This document is a table of contents for the specifications of a project to design a new emergency department at the Samuel S. Stratton VA Medical Center in Albany, NY (VA Project No. 528-809).
The key details include:
- The project involves demolition, asbestos abatement, excavation, site work, exterior improvements, general construction, alterations, and work on the structural, mechanical, plumbing, electrical, fire alarm, sprinkler, and medical gas systems.
- The contractor must utilize the VISN 2 Autodesk Build Construction management platform for all project-related communications and collaboration at no cost.
- The period of performance is 550 calendar days from the notice to proceed.
- The contractor must provide a competent 30-hour OSHA certified superintendent dedicated solely to this project.
- Commissioning of all required items must be completed prior to training government staff and the final inspection/punch list.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMUEL S. STRATTON VA MEDICAL CENTER
DESIGN NEW EMERGENCY DEPARTMENT
VA PROJECT NO. 528-809
01-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS – March 18, 2022
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01-21
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 07-20
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 03-19
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 01-21
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 01-21
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
03 30 20 Concrete Slab on Grade 01-21
03 20 25 Concrete Slab on Metal Deck 01-25
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
04 72 00 Cast Stone Masonry 01-21
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
VA PROJECT NO. 528-809
01-01-21
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 16 63 Cementitious Sheathing 01-21
06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21
07 40 00 Roofing and Siding Panels 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 72 00 Roof Accessories 01-21
07 81 00 Applied Fireproofing 10-17
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 31 13 Access Doors and Frames 01-21
08 32 13 ICU Sliding Glass Doors 01-21
08 34 53 Security Doors and Frames 01-21
08 41 13 Aluminum-Framed Entrances and Storefronts 01-21
08 44 13 Glazed Aluminum Curtain Walls 04-20
08 51 13 Aluminum Windows 01-21
08 56 53 Blast Resistant Windows 01-21
08 56 59 Service and Teller Window Units 01-21
08 71 00 Door Hardware 01-21
08 71 13 Automatic Door Operators 01-21
08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 54 23 Linear Metal Ceilings 01-21
VA PROJECT NO. 528-809
01-01-21
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 05-18
09 65 19 Resilient Tile Flooring 05-18
09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and
RES 6B)
01-21
09 68 00 Walk-Off Mat Carpet 01-21
09 91 00 Painting 01-21
09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2)
01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 21 23 Cubicle Curtain Tracks 01-21
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
10 51 13 Lockers 06-14
DIVISION 11 – EQUIPMENT
11 12 00 Parking Control Equipment 01-21
11 73 00 Ceiling Mounted Patient Lift System 08-20
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 12-18
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
13 49 00 Radiation Protection 02-16
DIVISION 14– CONVEYING EQUIPEMENT
14 92 00 Pneumatic Tube System
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
VA PROJECT NO. 528-809
01-01-21
00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 11-19
22 13 00 Facility Sanitary and Vent Piping 09-20
22 14 00 Facility Storm Drainage 09-15
22 40 00 Plumbing Fixtures 09-15
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
02-20
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 02-20
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 02-20
23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 02-20
23 23 00 Refrigerant Piping 02-20
23 31 00 HVAC Ducts and Casings 02-20
23 34 00 HVAC Fans 02-20
23 36 00 Air Terminal Units 02-20
23 37 00 Air Outlets and Inlets 02-20
23 40 00 HVAC Air Cleaning Devices 03-20
23 73 00 Indoor Central-Station Air-Handling Units 03-20
23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20
23 81 23 Computer-Room Air-Conditioners 03-20
23 82 00 Convection Heating and Cooling Units 03-20
23 82 16 Air Coils 03-20
DIVISION 25 – INTEGRATED AUTOMATION – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 13 Medium-Voltage Cables 01-17
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 36.26 Wireways for Radiology Equipment 01-18
26 05 41 Underground Electrical Construction 01-17
26 05 73 Overcurrent Protective Device Coordination Study 01-18
VA PROJECT NO. 528-809
01-01-21
00 01 10-5
SECTION NO. DIVISION AND SECTION TITLES DATE
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 01-18
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 01-18
26 24 13 Distribution Switchboards 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 36 23 Automatic Transfer Switches 01-17
26 41 00 Facility Lightning Protection 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
26 55 71 Medical and Surgical Lighting Fixtures 01-18
26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Control, Communication and Signal Wiring 06-15
27 15 00 Communications Structured Cabling 01-16
27 31 31 Voice Communications Switching and Routing Equipment -
Extension
06-15
27 51 23 Intercommunications and Program Systems 06-15
27 52 23 Nurse Call and Code Blue Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 13 53 Security Access Detection 09-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
28 26 00 Electronic Personal Protection System 09-11
28 31 00 Fire Detection and Alarm 10-11
28 52 31 Emergency Call System 06-15
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
31 23 19 Dewatering 10-12
VA PROJECT NO. 528-809
01-01-21
00 01 10-6
SECTION NO. DIVISION AND SECTION TITLES DATE
31 63 29 Drilled Concrete Piers 01-21
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 17 23 Pavement Markings 08-16
32 31 13 Chain Link Fences and Gates 06-18
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES
33 08 00 Commissioning of Site Utility Systems 11-16
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
33 40 00 Storm Sewer Utilities 12-17
33 46 13 Foundation Drainage 10-11
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
DIVISION 48 – Electrical Power Generation – NOT USED