About this file

This document is an amendment to a solicitation for fire sprinkler testing services. The Department of Veterans Affairs VISN 7 Network Contracting Activity is seeking proposals for inspection, testing, and maintenance of fire sprinkler systems at its facilities. Proposed work includes annual inspections, testing of waterflow devices, and necessary repairs. The solicitation requests that technicians be authorized by Johnson Controls or have a Simplex fire alarm license. An equipment list, recent inspection reports, and facility blueprints are attached. The prime contractor must meet all insurance requirements without relying on a subcontractor. Proposals are due by March 20, 2024 at 12:00 PM Eastern with no site visit scheduled. The amendment provides questions and answers from potential offerors and clarifies that all other solicitation terms remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to Fire Sprinkler Testing, newest first.
File Type Posted
BLDG 125 ASBUILT.pdf PDF
Bldg 128 As-Builts.pdf PDF
2022-06-06_Fort-McPherson-VAMC-Bldg-131_Annual Report.pdf PDF
2023-05-18_Fort-McPherson-VAMC-Bldg-128_SprinklerScan.pdf PDF
Ft. McPherson Bldg 128 Fire Alarm Drawings - RECORD Dwg.pdf PDF
FIRE SUPPRESSION.pdf PDF
BLDG 131 ASBUILTS.pdf PDF
2022-06-20_Fort-McPherson-VAMC-Bldg-129_Annual Report.pdf PDF
2023-02-09_Fort-McPherson-VAMC-Bldg-125_SprinklerScan.pdf PDF
FIRE ALARM 130.pdf PDF
2022-06-20_Fort-McPherson-VAMC-Bldg-128_Annual Report.pdf PDF
FIRE ALARM 129.pdf PDF
2023-05-18_Fort-McPherson-VAMC-Bldg-130_SprinklerScan.pdf PDF
2023-02-09_Fort-McPherson-VAMC-Bldg-130_SprinklerScan.pdf PDF
FIRE ALARM 125.pdf PDF
03 Series LIFE SAFETY - 100 AT-130 Fort McPherson Residental Treatment.pdf PDF
04 Series DOORS - 100 AT-125 Fort McPherson OPC.pdf PDF
2022-08-15_Fort-McPherson-VAMC-Bldg-130_SprinklerScan.pdf PDF
2022-08-15_Fort-McPherson-VAMC-Bldg-128_SprinklerScan.pdf PDF
2023-02-09_Fort-McPherson-VAMC-Bldg-131_SprinklerScan.pdf PDF
FIRE SUPPRESSION 131.pdf PDF
03 Series LIFE SAFETY - 100 AT-131 Fort McPherson Domiciliary Care.pdf PDF
05 series dampers - 100 at-125 fort mcpherson opc.pdf PDF
04 Series DOORS - 100 AT-130 Fort McPherson Residental Treatment.pdf PDF
2022-06-06_Fort-McPherson-VAMC-Bldg-125_Annual Report.pdf PDF
03 Series LIFE SAFETY - 100 AT-125 Fort McPherson OPC.pdf PDF
03 Series LIFE SAFETY - 100 AT-128 Fort McPherson Homeless Program.pdf PDF
04 Series DOORS - 100 AT-128 Fort McPherson Homeless Program.pdf PDF
BLDG 129 ASBUILT.pdf PDF
2023-05-18_Fort-McPherson-VAMC-Bldg-125_SprinklerScan.pdf PDF
2022-06-06_Fort-McPherson-VAMC-Bldg-130_Annual Report.pdf PDF
2023-02-10_Fort-McPherson-VAMC-Bldg-128_SprinklerScan (1).pdf PDF
BLDG. 125 FIRE SUPPRESSION.pdf PDF
04 Series DOORS - 100 AT-131 Fort McPherson Domiciliary Care.pdf PDF
2023-05-18_Fort-McPherson-VAMC-Bldg-131_SprinklerScan.pdf PDF
2023-05-18_Fort-McPherson-VAMC-Bldg-129_SprinklerScan.pdf PDF
2022-08-15_Fort-McPherson-VAMC-Bldg-131_SprinklerScan.pdf PDF
36C24724Q0269.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODECODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

36C247

Department of Veterans Affairs VISN 7 Network Contracting Activity 501 Greene Street Hatcher Building - Suite 2 Augusta GA 30901

Department of Veterans Affairs VISN 7 Network Contracting Activity 501 Greene Street Hatcher Building - Suite 2 Augusta GA 30901

To all Offerors/Bidders

36C24724Q0269

03-13-2024

X

X X

March 20, 2024 by 12:00 PM ET

The purpose of this Amendment is to post questions and answers submitted and to post requested attachments.

No site visit will be held for this requirement.

All other terms and conditions shall remain unchanged.

Jacob A. Tackett Contracting Officer

CONTINUATION PAGE

Questions and Answers:

1. In regards to the following, was this from the original scope for installation or are they looking for people that are currently certified for JCI?

“The service contractor shall have NICET-certified inspectors and Johnson Controls fire protection systems authorized partnerships that ensure technicians have the required training on the Fire Alarm System and provide OEM-issued Johnson Controls/Tyco certificates for documentation of training.”

The technician should be authorized by JCI or have a Simplex License to program the fire alarm panel.

2. Please provide an equipment list (with quantities).

See attachments

3. Please provide the most recent annual inspection report.

See attachments

4. Is there an incumbent?

No, this is a new contract

5. If so, what is the name of the vendor and was the contract award amount?

New contract

6. Will previous inspection reports be provided?

See attachments

7. Will blueprints be provided?

See attachments

8. Does the Prime need to have liability insurance or will the sub suffice?

All insurance requirements must be met by the Prime contractor

9. Will a site visit be scheduled?

No