About this file

36C26118R0487 570-16-302 VA Fresno CPP2_SPECIFICATIONS_DIV_00-13_IFC_020718.pdf

View the file

Other files

File Type Posted
36C26118R0487-0005000.docx DOCX document
36C26118R0487-0004000.docx DOCX document
36C26118R0487-0003001.pdf PDF
36C26118R0487-0003000.docx DOCX document
36C26118R0487-0002045.pdf PDF
36C26118R0487-0002037.pdf PDF
36C26118R0487-0002042.pdf PDF
36C26118R0487-0002039.pdf PDF
36C26118R0487-0002043.pdf PDF
36C26118R0487-0002040.pdf PDF
36C26118R0487-0002049.pdf PDF
36C26118R0487-0002048.pdf PDF
36C26118R0487-0002050.pdf PDF
36C26118R0487-0002044.pdf PDF
36C26118R0487-0002046.pdf PDF
36C26118R0487-0002041.pdf PDF
36C26118R0487-0002047.pdf PDF
36C26118R0487-0002038.pdf PDF
36C26118R0487-0002036.docx DOCX document
36C26118R0487-0001001.pdf PDF
36C26118R0487-0001000.docx DOCX document
36C26118R0487-0001003.pdf PDF
36C26118R0487-0001002.pdf PDF
36C26118R0487-101.pdf PDF
36C26118R0487-096.pdf PDF
36C26118R0487-099.pdf PDF
36C26118R0487-109.pdf PDF
36C26118R0487-107.pdf PDF
36C26118R0487-090.pdf PDF
36C26118R0487-106.pdf PDF
36C26118R0487-094.pdf PDF
36C26118R0487-110.pdf PDF
36C26118R0487-104.pdf PDF
36C26118R0487-089.docx DOCX document
36C26118R0487-100.pdf PDF
36C26118R0487-102.pdf PDF
36C26118R0487-108.pdf PDF
36C26118R0487-098.pdf PDF
36C26118R0487-105.pdf PDF
36C26118R0487-092.xls XLS spreadsheet
36C26118R0487-091.doc DOC document
36C26118R0487-097.pdf PDF
36C26118R0487-095.pdf PDF
36C26118R0487-103.pdf PDF
36C26118R0487-000.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CCVAHCS Fresno, CA December 15, 2017 Design Expanded Chilled Water Capacity, Phase 2 Page

APPENDIX D – SPECIFICATIONS

VACCHCS Fresno, CA #570-16-302 Design Expanded Chilled Water Capacity, Phase 2 - 100%CD November 15, 2017

Design Expanded Chilled Water Capacity, Phase 2- 100%CD December 11, 2017

Design Expanded Chilled Water Capacity, Phase 2- 100%CD December 11, 2017 February 7, 2018

February 7, 2018

Seals 00 01 07-1

SECTION 00 01 07

SEALS

1.1 DESIGN PROFESSIONALS OF RECORD

Firm name: Triple C – The A & E Group Individual’s name: Mathew Perkins State and license number: Arizona #39128

Sections:

00 01 15 01 00 00 01 00 10 01 33 23 01 35 26 01 42 19 01 45 29 01 58 16 01 91 00 02 21 13 02 41 00 04 05 13 04 72 00 05 31 00 05 40 00 07 92 00 08 80 00 09 91 00 10 73 00

Firm name: United Structural Design, LLC Individual’s name: David Grapsas, S.E.

State and license number: California

Sections:

03 30 00

05 12 00 05 21 00 13 05 41 31 63 26

Firm name: Bridgers & Paxton Individual’s name: Richard Reif, P.E.

State and license number:

Sections:

22 05 11 22 07 11 22 08 00 22 62 00 22 63 00 23 05 10 23 05 11 23 05 12 23 05 41 23 05 50 23 05 51 23 05 93

02/08/18

NM 14718

Expires 6.30.16Expires: 6/30/18

2/8 /18

John Elder. S.E.

02/08/2018

Seals 00 01 07-2

23 07 11 23 08 00 23 09 23 23 21 13 23 22 13 23 25 00 23 64 00

Firm name: Bridgers & Paxton Individual’s name: John Montaño, P.E.

State and license number:

Sections:

26 05 11 26 05 19 26 05 26 26 05 29 26 05 48 26 05 53 26 05 73 26 05 74 26 08 00 26 27 26 26 29 11 26 29 21 26 56 00

Firm name: Triple C – The A & E Group Individual’s name: David Potter, P.E.

State and license number:

Sections:

31 20 00 32 05 23 32 31 13 32 84 00 32 90 00 33 08 00 33 10 00 33 40 00 33 46 13 33 51 00 33 63 00

2/ 8/

2/08/17

11/03/16

EXPIRES: 12/31/18

2/08/18

26 05 13 26 05 41

Design Expanded Chilled Water Capacity, Phase 2- 100%CD February 7, 2018

TABLE OF CONTENTS

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-15

01 00 10 Contractor Quality Control (CQC)

01 32 16.15 Project Schedules (Small Projects) 02-15

01 33 23 Shop Drawings, Product Data, and Samples 07-15

01 35 26 Safety Requirements 09-16

01 42 19 Reference Standards 05-16

01 45 00 Quality Control

01 45 29 Testing Laboratory Services 06-16

01 45 35 Special Inspections

01 57 19 Temporary Environmental Controls

01 74 19 Construction Waste Management 09-13

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site Surveys 08-16

02 41 00 Demolition 02-15

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 12-15

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17

04 72 00 Cast Stone Masonry 02-15

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 02-16

05 21 00 Steel Joist Framing 03-10

05 31 00 Steel Decking 02-16

05 40 00 Cold-Formed Metal Framing 05-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants 10-15

00 01 10-2

DIVISION 08 - OPENINGS

08 80 00 Glazing 10-15

DIVISION 09 - FINISHES

09 91 00 Painting 01-16

DIVISION 10 - SPECIALTIES

10 73 00 Translucent Custom Canopies

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-14

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 07 11 Plumbing Insulation 09-15

22 08 00 Commissioning of Plumbing Systems

22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15

22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

(HVAC)

23 05 10 Common Work Results for Boiler Plant and Steam Generation 02-15

23 05 11 Common Work Results for HVAC 02-15

23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 11-10

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-15

23 05 50 Variable Frequency Drives

23 05 51 Noise and Vibration Control for Boiler Plant 02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC and Boiler Plant Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 09-12

23 22 13 Steam and Condensate Heating Piping 02-15

23 25 00 HVAC Water Treatment

23 64 00 Packaged Water Chillers 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 13 Medium Voltage Cables 01-17

26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13

26 05 26 Grounding and Bonding for Electrical Systems 12-12

26 05 29 Hangers and Supports for Electrical Systems

26 05 41 Underground Electrical Construction 01-17

26 05 48 Vibration and Seismic Controls for Electrical Systems

26 05 53 Identification for Electrical Systems

00 01 10-3

26 05 73 Overcurrent Protective Device Coordination Study 12-15

26 05 74 Overcurrent Protective Device Arc-Flash Study

26 08 00 Commissioning of Electrical Systems 11-16

26 27 26 Wiring Devices 01-16

26 29 11 Motor Controllers 08-14

26 29 21 Enclosed Switches and Circuit Breakers 12-12

26 56 00 Exterior Lighting 05-14

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

31 63 26 Drilled Caissons 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 31 13 Chain Link Fences and Gates 08-16

32 84 00 Planting Irrigation 08-16

32 90 00 Planting 08-16

DIVISION 33 – UTILITIES

33 08 00 Commissioning of Site Utility Systems 11-16

33 10 00 Water Utilities 03-17

33 40 00 Storm Sewer Utilities

33 46 13 Foundation Drainage

33 51 00 Natural-Gas Distribution

33 63 00 Steam Energy Distribution 09-17

DRAWING LIST

00 01 15 - 1

SECTION 00 01 15

00 01 15 - 2

00 01 15 - 3

GENERAL REQUIREMENTS

01 00 00 - 1

SECTION 01 00 00

TABLE OF

CONTENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 USE OF ROADWAYS

1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.17 TEMPORARY USE OF EXISTING ELEVATORS

1.18 TEMPORARY TOILETS

1.19 AVAILABILITY AND USE OF UTILITY SERVICES

1.20 TESTS

01 00 00 - 2

1.21 INSTRUCTIONS

1.22 CONSTRUCTION SIGN

1.23 SAFETY SIGN

1.24 HISTORIC PRESERVATION

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. The Chiller Infrastructure at the VA Central California Health Care system at 2615 E.

Clinton Ave. Fresno, CA 93703 requires updating, and corrections. This project is to increase the size of the chilled water piping system from the chilled water plant to Building

1 (the Main Hospital Building) to increase the distribution capacity for the main hospital. It also includes the installation of one additional chiller (Chiller 4) in the chiller plant to increase the chilled water capacity for the campus. Additionally, distribution of the chilled water system, and future utility systems, shall be located in overhead duct banks contained within a visually attractive, concealing pedestrian canopy. This necessitates the replacement and expansion of the existing pedestrian canopy system as shown on the drawings. It is noted that hospital operations must not be impacted by this project.

Therefore, an alternate pedestrian route has been identified for temporary or permanent construction depending on Additive Alternate execution. The scope also includes the removal and replacement of manhole/vault #7 along with providing new medium voltage feeders in new concrete duct bank to the new location. Additionally, corner drains will be added manhole/vault 5 and the B24 breezeway concrete floor will be resurfaced.

Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the removal and replacement of the existing pedestrian canopy system, associated infrastructure, chillers, and commissioning as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Medical

Center Engineering Officer.

C. Offices of Triple C – The A&E Group with offices at 4401 Atlantic Ave. Suite 200, Long

Beach, CA. 90807, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without

01 00 00 - 3 affirmations by Contracting Officer or his duly authorized representative.

D. All testing shall be by certified testing laboratories subcontracted by the Contract.

The Government shall not be required to contract testing for any trade.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Due to the phased approach of this project phased, commissioning will be required.

This will require acceptance and warranty start dates to vary. Contractor is to provide a schedule showing phased turnover, commissioning, acceptance, and warranty start by phase as indicated in the Contract Documents. VA acceptance of this schedule is required prior to the start of work.

G. Contractor to provide a third-party Mechanical Controls Engineer to perform complete calibration, programming, start-up, testing, demonstrations, instructions and training services required by the specifications, including (but not limited to): 01

45 00, 01 91 00, 22 08 00, and 23 08 00. Contractor to submit Mechanical Controls

Engineer qualifications, past experience and proposed responsibilities to the

COR/AE for review.

H. Comprehensive 3rd party inspections, testing and written reports for all Divisions (paid by the General Contractor). Contractor shall employ third party inspection consultants to perform all inspections required by this contract. The VA has no inspection capability. Any reference to VA inspections shall be by a third-party inspector qualified to perform the work.

Credentials shall be supplied to the VA/AE as required by this contract. All inspections, testing, certifications, and permits are to be paid for by the General Contractor. An air quality permit is required for the generator. The VA will not pay for or perform any required inspections. VA inspections are for VA use only, when performed, and do not reduce the inspection burden on the Contractor. Third party inspection services must be submitted for acceptance by the VA after award. Submission to include resumes of inspectors, with alternates, projected days on site, qualifications of inspectors showing similar projects, related portfolio, and description of communication protocol with Owner.

Acceptable 3rd Party inspectors include the following:

Parsons Brinckerhoff http://www.wsp-pb.com/en/WSP-USA/What-we-do-

USA/Services/All- Services-A-Z/Bridge-Engineering/Construction-Inspection/

Booz Allen http://www.boozallen.com

US Army Corps of Engineers http://www.usace.army.mil/ Bureau Veritas

01 00 00 - 4 http://www.bureauveritas.com/

Stantec http://www.stantec.com/our-work/services/construction-qa-qc-monitoring-inspection- services.html

HDR, Inc. http://www.hdrinc.com/

Gilbane http://www.gilbaneco.com

Minimum inspections required:

Material Testing, Excavation, Earthwork, Concrete, Mechanical, Electrical, Plumbing, Fire Protection, Structural Steel, Welding, Framing, Roofing, Lightning Protection, Utilities

(sewer, water, gas, electric, etc.), Landscaping

I. Contractor to provide Submittal Exchange® or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract. Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.

J. Contractor to provide Street Cleaners, Water Trucks, and rip rap on site for dust control during construction in addition to following the SWPPP requirements in the Contract

Documents. Submit usage plan for review by VA COR.

K. Contractor to provide Infection Control Plan as required by Memorandum 111-40, Subj:

VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.

L. Prior to commencing work, general contractor shall provide proof that a OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.

M. Pricing Proposal transparency requirements: this project requires pricing proposals to include breakdown pricing for the General Contractor and all subcontractors. All price proposals, including subcontractor pricing must include a breakdown of pricing per the format included with tis specification. Third-party inspections must be included as a line item in the price proposal. See example at the end of GENERAL REQUIREMENTS section.

N. Contractor to provide manufacturer’s letter that describes how the new Chiller #4 will be shipped and placed inside Building 22A given dimensional constraints of existing conditions at the time of shipment; and that split-shipments and field-assembly, if required, will not impact any equipment warranties.

01 00 00 - 5

O. Refer to specifications for installation requirements for each Division. Refer to drawings for estimated quantities and schematic layouts/locations. Contractor to provide a complete, commissioned, functioning product. The VA is not required to inspect or install any portion of this project. Contractor bears all installation and testing costs. Contractor to provide all testing reports prior to the start of commissioning. This project requires phased commissioning and turnover by building. This project will require night and weekend work.

1.3 STATEMENT OF BID ITEM(S)

CLIN 0001 - ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, walks, grading, drainage, retaining walls, demolition of existing pedestrian canopies, pathways, landscaping, and utilities and construction of one (1) new chiller with integration to existing automated controls and the addition of new differential pressure transducers in B1, OPC, B24 and B31, new infrastructure, new canopies and overhead utility chases, new electrical vault #7 with new 12 kV feeders and duct banks;

exclusive of Additive and Deductive Alternates. The new 12 kV feeders serve B22, B24, B25, B31 and B27. The new canopy and retaining wall will also include pathway, accent and duct bank lighting and power receptacles as shown on the drawings.

The overhead pedestrian canopies shall include an unseen raceway carrying chilled water from Building 22A to B1 subbasement, B31 penthouse and isolation valves for future connections as shown on the drawings. The overhead pedestrian raceway will include new steam and condensate return lines to B31 penthouse. New medical oxygen piping and medical oxygen and vacuum pump controls/alarms as shown on the drawings. Future utility

POC shown on the drawings are to be provided and coordinated with future projects detailed on the campus utility master plan and other future planned work detailed by the

COR. This includes provision for future overhead and eyebrow utility chases as shown on the drawings.

Existing utilities to be relocated/rerouted are enumerated on the contract drawings.

Contractor to perform complete survey to ensure conflicts between existing utilities and new canopy structure are avoided and new routing is provided with temporary utilities when to ensure minimal impact on hospital operations. All utility shutdowns are to be coordinated with COR minimum 30 days in advance. Contractor to also provide temporary pedestrian

01 00 00 - 6 walkways during construction, as shown on the drawings, to maintain 100% pedestrian access.

Further, the base bid also includes refurbishing the existing polished concrete slab under the B24 breezeway and the addition of drains to electrical manhole/vault #5 to mitigate standing water in the vault.

All systems are to be commissioned as new with re-commissioning after one year from

Government Acceptance.

A. CLIN 0002 - ITEM II: ADD ALTERNATE NO.1: Provide additional canopy routed from

B22/B31 sidewalk south along west side of B31, then along south side of campus and south of the B24 breezeway, see plans for routing. The base bid does not include this run as a permanent structure, the base bid is a temporary covered pedestrian walkway with temporary lighting for use during construction and is to be removed afterward.

B. CLIN 0003 - ITEM III ADD ALTERNATE NO.2: Widen sidewalk to 10’-0” as shown on drawings, this includes the construction of a new retaining/seat wall necessitated by the widened sidewalk.

C. CLIN 0004 - ITEM IV ADD ALTERNATE NO.3: Install self-supported translucent canopy system, Kalcurve (or approved equal) in lieu of the supported translucent canopy base bid design. If selected, this alternate will also apply to the canopy route outlined in Additive

Alternate No.

D. CLIN 0005 - ITEM V DEDUCTIVE ALTERNATE NO.1: CIP columns become framed columns as shown on drawings.

E. CLIN 0006 - ITEM VI DEDUCTIVE ALTERNATE NO. 2: Existing electrical manhole/vault #7 to be refurbished with surface treatment and epoxy sealant rather than providing a new manhole/vault. Contractor is still responsible for relocating existing electrical lines/duct banks as required to avoid conflicts with the new canopy.

F. Identify complete bids associated with the CLINs (Contract Line Item Number) as follows:

CLIN 0001: All work associated with ITEM I.- BASE BID

CLIN 0002: All work associated with ITEM II, ADD ALTERNATE NO. 1

CLIN 0003: All work associated with ITEM III, ADD ALTERNATE NO. 2.

CLIN 0004: All work associated with ITEM IV, ADD ALTERNATE NO. 3.

CLIN 0005: All work associated with ITEM V, DEDUCTIVE ALTERNATE NO. 1.

CLIN 0006: All work associated with ITEM VI, DEDUCTIVE ALTERNATE NO. 2.

G. Bids shall identify CLIN 001 – CLIN 006 as separate bid line items. See 01 00 00 Appendix A. “Sample Bid Form” for format.

01 00 00 - 7

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the

Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the

Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency. The

General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to

01 00 00 - 8 following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked

“Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software

(EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on

Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by

01 00 00 - 9 the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

1. Exterior Working spaces are to be fully maintained to include securing fencing, providing fabric screening on fencing, controlling dust through application of water as required, protecting the site with the use of rock, gravel material to control dust and erosion.

E. Workmen are subject to rules of Medical Center applicable to their conduct. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), 01 00 00 - 10 they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the

Contractor.

H. Phasing: Execute work so as to interfere as little as possible with normal functioning of Medical

Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

Pre-Phase I: Construct alternate pedestrian route and commission for use. See drawings for additional information.

Phase I: Construct primary pedestrian route, (Phase I section as shown on drawings), chillers, and infrastructure. Remove temporary canopy from alternate route if ADD ALTERNATIVE 01 is not executed. See drawings for additional information.

Phase II: Construct primary pedestrian route and infrastructure. (Phase II section) See drawings for additional information.

Phase III: Construct primary pedestrian route and infrastructure. (Phase II section) See drawings for additional information.

01 00 00 - 11

I. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees

F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

J. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; it is anticipated that no more than an 8 hour loss of chilled water should occur with this project. Contractor’s proposed schedule shall reflect this limitation.

Contractor shall provide temporary chilled water if this 8 hour chilled water disruption is exceeded. This project shall be scheduled with night and weekend work for all utility interruptions and

1. No utility service such as water, gas, steam, chilled water, sewers, electricity, fire protection systems, security systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de- energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 22 05 11

Common Work Results for Plumbing, 23 05 11 Common Work results for HVAC, 26

05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11REQUIREMENTS

FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS

FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date

01 00 00 - 12 and/or time such interruption will cause least inconvenience to operations of Medical

Center. Interruption time approved by Medical Center may occur at other than

Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the

Government and not the Contractor.

K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from.

The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

L. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

M. Coordinate the work for this contract with other construction operations as directed by

COR. This includes the scheduling of traffic and the use of roadways, as specified in

Article, USE OF ROADWAYS.

A. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR

52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).

B. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against

01 00 00 - 13 water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is complete

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the

COR of site, buildings and areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting

Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas and buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and

COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition

01 00 00 - 14 survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the

Government. When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

01 00 00 - 15

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The

Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the

Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work

(walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be

01 00 00 - 16 patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING

SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the Contractor's information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications, are the result of site investigations by Earth Systems Pacific, dated October 16, 2013.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report is included as Appendix to the GENERAL REQUIREMENTS and shall be considered part of the contract documents.

D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

01 00 00 - 17

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the

Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-

17)

B. Establish and plainly mark center lines for each corner of column lines and/or connection to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a

01 00 00 - 18 registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each canopy in relation to existing, adjacent buildings.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying

Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

E. Contractor is to provide a LIDAR survey of the renovated area and the interstitial spaces above and below the affected area as part of the close out process. This LIDAR survey will serve as documentation that the work was completed and shall work in conjunction with the as-built drawings. The unregistered (raw) point cloud data and registered, linked, point cloud model shall be turned over the Government at project close out.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration;

performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

01 00 00 - 19

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent…

This is the start of the file's text. The full file is on GovTribe.