National Museum of American History PSRP IV Collection Move
Solicitation number
33330225RF0010008
Issued by

About this file

This document is an Amendment (0003) to a Smithsonian Institution solicitation for the National Museum of American History (NMAH) PSRP IV Collections Move project. The amendment extends the bid due date to Tuesday, April 1, 2025, at 3:00 PM EST and includes responses to 47 Request for Information (RFI) questions covering topics such as project logistics, safety requirements, transportation specifications, and collections handling procedures. Key clarifications include confirmation that the project involves moving museum collections from NMAH to the Suitland Collections Center, with specific requirements for transportation (air-ride suspension, climate control, dual drivers), rigging, and collections processing.

The amendment provides detailed guidance on project expectations, including restrictions on simultaneous work spaces (2-4 rooms), requirements for specialized personnel like a full-time Quality Control Manager, and protocols for handling various collection types. Noteworthy details include provisions for open-load transit of oversized artifacts under strict weather conditions, specifications for protective coverings like Nomex, and confirmation that NMAH staff will handle exhibit case openings and inert artifact preparation. The project has subcontracting goals of 40% with small businesses, including specific allocations for disadvantaged, women-owned, veteran-owned, and hub-zone businesses, with an estimated total project value exceeding $10 million and a 1,095-day performance period.

View the file

Other files

File Type Posted
33330225RF0010008 Amendment 0007.pdf PDF
143101 PRSP IV Collection Move Bid Schedule - REVISED 2025.07.xlsx XLSX spreadsheet
33330225RF0010008 Amendment 0006.pdf PDF
NMAH_Collections Move Bid RFIs_reponses_FollowUponly_250320.pdf PDF
AHB 2301_yellowForUncrating.pdf PDF
NMAH_Collections Move Bid RFIs_reponses_all_250320.xlsx XLSX spreadsheet
NMAH_Collections Move Bid RFIs_reponses_all_250320.pdf PDF
NMAH_Collections Move Bid RFIs_reponses_FollowUponly_250320.xlsx XLSX spreadsheet
33330225RF0010008 Amendment 0005.pdf PDF
AHB 2301_yellowForUncrating.xlsx XLSX spreadsheet
2024 12 02 1403102_PSRP IV Collections Move_Multi-Year funding Document - R1 (Final).docx DOCX document
NMAH_Collections Move Bid RFIs_reponses_250314_all.pdf PDF
NMAH Collections Move Schedule_r1_250314.pdf PDF
33330225RF0010008 Amendment 0004.pdf PDF
NMAH_Collections Move Bid RFIs_reponses_250314_all.xlsx XLSX spreadsheet
NMAH_Collections Move Bid RFIs_reponses_250314_revisedOnly.xlsx XLSX spreadsheet
25-03_13_PSRP4_CollectionsMove_PreBidRFIs_responses.xlsx XLSX spreadsheet
1403101_132000_PROTECTION OF EXHIBITS AND COLLECTIONS.pdf PDF
25-03_11_PSRP4_CollectionsMove_PreBidRFIs_responses.xlsx XLSX spreadsheet
Pod6_StorageEquipment_Conformed_color.pdf PDF
PSRP IV_AHB ROOM MAPS_LEGEND.pdf PDF
NMAHequipment.pdf PDF
33330225RF0010008 Amendment 0002.pdf PDF
Jeep_WTCsteelDetails.pdf PDF
PSRP4 Object Damage Incident Reporting.pdf PDF
SI Magazine article_Huey install.pdf PDF
Creating Condition Reports during PSRP4 Move.pdf PDF
huey dimensions and schematic (1).jpg JPG image
scan3 huey platform.zip ZIP file
NMAH Plans-WorkAreas_with openingDims.pdf PDF
PSRP IV Inventories_All_Final for RFP.xlsx XLSX spreadsheet
PSRP IV_Inventory Lists_By Room_Excel.zip ZIP file
33330225RF0010008 Amendment 0001.pdf PDF
1403101 NMAH PSRP IV Collections Move Solicitation Document.docx DOCX document
01_1403101_PSRP IV Collections Move_Specs.pdf PDF
Payment Bonds.pdf PDF
Contractor_COVID-19_Safety Protocols_LOW_3.30.22-eg.pdf PDF
Service Contract Act.pdf PDF
04_Appendices.pdf PDF
Clauses_33330225RF0010008.pdf PDF
Davis Bacon Building.pdf PDF
Davis Bacon Heavy.pdf PDF
2024 12 02 1403102_PSRP IV Collections Move_Multi-Year funding Document.docx DOCX document
Release of Claim Form.pdf PDF
Performance bonds.pdf PDF
02_NMAH Plans-WorkAreas.pdf PDF
143101 PRSP IV Collection Move Bid Schedule.xlsx XLSX spreadsheet
03_RoomInventories_Bookmarked.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, xis not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

A. The Solicitation Number cited above, National Museum of American History (NMAH) PSRP IV Collections Move, located in Washington, DC, is hereby amended as follows:

A.1. Attached hereto and made part of this Amendment Three are SI Responses to 47 RFI Questions. The Excel version is available for download in the SAM Attachments section.

B. Offerors shall acknowledge receipt of all amendments to this solicitation signed and dated and submit with proposal.

C. Questions or Clarifications due date is extended to March 18, 2025.

Continued ...

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Christine Grant

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

(x)

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED

33330225RF0010008/0003

PAGE OF

2 9

NAME OF OFFEROR OR CONTRACTOR

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

D. THE BID DUE DATE IS TUESDAY, APRIL 1, 2025, AT

3:00PM EST.

E. ATTACHMENTS (available in the SAM Attachments section)

- Excel file for RFI dated 03/11/2025

- Section 132000 - Protection of Exhibits and Collections

- Pod 6 Storage Equipment Conformed Color

- PSRP IV AHB Room Maps Legend

Except as provided herein, all other provisions, terms and conditions of the Solicitation remain unchanged.

END OF AMENDMENT THREE

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

SI RFI Tracking Number Reference QUESTION FINAL RESPONSE SI-RFI-100 Is there any ether in the chemicals/medicines collection?

Yes, the medical and science collection contains ether and other specimen preservation chemicals. Refer to Division 1

(010000-50) Personal Protective Equipment.

SI-RFI-11 What is the difference in the roles and duties of

Contractor Quality Control Manager and the Lead On-

Site Project Manager? Can they be fulfilled by the same person?

Refer to RFP language and Division 1 requirements for

Quality Control and Project Management. Refer to SI-RFI-

215 response.

SI-RFI-111 Will there be any conflict w/ other SI or NGA moves into

POD 6?

Access to Pod 6 for loading and freight elevator scheduling will need to be coordinated with SI. SI has a dedicated at-grade rolling door (1st floor) at Pod 6 that will be available most days, but also must be coordinated with deliveries to other bays.

SI-RFI-114 Can we get a copy of the population plan? Refer to SI-RFI-204 response

SI-RFI-118 List of artifacts that will need a submittal and will submittal(s) need to be engineer stamped

All project submittals are listed in Specifications. For rigging requirements refer to Section 0224400 1.4.H. & 3.7

SI-RFI-12 Can the role of the Safety Coordinator (Safety

Coordinator: Completed OSHA 30-hour course and on site at all times with a minimum of five (5) years’ experience in similar projects of this scope and magnitude) be fulfilled by the Lead On-Site Project

Manager?

The Project Safety Coordinator can also be the project supervisor or art handler, if they meet the training and experience requirements identified in the specifications.

SI-RFI-123 Is there a limit to the number of spaces the contractor can be working in at any given time? PG 8 (3)

Due to the existing conditions constraints of processing space, swing space and NMAH staff support, as well as the challenges of working in an operating museum, SI believes that somewhere between 2 and 4 rooms can be worked in simultaneously.

SI-RFI-14 Are we responsible for disposal or removal of exhibition display furniture? Similarly, will we be responsible for packing and transporting any exhibition display

Refer to SI-RFI-43 Response.

SI-RFI-141 Regarding CB069 Hazardous materials, please clarify what mitigation efforts will be required by the contractor

vs. what will be in place prior to the move?

Contractor will be made aware of any existing hazards for proper PPE for handling of the objects. (Refer to Division 1

(010000-50) Personal Protective Equipment.

SI-RFI-143 Crated Objects: Other than tall clocks (noted above), objects crated for move will remain crated and stored on

Level 1 of Pod 6, in Open

Storage area or on adjacent tall object shelves.

Is there a height determination that defines this category? If so, please provide the height limit for shelved collections. For instance something may be packed onto a pallet but be too tall for racking or shelving.

Refer to attachment

"Pod6_StorageEquipment_Conformed_color.pdf" showing shelving elevations. Crated or Palletized objects which are too tall for practical storage on shelving shall be located on the 1st Floor in the "Open Floor Storage" area.

ChanVC Typewriter Date: 03/13/2025

SI-RFI-146 SCHEDULE OF OPTIONS

FOR PROPOSAL

Please confirm if there are any hazardous materials in the archive collection that the bidders should be aware of.

No hazards in Archive collection.

SI-RFI-15 In reference to the 02_NMAH Plans-WorkAreas document, can you please provide the legend for the color-coded areas for pages 7-27?

Refer to attachment PSRP IV_AHB ROOM

MAPS_LEGEND.pdf

SI-RFI-16 If anything is pre-packed, is the Contractor expected to repack in a similar manner?

All objects in 2301 (refer to

RoomInventories_Bookmarked.pdf) were very recently packed, have up-to date condition reporting, and do not need to be repacked by the contractor. Assume other crates outside of 2301 will require visual inspection, processing and photography. For pricing purposes, assume new crating/retrofitting will be required for existing rooms other than 2301.

SI-RFI-165 As-Built Record

Specifications Submitted:

During the course of the

Work, the Contractor shall maintain a complete and up-to- date set of records, open to inspection by the COTR at any time. These records shall provide a complete and accurate as-built record of all changes to the Contract

Documents, including revisions to any rigging plans, disassembly plans, packing plans, move transport plans

Please confirm that bidders should not include costs associated with providing individual packing plan submittals per artifact in this scope.

All project submittals are listed in Specifications. Refer specifically to Section 0224400 for move plan submittal requirements.

SI-RFI-177 For the Armament Collections Specialist, please expand on the specific tasks and skills that are expected of these individuals. Is this just experience packing and handling armament as part of a museum collection? Do the firearms need to be made safe, ie removal of firing pins? And / or does additional cataloguing data need to be provided for Mimsy XG database fields? Please clarify the specific tasks that the museum envisions this specialist performing.

Armaments specialist not required. NMAH has/will ensure that objects are made safe prior to packing. These objects do not require any different or additional XG cataloging data.

SI-RFI-181 Please confirm that if oversized artifacts are too large to travel in an enclosed vehicle that they must be protected for open load transit. If yes, please provide specifications for open load protection.

Contractor to identify objects they believe may require open load transit. For those objects, open trailer loads can be scheduled only under acceptable road and weather conditions, as determined by NMAH, in which there is no precipitation or road spray. The requirements are 0% moisture on the ground at the time of the operation; 10% or less chance of precipitation; and no chemical residue i.e.

road treatments on the roads. The go/no-go call can be made up to 24 hours in advance of the day of move, however, it is understood that if the weather or outlook changes, the transport maybe cancelled as determined by authorized

Collections personnel. Open loads shall only be approved when an enclosed load is not possible. The trailer shall be secured with tamper resistant seal prior to transit. Level of protection for artifacts travelling as open loads shall be determined by the type of artifact, its materials, level of fragility, dimensions, and shape as necessary, and as approved by NMAH to protect it during transport.

SI-RFI-191 Nomex coverings may be required for artifacts on aluminum pallets and shall be incorporated into the overall submittal as required.

Please provide a list of which artifacts shall require

Nomex covers. Additionally, provide a specification for the type of Nomex required.

Refer to RoomInventories_Bookmarked.pdf. For all furniture identified for palette, provide Nomex cover.

SI-RFI-193 Please provide AIA Document A-305 for bidders to include int their technical proposal.

Contractor can purchase from AIA.org

SI-RFI-198 Who deinstalls, demos and/or disposes of exhibitry to create a path for larger artifacts to exit the galleries?

Refer to SI-RFI-43 Response. Contractor to detail in the

Plan of Accomplishment which large items may require additional demolition for removal and indicate preferred pathway to freight elevator. SI will arrange for or procure demolition services at the appropriate time.

SI-RFI-199 Please confirm that during select demolition of exhibitry to facilitate deinstallation of oversized artifacts, the MC will be required to protect-in-place any affected artifacts.

Please additionally provide specifications for protection.

Remove all non-oversized collections prior to removing oversized collections. For the oversized object for which demolition is required, objects must be protected in place.

Refer to Attachment SECTION 132000 – PROTECTION OF

EXHIBITS AND COLLECTIONS

SI-RFI-204 • Overseeing contractors to remove boxed collections from shipping containers and store them on pallet racking and in cabinets at the SCC, and updating final location data;

Please confirm if NMAH will be providing a population plan for the collections storage space at the SCC or if the contractor will be responsible for planning this. If

NMAH will be providing this document, please provide so that deinstall, packing and transport sequence required to facilitate the population plan may be considered and factored into the cost proposal.

NMAH mapped collections from AHB to Pod 6 by store room.

Specifics will be determined upon arrival at Pod 6. Refer to color coded attachement

Pod6_StorageEquipment_Conformed_color.pdf

SI-RFI-205 • Coordinating disposal of old cabinetry and containers as they are emptied and the collections are housed and packed, and shipped to SCC for storage on or in new rack and cabinets;

Please confirm that the MC will only be responsible for coordinating with the COTR and other relevant stakeholders for the removal and disposal of old cabinetry and is not directly responsible for the physical removal and disposal. If the MC is required to provide all labor and equipment to physically remove and dispose of the old cabinetry, then please provide a complete list of cabinetry and volume identified for disposal. Please confirm that the contractor will be responsible for providing a dumpster on site to support this and that contractor staff will be responsible for moving old storage cabinets from the collections storage space and placing them in said dumpster.

Please additionally confirm that there are no hazardous materials associated with old cabinetry such as arsenic.

Refer to SI-RFI-31 Response.

SI-RFI-208 1. The truck shall be equipped with air ride suspension, a working lift gate, pallet jacks, dual drivers, Constant

Surveillance Service, and climate control.

Please confirm that the requirement of "Constant

Surveillance Service" is met by the dual driver requirement and locked and alarmed trucks. If not please clarify what would meet this requirement.

Dual driver requirement and locked and alarmed trucks are sufficient to meet security requirements. SI-OPS guard will attend both the loading and unloading points.

SI-RFI-209 3. Smithsonian may monitor truck temperature, humidity

GPS location and shock readings.

Please confirm if the contractor should plan to provide

GPS location tracking at an additional cost to the

Smithsonian or if Smithsonian will be providing a GPS tracker to place with each shipment.

Contractor is not required to provide GPS location tracking.

SI-RFI-212 Safety Coordinator:

Completed OSHA 30-hour course and on site at all times with a minimum of five

(5) years’ experience in similar projects of this scope and magnitude.

Please confirm that a Site Supervisor who is also an Art

Handler can serve in this capacity

Refer to SI-RFI-12 response

SI-RFI-215 Contractor Quality Control

Manager: Minimum five (5) years’ experience in a museum environment performing services of a similar size, scope and complexity to the project.

Please confirm that this is intended to be a full time role dedicated to this project and that the person serving in this role cannot be serving in any other capacity, such as Registrar, Site Supervisor or Lead PM

Yes, Quality Control Manager must be a full time role dedicated to this project and the person serving in the role cannot be serving in another capacity, such as Registrar, Site Supervisor Lead PM.

SI-RFI-216 Technical: Provide a completed Contractor's

Qualifications Statement (AIA

Document A-305) and the latest certified audit report.

Please prove AIA Document A-305 for bidders to include in their technical proposal.

Refer to SI-RFI-193 response

SI-RFI-22 In reference to the 03_RoomInventories_Bookmarked document, are there any objects that frequently travel on loan or would require a more holistic or robust approach to its packing? Does SI anticipate any of these will be loaned out during the timeline of the project?

All objects on Room Inventory list should be packed for storage per Specifications. Refer to Division 6 (062999-2.2)

Housing for Conveyance

SI-RFI-225 Who is responsible for opening exhibit cases and/or removing vitrines in the exhibit spaces?

NMAH staff will open exhibit cases and/or open vitrines for access to objects. Coordinate with COTR when access is required. Refer to Specification Sections 010000 and 024400 for coordination time requirements.

SI-RFI-226 Please confirm that all armament included in this scope are inert and / or have had the firing pins removed and made safe.

All ordnance will be confirmed inert before movement

SI-RFI-26 There is a note that NMAH requires access to temp & humidity logs for all transportation. Does this mean live access to logs, and if so is NMAH going to provide temp

& humidity trackers for trucks?

Tracking of temperature and humidity is not required by the move contractor.

SI-RFI-27 Can the vendor assume that aside from the clocks, all pre-packed items should be unpacked for registration and processing, and repacked by the vendor?

Refer to SI-RFI-16 Response.

SI-RFI-28 Which NMAH staff member(s) will decide whether an item will need better housing/new fabrication? What will the work-order process be when damage is discovered or inadequate housing needs replacing?

Refer to SI-RFI-16 Response.

SI-RFI-31 For the disposal requested, approximately how much of the old furniture and cabinetry will need to be disposed of? Can you provide an estimated number/square footage/cubic feet for disposal?

This contract excludes "old furniture & cabinetry" disposal which will be performed by SI.

SI-RFI-33 In reference to the 03_RoomInventories_Bookmarked document, what does the “Rehousing Details”, “Crate”, “BB Box”, and “Pallet” columns mean? Does the data in these columns reflect existing packing or “requested new fabrication” packing?

Lists and columns estimate new housing details. Any artifact currently in housing (that was noted in XG) was called out as

“Existing Crate/Box/Pallet” and did not get included in the estimated total.

SI-RFI-34 Could you provide the “packed dimensions” of existing packed works?

Refer to RoomInventories_Bookmarked.pdf (2301)

SI-RFI-45 If the vendor contracted for the base move adjusts the racking or shelving themselves, is there a risk the warranty of these units will be voided? Would the vendor need to hire the company that installed the racks to modify them?

Refer to attachment

"Pod6_StorageEquipment_Conformed_color" showing shelving elevations. If there is a need or request to adjust shelving, this work would need to be coordinated with SI.

Move contractor is welcome to adjust, reuse and relocate storage equipment that has been emptied as needed for use at AHB for this project.

SI-RFI-46 The multi-year funding document requests that FY25 items relate only to the Base

Contract scope, whereas FY26 items are for both the

Base Contract Scope and the

Option 1 Scope. As we do not currently have clarity as to when work will begin, how should we approach splitting our costs between these two fiscal years within our proposal?

SI currently intends to award the project in FY25. SI will make a decision to award or not Option 1 at the time of award. If funds are available SI intends to award up to $5M in FY25 and the balance in subsequent years.

SI-RFI-56 Are contractors fully liable for restoration or replacement costs, or is there a liability cap?

SI will purchase a policy to cover the objects during the movement. Restoration or replacement costs may be pursued in the event of gross negligence.

SI-RFI-57 If damage occurs, will the Smithsonian provide conservation support, or is the contractor responsible for arranging restoration?

SI would consult their own conservators for advice. Refer to

SI-RFI-56 response.

SI-RFI-58 Is there a specific dispute resolution process for damage claims?

SI is likely to follow the guidelines of our insurance which means if we can’t agree on a settlement – each would hire an umpire and work with a third party to settle the claim.

The Smithsonian would work with its insurer on any disputes.

If damage is caused by gross negligence and there was a dispute for the damage, we would follow the guidelines in our policy.

SI-RFI-62 • Are there specific temperature-controlled requirements for high-value or fragile artifacts?

Refer to SI-RFI-26 response.

SI-RFI-68 If possible, please describe how involved the Gov't staff will be involved in the "Pack, Move & Unpack" Process.

NMAH staff will be on hand to provide initial training, and provide oversight of data, housing, transit, unpacking, and storage. NMAH staff will be providing access to collections storage areas, and be available daily for questions.

SI-RFI-80 Weight of helicopter? Approximately 5000 lbs.

SI-RFI-9 Considering there are crates that are pre-packed but conditions are unknown, in the event that the crate needs to be retrofitted, how should we account for these additional costs or labor needed to meet deadlines?

Would there be an opportunity to review these objects prior to the NTP?

Refer to SI-RFI-16 response.

SI-RFI-98 Can we get all the crate dimensions and weights for the works not being packed by move contractor but are in the move scope?

Refer to RoomInventories_Bookmarked.pdf (2301). Weights are not currently available.

SI-RFI-99 Will the move contractor require to unpack/condition report/populate conveyances packed by others?

Refer to SI-RFI-16 response.

133330225RF0010008 Amendment 0003.docx.pdf
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
233330225RF0010008 Amendment 0003.docx.pdf
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

File details come from the government source that posted it. Updated .