28-IFB 092-25-RM-Addendum 2.docx
DOCX document 28 KB Posted
- Attached to
- Pump Station 43 Improvements
- Solicitation number
- IFB-092-25-RM
- Issued by
- Leon County, Florida
About this file
This document is Addendum No. 2 for the Pump Station 43 Improvements Invitation for Bid (IFB 092-25-RM) issued by a local government entity in Florida. The addendum modifies the original bid solicitation and announces a change in the bid opening date to Thursday, August 21, 2025, at 2:30 P.M. The addendum indicates that additional information regarding by-pass pumping will be provided in a subsequent Addendum 3, and bidders are required to acknowledge the addendum through the Bonfire platform.
The associated state and local contract opportunity involves a comprehensive infrastructure project for Pump Station 43, which includes removing an out-of-service forcemain, installing approximately 675 linear feet of 18-inch ductile iron pipe force main, installing a surge tank and kingpin manhole, implementing bypass pumping components, and relocating an existing chemical tank. The project also encompasses surface restoration, asphalt patching, milling, and resurfacing. A mandatory pre-bid meeting was held on July 23, 2025, via Microsoft Teams, and the project requires arboricultural mitigation for impacted trees and submission of temporary traffic control plans. The contractor is expected to perform all services in a timely and professional manner.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
August 12, 2025
NOTICE TO BIDDERS ADDENDUM NO. 2
PUMP STATION 43 IMPROVEMENTS
IFB 092-25-RM
Please be advised of Addendum No. 2 to the above referenced Bid Solicitation as follows:
1. This addendum forms a part of the proposal documents and modifies the original specifications and proposal documents, dated DATE as noted below.
2. Respondent must acknowledge this addendum by accepting the addendum in Bonfire.
This addendum consists of one item:
ITEM NO. 1:
Additional information will be provided on by-pass pumping in Addendum 3
BID OPENING HAS CHANGED AND IS THURSDAY, AUGUST 21, 2025, AT 2:30 P.M.
Veronica McCrackin Veronica McCrackin Purchasing Director image1.png