IN THE ADJACENT ROOM PLAN EAST FROM
THIS SINK.
B. MATERIAL:
a. SINK - ACCESSIBLE, SELF-RIMMING
SINGLE COMPARTMENT WITH FAUCET
DECK AND OVERFLOW, 18 GAUGE TYPE
304 STAINLESS STEEL, 20" (SIDE-TO-
SIDE) x 16" (FRONT-TO-BACK) OVERALL SIZE, 18" x 14" x 6.5" DEEP BOWL, SOUND DEADENING ON BOTTOM OF
BASIN, 3-1/2" DIAMETER DRAIN OUTLET
LOCATION OFF-CENTERED REAR IN
BOWL, PERFORATED TYPE 304
STAINLESS STEEL GRID STRAINER.
b. SINK TRIM - SINGLE HANDLE MIXING
FAUCET, BRASS CONSTRUCTION,
CHROME-PLATED FINISH, NOMINAL 10"
HIGH-RISE SWING SPOUT, CERAMIC
CARTRIDGE, NOMINAL 8" REACH, PULL
DOWN SPRAY HOSE WITH AERATOR
STREAM / SPRAY SELECTOR, LEVER
HANDLE. MAXIMUM FLOW TO BE 2.2
GPM IN COMPLIANCE WITH ENERGY
POLICY ACT OF 2005 AND ASME/ANSI
STANDARD A112.18.1M. FAUCET SHALL
COMPLY WITH FEDERAL ACT S.3874.
PROVIDE RESTRICTIVE DEVICE AND
ESCUTCHEON PLATE AS REQUIRED.
c. ACCESSORIES - OFFSET 1-1/2" 17
GAUGE CHROME-PLATED BRASS
TAILPIECE AND P-TRAP, QUARTER-
TURN BALL VALVE TYPE 3/8" CHROME-
PLATED BRASS ANGLE SUPPLIES WITH
LOOSE KEY STOPS, CHROME-PLATED
SOFT COPPER SUPPLY LINES.
Revisions: Date:
Δ A, Addendum 1 08/24/2023
ClarkGarrettAIANCARB Text Box A
| Sheets |
| MN424 - 1ST FLOOR - DATA CENTER - MECHANICAL - ENLARGED NEW WORK PLANS |