071352 Modified Bituminous Sheet Waterproofing.pdf
PDF 101 KB Posted
- Solicitation number
- 36C24224R0071
About this file
This document is a Request for Proposals (RFP) for a construction project to build a new Emergency Department at the Stratton VA Medical Center in Albany, NY. The project includes demolition, site work, general construction, mechanical, plumbing, electrical, and other work for the new facility. The successful offeror must begin work within 15 calendar days of the notice to proceed and complete the project within 550 calendar days. Key requirements include providing a competent, 30-hour OSHA certified superintendent dedicated full-time to this project, utilizing the Autodesk Build construction management platform, and completing commissioning and punch list items within the period of performance. The solicitation is issued by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 2.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMUEL S. STRATTON VA MEDICAL CENTER
DESIGN NEW EMERGENCY DEPARTMENT
VA PROJECT NO. 528-809
01-01-21
07 13 52 - 1
SECTION 07 13 52
MODIFIED BITUMINOUS SHEET WATERPROOFING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Modified bituminous sheet material used for exterior below grade waterproofing and wall cavity waterproofing.
1.2 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. Federal Specifications (Fed. Spec.):
UU-B-790A Notice 2 v04-1992 Building Paper, Vegetable Fiber: (Kraft, Waterproofed, Water Repellent, and Fire
Resistant).
C. ASTM International (ASTM):
C578-19.................Rigid, Cellular Polystyrene Thermal Insulation.
D41/D41M-11(2016).......Asphalt Primer Used in Roofing, Dampproofing and Waterproofing.
D4586/D4586M-07(2018)...Asphalt Roof Cement, Asbestos-Free.
D6380/D6380M-03(2018)...Asphalt Roll Roofing (Organic Felt).
D. American Hardboard Association (AHA):
A135.4-(r2020)..........Basic Hardboard.
1.3 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Submittal Drawings: Show size, configuration, and installation details.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Installation instructions.
3. Warranty.
D. Samples:
1. Waterproofing and Flashing Sheet: 200 mm (8 inch) square, each type and color.
2. Insulation: 200 mm (8 inch) square.
E. Test reports: Certify products comply with specifications.
F. Certificates: Certify products comply with specifications.
G. Qualifications: Substantiate qualifications comply with specifications:
1. Installer with project experience list.
07 13 52 - 2
1.4 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified products.
2. Installed specified products with satisfactory service on five similar installations for minimum five years.
a. Project Experience List: Provide contact names and addresses for completed projects.
1.5 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
1.6 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight conditioned facility.
B. Protect products from damage during handling and construction operations.
1.7 FIELD CONDITIONS
A. Environment:
1. Product Temperature: Minimum 4 degrees C (40 degrees F) for minimum
48 hours before installation.
2. Weather Limitations: Install waterproofing only during dry current and forecasted weather conditions.
1.8 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
B. Manufacturer's Warranty: Warrant waterproofing system against material and manufacturing defects and agree to repair any leak caused by a defect in the waterproofing system materials or workmanship of the installer.
1. Warranty Period: 10 years.
PART 2 - PRODUCTS
2.1 SYSTEM DESCRIPTION
A. Waterproofing System: Modified bituminous sheet material for exterior waterproofing.
2.2 PRODUCTS - GENERAL
A. Provide each product from one manufacturer.
07 13 52 - 3
2.3 BITUMINOUS SHEET
A. Cold applied waterproofing membrane composed primarily of modified bituminous material prefabricated in sheet form designed for below grade exterior and cavity waterproofing. Sheet reinforced with fibers at manufacturer's option.
B. Thickness: Not less than 1.5 mm (60 mils), plus or minus 0.13 mm
(5 mils), and bonded to 0.1 mm (4 mil) thick plastic sheet.
C. Provide release sheet to prevent bonding of bituminous sheet to itself.
2.4 PROTECTION MATERIAL
A. Polystyrene Insulation: ASTM C578, Type I or VIII, 13 mm (1/2 inch) minimum thickness or as specified on drawings to meet required R-value.
B. Hardboard: AHA A135.4, Service Type, 6 mm (1/4 inch) thick.
C. Waterproofed Building Paper: Fed. Spec. UU-B-790A Notice 2, Type I, Grade C.
D. Roll Roofing: ASTM D6380/D6380M, Class S (smooth), Type III with minimum net mass per unit area of roofing, 2495 g/sq. m
(51 lbs./100 sq. ft.).
2.5 ACCESSORIES
A. Patching Compound: Factory-prepared, non-shrinking, fast-setting, cementitious adhesive compound containing no ferrous metal or oxide.
B. Primer: ASTM D41/D41M.
C. Roof Cement: ASTM D4586/D4586M.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for product installation.
1. Concrete surfaces cured minimum time recommended by waterproofing manufacturer.
2. Substrate to be dry as recommended by waterproofing manufacturer.
B. Protect existing construction and completed work from damage.
C. Correct substrate deficiencies.
1. Fill voids, joints, and cracks with patching compound.
D. Clean substrates. Remove contaminants capable of preventing full adhesion.
E. Priming:
1. Prime concrete and masonry surfaces.
07 13 52 - 4
2. Application method, amount of primer and condition or primer before installation of bituminous sheet as recommended by primer manufacturer.
3. Reprime when required according to manufacturer's instructions.
3.2 INSTALLATION - GENERAL
A. Install products according to manufacturer's instructions and approved submittal drawings.
1. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's Representative consideration.
3.3 WATERPROOFING INSTALLATION
A. Bituminous Sheet Installation:
1. Remove release sheet before application.
2. Lay bituminous sheet from low point to high point so laps shed water.
3. Treat expansion, construction and control joints and evident working cracks as expansion joints. Apply bituminous sheet in double thickness over joint by first applying a strip of bituminous sheet minimum 200 mm (8 inches) wide, centered over joint.
4. Lap seams minimum 50 mm (2 inches).
5. Lay succeeding sheet with laps, and roll or press into place.
6. Repair misaligned or inadequately lapped seams according to manufacturer’s instructions.
7. Seal seams and terminations according to sheet manufacturer’s instructions.
B. Corner Treatment:
1. At inside and outside corners, apply double cover using an initial strip minimum 280 mm (11 inches) wide, centered along axis of corner.
2. Cover each strip completely by the regular application of bituminous sheet.
3. Provide a fillet or cant on inside corners.
4. Form cants using patching compound.
5. Do not use wood, fiber, and insulating materials for cants.
C. Projection Treatment:
1. Apply a double layer of bituminous sheet around pipes and similar projections at least 150 mm (6 inches) wide.
07 13 52 - 5
2. At drains, apply a bead of roof cement over a double layer of bituminous sheet under clamping rings.
D. Patching:
1. Repair tears, punctures, air blisters, and inadequately lapped seams, according to manufacturer’s instructions before protection course is applied.
E. Permanent Protection:
1. Vertical Surfaces:
a. Install hardboard, polystyrene insulation, or roll roofing protection material.
b. Extend protection full height from footing to top of backfill.
c. If graded backfill is used, use roll roofing or hardboard.
F. Horizontal Surfaces:
1. Install roll roofing protection under concrete wearing courses.
2. Install roll roofing, hardboard, or polystyrene insulation under earth backfill.
3. Where no concrete wearing course occurs or when surfaces will bear heavy traffic and will not immediately be covered with a wearing course, use protection specified for vertical surfaces.
G. Temporary Protection:
1. When waterproofing materials are subjected to damage by sunlight and cannot be immediately protected as specified, protect waterproofing materials by waterproof building paper or suitable coating approved by manufacturer of waterproofing system used.
3.4 FIELD QUALITY CONTROL
A. Field Tests: Performed by testing laboratory specified in Section
01 45 29, TESTING LABORATORY SERVICES.
B. Testing:
1. Before any protection or wearing course is applied, test all horizontal applications of waterproofing with a minimum of 25 mm
(1 inch) head of water above highest point and leave for 24 hours.
2. Mark leaks and repair when waterproofing is dry.
3. Certify, to Contracting Officer's Representative, that water tests have been made and that areas tested were found watertight.
C. Inspection:
1. Do not cover waterproofed surfaces by other materials or backfill until work is approved by Contracting Officer's Representative.
07 13 52 - 6
3.5 CLEANING
A. Remove excess adhesive before adhesive sets.
B. Clean exposed waterproofing surfaces. Remove contaminants and stains.
3.6 PROTECTION
A. Protect waterproofing from construction operations.
B. Remove protective materials immediately before acceptance.
C. Repair damage.
- - - E N D - - -
File details come from the government source that posted it. Updated .