This addendum modifies an original solicitation for infrastructure upgrades at an Audie L. Murphy Memorial Veterans' Hospital in San Antonio, Texas. The addendum provides revisions to specifications, drawings, and notes for sections including hazardous materials abatement, roofing, and civil works. Changes include adding new specification sections, revising demolition and construction barrier details, and modifying mechanical, telecommunications, and technology drawings and schedules. The related federal contract opportunity is a SDVOSB set-aside solicitation from the Department of Veterans Affairs Technology Acquisition Center Austin for construction services involving the EHRM San Antonio infrastructure upgrades.
View the file
Other files for this federal contract opportunity
Show all 50
EHRM San Antonio Infrastructure Upgrades Construction (SDVOSB Set-Aside and 236220 NAICS) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
Page | 1
From: Awen Solutions Group
Project: EHRM Infrastructure Upgrades
Audie L. Murphy Memorial Veterans' Hospital
7400 Merton Minter Boulevard, San Antonio TX
Project No. 671-22-700
Date: August 24, 2023
To: Prospective Bidders
This Addendum forms a part of the Contract Documents and modifies the original Procurement
Documents date June 9, 2023, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification.
This Addendum consists of two (2) pages and the attachments listed below with the revised date of
August 24, 2023.
CHANGES TO PRIOR ADDENDA:
1. None
CHANGES TO PROCUREMENT REQUIREMENTS:
1. None
CHANGES TO CONTRACTING REQUIREMENTS:
1. None
CHANGES TO SPECIFICATIONS:
1. Section 02 82 13.21, new section.
2. Section 07 51 00, new section.
3. Section 32 05 23, new section.
CHANGES TO DRAWINGS:
1. GENERAL
a. Sheet GI005, Sequencing Notes, Note 4B, delete this note. Contractor shall coordinate work scheduling with the VA, refer to Section 01 32 16.15.
2. ARCHITECTURAL
a. Sheet AD406, Demotion Legend, revise Temporary Construction Barrier reference to read F1/AE551.
b. Sheet AE551, Detail F1/AE551, provide acoustical insulation, unfaced mineral fiber batts or blankets, ASTM 665, Flame Spread Rating: 25, Smoke Developed Rating: 450.
c. Sheet AE521, Keynote W18 revised to read, Rubber type sheet formed of non-reinforced, homogeneous, impermeable, sheeting compound reduced to thermoplastic state, resistant to fungus, mildew and bacteria, not less than 1.5 mm (60 mils) thick.
Install per manufacturer’s instructions.
ADDENDUM NO. 1
Page | 2
d. Sheet AE521, Keynote W21, please disregard this note, there is no wall protection and railing installation anticipated. If any requires removal, it should be salvaged for reinstallation.
3. MECHANICAL
a. Sheet MN424 – 1st Floor - Data Center - Mechanical - Enlarged New Work Plans, add note to revise sprinkler layout for old data center/new office space. Sheet reissued, Δ A.
b. .
4. TELECOMMUNICATIONS
a. Sheet TN101 - 1st Floor Plan - Technology – Overall, revise the area served for rooms TR-
1-2 & TR-1-2 as shown on the supplemental drawings. Sheet reissued, Δ A.
b. Sheets TN400, TN401, TN402, TN403, TN404, TN405, TN406, TN407, TN410, TN411, TN412, TN414, TN415, TN416, TN417, TN419, TN420, TN421, TN422, TN423, TN424, TN425, TN450:
i. Revise the equipment rack and notes to provide the quantities of patch panels required for complete cabling installation.
c. Sheet TN411 - 1st Floor - TR J104 - Technology - Enlarged Plans, remove equipment rack as shown on the supplemental drawing.
d. Sheet TN142 - 1st Floor Plan - Technology - Area G, revise the data outlet types in the new IT office space. Added new supporting keynote. Sheet reissued, Δ A.
e. SheetT605 – Technology – Schedules, revise TES to include SC-ER-2.
Attachments:
Specification Section 02 82 13.21
Specification Section 07 51 00, new section.
Specification Section 32 05 23, new section.
Sheet MN424
Sheet TN101
Sheet TN142