This document presents Special Conditions for Job Order Contracting (JOC) at Los Angeles World Airports (LAWA), modifying the standard General Conditions to reflect JOC-specific terminology and operational requirements. The contract covers supplementary construction and repair services at LAX and VNY with a combined estimated value of $6,000,000 over a three-year term. Work will be performed pursuant to individual Task Orders issued by LAWA, which may range from complete bid documents to partially defined scopes or general project needs. Contractors must possess valid California licenses in good standing with the California State Contractors Board, appropriate to the work scope. The order of precedence for contract document interpretation places Applicable Laws and Regulations first, followed by Permits, Executed Change Orders, the Contract Agreement, Special Conditions, General Conditions, Project Requirements, and supporting documentation. Task Order scope and pricing responsibilities fall entirely to the contractor, who must complete scoping and pricing in accordance with LAWA Technical Specifications.
Contractors operating at LAX must comply with extensive airport coordination requirements, including obtaining AOA (Air Operations Area) access credentials, restricted area driving passes, and badging from LAWA Airport Police. All vehicles operating on airport property must display company identification on both sides and pay monthly vehicle permit fees considered incidental to work costs. Vehicles extending above fifteen feet must have checkered flags and obstruction lighting per FAA standards. Security fencing work requires minimum three full-time badged security guards per gate or opening at contractor expense, with costs included in the bid and no separate payment made. Normal airport operational delays, including security badge processing and taxiway crossing delays, do not entitle contractors to time extensions; however, Engineer-ordered work suspensions due to weather or security issues provide non-compensatory time extensions for critical path work. Contractors must ensure Building Commissioning compliance with CALGreen Tier II standards and coordinate all start-up, testing, and training activities with subcontractors and suppliers.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL CONDITIONS
JOB ORDER CONTRACTING AT LAX
Los Angeles World Airports
SPECIAL CONDITIONS 1
SC-1 CHANGES TO THE GENERAL CONDITIONS
MODIFIES GC-2 ORDER OF PRECEDENCE AND CONTRACT INTERPRETATION
A. Conflicts in the application or interpretation of any parts of the Contract Documents that cannot be resolved shall be interpreted in accordance with the following order of precedence (the first listed being the highest precedence):
1- Applicable Laws and Regulations
2- Permits
3. Executed Change Orders (more recent controlling)
4. Executed Contract Agreement, including RFP
5. Special Conditions
6. General Conditions
7. Project Requirements
8. LAWA 2020 Design and Construction Handbook
9. Technical Specifications
10. Project Plans/Drawings (detailed plans having greater precedence)
11. Reference Documents
MODIFIES GC-3 CONTRACTING DEFINITIONS (the following definitions are edited to include JOC terminology)
CONTRACT DOCUMENTS – The RFP, executed Contract Agreement, Task Orders, the
General Conditions, Special Conditions, Administrative Requirements, Division 1 – Project
Requirements, Technical Specifications, Plans and Reference Documents.
CONTRACT TIME – The length of time the contractor is allowed to complete the work within the
Contract or Task Order milestones or schedule, as specified in the Task Order.
COST OF WORK – Cost necessarily and reasonably incurred by the contractor in the proper performance of the work only to the extent they are directly related to the Task Order.
MAXIMUM CONTRACT AMOUNT – The maximum amount that LAWA is obligated to pay to the
Contractor under the terms of this Contract or Task Order.
NOTICE TO PROCEED – The written notice by LAWA to the contractor notifying it to begin work on the Task Order or any component thereof.
WORK – The scope of work outlines by the Task Order which includes all labor, materials, equipment, services, subcontracts, permits, licenses and taxes, and other things necessary for the contractor to perform its obligations and complete the project.
GC-4 ABBREVIATIONS, ACRONYMS AND INITIALISMS (ADD)
RFP Request for Proposal
REPLACES GC-12 OWNER-FURNISHED DOCUMENTS AND SPECIFICATIONS
SPECIAL CONDITIONS ADVERTISED
Los Angeles World Airports
SPECIAL CONDITIONS 2
LAWA will furnish Task Order documents ranging in scope from the issuance of complete bid documents, to a partially defined scope of work, to telephonic/e-mail communication of a general project need. Contractor is responsible for complete scoping and pricing of the project as required in accordance with LAWA Technical Specifications.
GC-45 LIQUIDATED DAMAGES – DELETE
GC-75 FIRST SOURCE HIRING PROGRAM FOR AIRPORT EMPLOYERS – DELETE
SC- 2 VALID CALIFORNIA CONTRACTORS LICENSE
Each subcontractor selected for the Work shall possess valid California Licenses in good standing with the California State Contractors Board, appropriate for the portion of the Work that will be accomplished by each subcontractor.
SC-3 AIRPORT COORDINATION
A. The Contractor shall comply at all times with any and all oral and /or written instructions by LAWA Engineer and Inspector regarding routes of travel to be used in moving personnel and/or materials to and from the construction site. The deliveries of materials and removal of construction related debris may be required to be done at night. The
Contractor shall work with the Engineer on the schedule of any night work that needs to be performed on LAWAs property.
B. The Contractor shall contact the Airport police, Security Technology Section, Telephone
(310) 646-0508 regarding specific requirements for the operation of vehicles on airport property and for LAWA drivers’ licenses and photo I.D. badges. No passenger cars will be permitted in the restricted area of the Airport. Employees’ personal vehicles shall be parked in public lots or off the Airport. Employees shall be transported from there to the
Site in vehicles provided and supervised by the Contractor. The Contractor shall follow
LAWA badging and driving instructions per Badging Policies and Procedures at LAWA.
C. The Contractor is responsible for payment of monthly vehicle permit fees, the cost for which is considered incidental to the work. Each vehicle or unit of equipment that travels or operates on any part of the AOA shall have an approved decal or painted company name applied to both sides of the vehicles in a location opposite the driver’s seat. The identification should be applied to the front door panels. Magnetic or temporary signs are not acceptable. The name of the company should be spelled out in letters no less than three (3) inches high. Use of logos or symbols in lieu of letters is subject to approval by the Airport Operations Manager.
D. Each vehicle or piece of equipment anywhere on the airport that extends higher than fifteen (15) feet above ground shall be equipped with a checkered flag mounted firmly on the highest part of the vehicle, and shall be obstruction lighted per FAA Advisory Circular
70/7460-1K, Obstruction marking and Lighting, when the visibility is less than three (3)
SPECIAL CONDITIONS 3
miles. This flag shall be three (3) feet square overall and comprised of nine (9) panels, each one being one (1) foot square. The corner and center panels shall be international orange in color, and the remaining four panels shall be white.
E. Delivery vehicles, materials trucks, and heavy equipment shall enter and depart through a point designed by the Engineer. Except as otherwise directed or approved by the
Engineer, vehicles in use on the airport shall be confined to the construction area work
Site. Only operators with current restricted area driving passes issued by the LAWA
Airport Police, Security Technology Section, will be permitted to operate vehicles in the
AOA. When an operator does not have a current pass, a LAWA authorized driver must escort the operator.
F. The maximum vehicular speed allowed at various locations will be established by the
Airport Operations Manager. Vehicles shall be under safe control at all times, weather and traffic conditions being considered. No vehicle shall at any time be permitted to interfere with or endanger aircraft traffic.
G. Any airport security fencing to be relocated or installed is important to the security of the
Airport. The Contractor shall schedule the Work to ensure security at all times. Any temporary openings in the airport security fence to facilitate access, relocation, and/or replacement shall be assigned full-time, badged security guards at the Contractor’s expense. At each gate or fence opening, the Contractor shall provide a minimum of three gate guards equipped with cell phones or radios, portable lights, and guard shack.
The cost for security guards shall be considered incidental; therefore, no separate payment will be made and shall be included in the Bid. At each gate or fence opening, the Contractor shall provide a minimum of three gate guards equipped with cell phones or radios, area lighting, portable flash lights, and guard shack.
SC-4 DELAYS
A. Normal delays to be expected while operating on an active airport shall not entitle the
Contractor to time extensions. Such normal delays include, but are not limited to, delays in obtaining security badges, delays in obtaining AOA access, delays in crossing active taxiways, and delays due to periodic holding of truck traffic through NAVAID critical areas on the haul road. Whenever the Engineer orders a temporary suspension of Work due to unsuitable weather conditions or security issues, the Contractor shall be entitled to a non-compensatory extension of time equal to the duration of the suspension, provided the suspension applies to work on the critical path.
SC-5 COMMISSIONING
A. The Contractor shall become familiar with the design intent for each of the relevant building systems (including airport/aircraft support systems and infrastructure) and
SPECIAL CONDITIONS 4
equipment and incorporate the established critical performance criteria into its start-up, testing and training activities.
B. The Contractor shall clearly define all duties and activities required of the various subcontractors relating to Building Commissioning, any necessary order in which these activities and duties must take place, and define all critical performance criteria to be achieved.
C. The Contractor shall coordinate and prepare all start-up, testing and training activities with its subcontractors, suppliers and work force to ensure timely and well-prepared commissioning.
D. The Contractor shall ensure that all necessary documentation required in the CALGreen
Tier II standard is provided to LAWA.
END OF SPECIAL CONDITIONS