This is an Environmental Management Permit (LEM24-062) issued by Leon County's Department of Development Support and Environmental Management for the PS 43 Forcemain Improvements project located at 2900 Meginnis Arm Road in Tallahassee, Florida. The project involves replacing an existing sanitary sewer pump station forcemain with an 18" ductile iron pipe from the pump station building to the northern side of the I-10 crossing. The City of Tallahassee will also install a pressure surge tank at the pump station site and add a sewer manhole structure to facilitate future bypass pumping operations. The project spans three separate parcels totaling 0.83 acres, with one parcel recently acquired specifically for this implementation.
The permit was issued on 01/07/2025 and will expire on 01/07/2028, with a total permit fee of $720.00. The project requires a pre-construction conference with the County Environmental Inspector and compliance with various environmental management conditions, including erosion control measures, tree protection, and water quality monitoring during dewatering activities. The permittee must obtain all necessary property rights and easements, and submit various certifications and documentation, including a Compliance Certification by a Florida licensed Professional Engineer and a potential Tree Mitigation report prior to final inspection.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reviewer Name Reviewer Email Reviewer Phone
Deji Ajose-Adeogun ajoseadeogund@leoncountyfl.gov
Report Date: 01/07/2025 Description : The City of Tallahassee owns and operates a sanitary sewer pump station, PS 43, on Meginnis Arm Road. The existing pump station discharges through an 18” PVC forcemain located on the southern side of Meginnis Arm Road. The existing forcemain crosses the I-10 corridor, via an encased 18” ductile iron pipe, continues south along Callaway Road, and west along Pullen Road to a manhole which is the terminus of the forcemain. Due to pressure surges in the segment along Meginnis Arm Road, the City has made multiple repairs to the forcemain and desires to replace the forcemain with an 18” ductile iron pipe. The limits of the forcemain replacement are from the pump station building to the northern side of the I-10 crossing. In conjunction, the City desires to install a pressure surge tank at the pump station site to regulate pressure surges in the reconstructed forcemain. The project also includes the addition of a sewer manhole structure and onsite piping to facilitate future bypass pumping operations.
PS 43 is located on three separate parcels, Parcel #211408020000, 2114204300000, and 2114510000193, totaling 0.83 acres. Parcel 2114510000193 was recently acquired by the City for the implementation of this project.
Address : 2900 MEGINNIS ARM RD, Tallahassee, FL, 32312 Record Type : EMP Short Forms Document Filename : Permit Card.pdf
Reviewer Contact Information:
Markups for this Approved Document or Plan
Review Report - Approved
Application Number: LEM24062
General Comments
LEON COUNTY
DEPARTMENT OF DEVELOPMENT SUPPORT AND ENVIRONMENTAL MANAGEMENT
ENVIRONMENTAL MANAGEMENT PERMIT
TO SPEAK TO AN ENVIRONMENTAL INSPECTOR, CALL (850) 606-1300.
PERMIT EXPIRES THIRTY-SIX (36) MONTHS FROM ISSUANCE PER ARTICLE 5, SECTION 7-41(4)(A)(1), ENVIRONMENTAL MANAGEMENT ACT
PERMIT EXPIRES: 01/07/2028
PERMIT #:
PROJECT NAME:
LEM24062
LOCATION: 2900 MEGINNIS ARM RD
Tallahassee, FL 32312
PERMITTEE: Charles Hargraves
DATE ISSUED:
PARCEL TAX ID:
01/07/2025
2114208020000
FEE INFORMATION
Stormwater Short Form B - Low
Intensity
720.00
Stormwater Short Form B - Low
Intensity
720.00
TOTAL FEES:
TOTAL PAYMENTS
BALANCE:
720.00
720.00
0.00
Deji Ajose-Adeogun, P.E.
Director, Environmental Services Division
County Administrator's Designee
ACCEPTANCE OF THIS PERMIT ACKNOWLEDGES PERMISSIONS FOR LEON COUNTY PERSONNEL TO INSPECT AT
REASONABLE TIMES THE PROPERTY AND WORK ASCRIBED IN THIS PERMIT. FAILURE TO POST THE PERMIT PLACARD IN
A CONSPICUOUS PLACE ON-SITE OR FAILURE TO HAVE THE APPROVED PERMIT AND PLANS AVAILABLE ON-SITE MAY
RESULT IN THE IMMEDIATE ISSUANCE OF A STOP WORK ORDER.
Reviewer Name Reviewer Email Reviewer Phone
Deji Ajose-Adeogun ajoseadeogund@leoncountyfl.gov
Report Date: 01/07/2025 Description : The City of Tallahassee owns and operates a sanitary sewer pump station, PS 43, on Meginnis Arm Road. The existing pump station discharges through an 18” PVC forcemain located on the southern side of Meginnis Arm Road. The existing forcemain crosses the I-10 corridor, via an encased 18” ductile iron pipe, continues south along Callaway Road, and west along Pullen Road to a manhole which is the terminus of the forcemain. Due to pressure surges in the segment along Meginnis Arm Road, the City has made multiple repairs to the forcemain and desires to replace the forcemain with an 18” ductile iron pipe. The limits of the forcemain replacement are from the pump station building to the northern side of the I-10 crossing. In conjunction, the City desires to install a pressure surge tank at the pump station site to regulate pressure surges in the reconstructed forcemain. The project also includes the addition of a sewer manhole structure and onsite piping to facilitate future bypass pumping operations.
PS 43 is located on three separate parcels, Parcel #211408020000, 2114204300000, and 2114510000193, totaling 0.83 acres. Parcel 2114510000193 was recently acquired by the City for the implementation of this project.
Address : 2900 MEGINNIS ARM RD, Tallahassee, FL, 32312 Record Type : EMP Short Forms Document Filename : PAA.pdf
Reviewer Contact Information:
Markups for this Approved Document or Plan
Review Report - Approved
Application Number: LEM24062
General Comments
1/7/2025 LEM24-062 Page 1 of 8
(Pages are Two-Sided)
BOARD OF COUNTY COMMISSIONERS
LEON COUNTY
DEPARTMENT OF DEVELOPMENT SUPPORT AND ENVIRONMENTAL
MANAGEMENT
PS 43 FORCEMAIN IMPROVEMENTS
MEGINNIS ARM RD
ENVIRONMENTAL MANAGEMENT PERMIT
LEM24-062
A Pre-Construction Conference with the County Environmental Inspector is required.
(Contact David Graham at 850-606-1378 or 850-544-0827 to schedule a meeting)
This environmental management permit authorizes the construction (within the approved limits of construction) of infrastructure (i.e., sewer force main and pump station infrastructure, resurfacing, etc.) associated with the proposed development of parcel ID. No.: 21-14-08-021-000 0, 21-14-
20-430-000 0, & 21-14-51-000-019 3 in Leon County, consistent with the attachments and exhibits identified below.
Attachment A: Permit Conditions
Exhibit A: Approved Plans (Permit Plan Set)
Exhibit B: Erosion Certification
Exhibit C: RoW Placement Permit
The permittee should be familiar with the permit conditions and all other attachments and exhibits included in this permit prior to the commencement of development activity. Failure to conform to this permit may cause appropriate enforcement action to be taken that could include a "Stop Work
Order" or a "Notice of Violation".
Approved By:
Ayodeji Ajose-Adeogun, P.E., Director Date
County Administrator Designee
Environmental Services
MAH
1/7/2025 LEM24-062 ATTACHMENT A Page 2 of 8
ATTACHMENT "A"
PERMIT CONDITIONS:
PS 43 FORCEMAIN IMPROVEMENTS
MEGINNIS ARM RD
GENERAL CONDITIONS:
1. The permittee shall conduct all development activity consistent with the "Environmental Management
Act," Article IV, Chapter 10 of the Leon County Land Development Code. Reference Section 10-
4.105.
2. Posting of placards. A placard indicating issuance of a valid permit shall be posted in a conspicuous place on site at all times during the development activity. Reference Section 10-4.203(c)(1).
3. Permit and plans on-site. A copy of the approved permit and plans (Exhibit "A" and subsequent approved contractor "Shop Drawings") shall be available on site at all times when any development activity is occurring on the site. Reference Section 10-4.203(c)(2).
4. Notice of intent to proceed. A notice of intent to proceed shall be filed with the County Administrator or designee at least three working days prior to initiation of any physical development activity on any site, except for development activity limited to that which has been permitted in relation to construction of a detached single-family residence, which shall require filing of a notice of intent to proceed within 24 hours prior to initiation of development activity. The notice shall specify the site location and the permit number applicable to the activity and shall specify the date and approximate time at which such physical development activity is to commence. Reference Section 10-4.203(c)(3).
5. Environmental Management Officer. The permittee shall designate, as part of the environmental management permit application, an individual to act as the environmental management officer for the project. Such individual shall be in responsible charge of all on-going work on the site and shall have sufficient familiarity with the project to ensure that all work is proceeding according to the approved plans and permit. The designated environmental management officer is not required to remain on the site at all times during all operations but must ensure that during such time as the officer is not personally present on the site a designated alternate person remains in responsible charge of the project. Reference Section 10-4.203(c)(6).
6. Permit Expiration. Environmental management permits shall expire 36 months after issuance unless otherwise specified by the County Administrator or designee for master planned subdivisions or phased development projects. Reference Section 10-4.214(a)(1).
7. Extensions. Permits may be extended, by request of the applicant and approval of the County
Administrator or designee, for successive periods of time not to exceed 36 months each, provided the request for extension is made prior to the expiration of the prior approval and provided continuous good faith efforts have been made to complete the development. Reference Section 10-4.214(a)(2).
8. Early expiration for cause. If no substantial and readily observable site development activity has taken place within 24 months of the issuance of the permit or, once development is started, if no such development activity occurs for any 24 consecutive months, the County Administrator or designee may, after notifying the permittee and providing an opportunity for hearing, determine the permit to
1/7/2025 LEM24-062 ATTACHMENT A Page 3 of 8 be expired and shall so notify the permittee. Such a permit may not thereafter be extended. Reference
Section 10-4.214(a)(3).
9. Effect of permit expiration. Once a permit has expired, no further development activity may proceed on the permitted development site unless and until a new permit application has been submitted and approved for the particular development site and activity. Reference Section 10-4.214(d).
10. Continued responsibility under expired permit. Permit expiration shall not, however, terminate the obligations of the permittee or property owner to ensure continued compliance with this code, or to complete and maintain the landscaping, trees, or stormwater management systems and facilities which were required for undertaking the development activities on the site. Where a permitted development activity has been commenced under a permit prior to the date of the permit's expiration, but has not received final inspection approval prior to such expiration, the developer, owner, or permittee of the development site may be cited for any violation of this code or of the permit and plans which had been approved for the development activity or site, and may be required to submit, and obtain the County
Administrator or designee's approval of, a new environmental management permit application or an application for amendment of the expired permit, or to complete and maintain the landscaping, trees, or stormwater management systems and facilities which were required by the expired permits, as necessary to prevent significant adverse environmental impacts as a result of the development activity which has occurred on the site. Reference Section 10-4.214(d).
11. Notice of transfer of permit. No later than ten days after the sale or legal transfer of property upon which a stormwater management facility has been, or is approved to be, constructed pursuant to a permit issued by the county, a notice of transfer of permit shall be submitted to the County
Administrator or designee. Reference Section 10-4.214(f)(1).
12. Transfer liability. Until a proper notice of permit transfer is provided to the County Administrator or designee, the permittee and any other person constructing, operating, or maintaining the permitted facility shall be liable for compliance with the terms of the permit. The permittee transferring the permit shall remain liable for corrective actions required as a result of any violations occurring prior to sale unless the new permittee obtains approval of the County Administrator or designee to specifically assume such obligations and provides to the County Administrator or designee written evidence in legal form of such assumption of obligations. For facilities that have received final inspection approval prior to the time of sale or legal transfer, the original permittee shall remain liable for performance of warranty obligations as set forth in section 10-4.209(d), absent an express assumption of liability as to such warranty obligations by the subsequent holder of the property.
Reference Section 10-4.214(f)(2).
13. Amendments. Any minor change or deviation from the approved plans shall require an amendment to this permit. Substantial changes, including significant increases in impervious area, changes in intended land use, modification of stormwater management system, new phases of development, or other additions, shall not be treated as amendments, but shall require a new permit application.
Reference Section 10-4.215.
14. During development. All environmental management controls and facilities shall be maintained in a manner which will ensure proper functioning and protection from unnecessary environmental degradation, throughout the development process. Reference Section 10-4.210(a).
15. Post-development. Upon completion of development activities and construction, the permittee shall ensure that each site is properly stabilized, and that swales and other stormwater management features
1/7/2025 LEM24-062 ATTACHMENT A Page 4 of 8 shown in the permit are in place in a manner consistent with the permit, approved plans and specifications. Reference Section 10-4.210(b).
16. Post-construction inspection. Prior to requesting a final inspection by the director pursuant to section
10-4.212(b)(3), the permittee shall cause a qualified professional personally to inspect the site and facilities and certify as provided for in Section 10-4.208(b). Reference Section 10-4.208(a).
SPECIFIC CONDITIONS:
1. Permit Scope. As shown in Exhibit “A” (the permit plan set), this permit authorizes the construction
(within the approved limits of cleaning)of infrastructure (i.e., sewer force main and pump station infrastructure, resurfacing, etc.) associated with the proposed development of parcel ID. No.: 21-14-
08-021-000 0, 21-14-20-430-000 0, & 21-14-51-000-019 3 in Leon County consistent with the attachments and exhibits accompanying this permit.
2. Licensed contractors. All excavation, grading work, and other site work to be performed under any permit shall be supervised by a state-licensed general contractor, building contractor, residential contractor, commercial or residential pool/spa contractor, underground utility contractor, or any state-certified specialty contractor with 40 competencies (or expertise) to complete the specified development activities. Reference Section 10-4.203(c)(5).
3. Notification of Easements. A copy of any and all required easements, with proof of executed recording, shall be provided to the county administrator or designee prior to final inspection. Where transfer of title for any affected parcel is proposed, the owner shall provide clear information to each prospective buyer prior to execution of any contracts, about the existence, impacts, and responsibilities associated with any easements on the property. A copy of the applicable easements shall be provided by the owner to each prospective purchaser prior to closing, and the copy shall be initialed by the parties and attached to such closing documents upon execution. Reference Section 10-4.203(c)(8).
4. Stormwater management facility operating permit. No stormwater management facility shall be utilized until a stormwater management operating permit is obtained. An operating permit is not required for facilities which have as their primary function the conveyance of stormwater, facilities under construction as part of an approved development plan, and temporary facilities which are part of an erosion and sediment control plan. Reference Section 10-4.209(a).
5. Required disclaimers. Any contract for the conveyance of title to land for which stormwater management is provided by a system or facility not maintained by the County or the City of
Tallahassee shall contain the following statement: "Neither Leon County nor the City of Tallahassee is responsible for the maintenance, upkeep or improvement of any stormwater management facility utilized by the land described herein. Title to this property carries with it the requirement that the current and all subsequent owners or their authorized agent obtain a stormwater management facility operating permit from the County. The owner of this property shall be legally responsible, jointly with other owners using the facility and based on pro rata share, for compliance with all stormwater management facility operating permit maintenance and operation requirements, as well as all other permit conditions, unless such maintenance and operation obligations have been specifically assumed by some other entity pursuant to Director approval and appropriate documentation recorded in the public records of Leon County." Reference Section 10-4.210(d).
6. Landscape and tree maintenance, if applicable. All landscaping, landscaped areas, landscape development, buffer areas, trees, and conservation areas required as part of this permit shall be
1/7/2025 LEM24-062 ATTACHMENT A Page 5 of 8 maintained and used pursuant to Sections 10-4.348(b), 10-4.355, 10-4.209(f)(1)(h), 10-4.209(g)(7) and 10-4.211 of the Land Development Code and shall be checked for compliance during the operating permit renewal process. An Operating Permit covering the landscape and tree maintenance shall be submitted (Section 10-4.351(e)(2)i.). For projects with no Stormwater Management Facility(ies), a
Stand-Alone Operating Permit to ensure the perpetual maintenance, shall be submitted. This will ensure compliance with the requirements, purpose, intent, and objectives of the permit (Section. 10-
4.203(c)(9)).
7. Intergovernmental Transfer. If at any time, the City of Tallahassee (the "City") annexes the permitted development into its corporate boundary, then this permit shall be transferred to the City with all provisions fully enforceable by the City. The City shall assume the role of the County in each provision of this permit.
8. System Evaluation & Redesign. At any time, should the County determine that the stormwater management system, stormwater pollution prevention plan, landscape plan, or any maintenance program is not functioning as designed, the County may request a system evaluation to determine compliance. The Permittee shall have thirty (30) days to evaluate the discrepancy and respond. Should the Permittee verify that a discrepancy exists, then the Permittee shall have sixty (60) days to redesign and implement the appropriate redesign necessary to correct the discrepancy. This process does not apply to any event of noncompliance with the permit and approved plans, in which case the enforcement provisions of the Environmental Management Act shall apply.
9. Other Permits. This permit is issued with the condition that the applicant procure and comply with all other necessary federal, state, and local agency permits, including but not limited to the City of
Tallahassee (COT) Utilities or Infrastructure, Florida Department of Environmental Protection
(FDEP) permits, FDEP 10-2 permit, Northwest Florida Water Management District (NWFWMD) permits, Florida Department of Transportation (FDOT) drainage and/or access connection permits, NPDES permit and Leon County driveway connection permit. These permits must be provided to the environmental inspector prior to the pre-construction. Reference Section 10-4.201(f).
10. Construction or repair of buildings, excavation of streets and highways: The construction, demolition, alteration or repair of any building or the excavation of streets and highways other than between the hours of 7:00 a.m. and 8:00 p.m. on weekdays and Saturdays and between 9:00 a.m. and 5:00 p.m. on
Sundays. This prohibition does not apply to the delivery and installation of concrete and other materials associated with residential slab installation. In cases of emergency, construction or repair noises are exempt from this provision. Reference Section 12-56(10).
11. If prehistoric or historic artifacts, such as pottery or ceramics, projectile points, dugout canoes, metal implements, historic building materials, or any other physical remains that could be associated with
Native American, early European, or American settlement are encountered at any time with the project site area, the permitted project shall cease all activities involving subsurface disturbance in the vicinity of the discovery. The applicant shall contact the Florida Department of State, Division of Historical
Resources, Compliance Review Section at (850) 245-6333. Project activities shall not resume without verbal and/or written authorization. In the event that unmarked human remains are encountered during permitted activities, all work shall stop immediately, and the proper authorities notified in accordance with Section 872.05, Florida Statutes.
12. Engineering Review Limitations: The review of this permit was limited to verifying compliance with the minimum standards of the Environmental Management Act (EMA) and other general civil site design standards. Any plans/specifications relating to the structural, water, or sewer component, or the like, were not reviewed in depth for constructability or compliance with other regulatory agencies.
1/7/2025 LEM24-062 ATTACHMENT A Page 6 of 8
13. SPECIAL CONDITIONS:
As shown in Exhibit “A” (the permit plan set), this permit authorizes the construction (within the approved limits of cleaning)of infrastructure (i.e., sewer force main and pump station infrastructure, resurfacing, etc.)
associated with the proposed development of parcel ID. No.: 21-14-08-021-000 0, 21-14-20-430-000 0, &
21-14-51-000-019 3 in Leon County consistent with the attachments and exhibits accompanying this document.
1. As used herein, the term “permittee” shall refer to the current owner(s) of the parcel. This permit may be transferred to another party in accordance with the General Conditions. Upon the Director’s approval of a Notice of Transfer of Permit, the term “permittee” shall refer to the new property owner(s) identified in this approved notice. The permittee shall ensure that all contractors and other agents authorized by the permittee to conduct the permitted development activities abide by the terms and conditions of this permit.
2. The permittee or permittee’s authorized agent shall arrange a pre-construction conference prior to the commencement of any construction/development activities. The Leon County inspector for this project is Mr. David Graham who may be contacted at 850-606-1378 or 850-544-0827.
3. Prior to the pre-construction conference being scheduled, submittal of the Qualified Stormwater
Management Inspector Certification along with any additional permit requirements (i.e., NDPES, FDOT, etc.) or a letter of exemption must be submitted to the Environmental Inspector as part of the request to schedule the pre-construction conference referenced in Special Condition #2 above.
4. Engineer of Record or designated delegate shall complete the Design Professional Certification Form for sedimentation & erosion control measures on-site within 7 days of installation. [See Exhibit B].
5. Project staging activity in areas outside of the areas shown in Exhibit “A” will require a separate
Environmental Management Permit and site plan from Leon County Development Support and
Environmental Management (LCDSEM) in association with the unincorporated area . LCDSEM should be contacted regarding any proposed staging activity outside of the project area prior to construction commencement.
6. A Right of Way (RoW) Placement Permit from Leon County Public Works (LCPW) is required for any proposed utility work in the County RoW. The RoW Placement Permit has been received and is
Exhibit C. Any road closure requests must contain a traffic management plan and be submitted to the
Public Works Department in advance consistent with Leon County Policy 17-1.
7. Limits of clearing to be marked and/or staked as the project area necessitates prior to pre-construction meeting with the Leon County Environmental Inspector. The requirements pertaining to the City’s environmental inspectors concerning erosion control, etc. duly applies to DSEM personnel.
8. The permittee shall acquire all necessary property rights, right-of-way, and easement acquisitions prior to construction commencement. The permittee shall supply copies of legal documents to LCDSEM prior to the pre-construction conference demonstrating that sufficient property rights, right-of-way, and easement acquisition have been obtained to conduct the permitted work.
9. Prior to beginning installation of underground infrastructure, approval documentation from City of
Tallahassee Utilities of final construction plans to be submitted to inspector (both Public Works and
DSEM as applicable).
lane Highlight
1/7/2025 LEM24-062 ATTACHMENT A Page 7 of 8
10. Erosion and sedimentation control measures shall be in accordance with the Florida Sediment and
Erosion Manual, reference Sheet 2. Items such as temporary sediment traps, diversion berms, swales, and stabilization methods such as, pinned sod, erosion control matting/blankets, mulching, temporary and permanent seeding shall be utilized to control erosion and retain sediment onsite.
a. Sediment Control measures shall be sufficient to prevent the tracking or direct flow of mud and sediments onto public or private streets or drainage ditches. Any sediments or mud spilled, dropped, washed, or tracked from any vehicles onto the public or private streets or into the public drainage system shall be recovered and cleaned up immediately. Wash water shall be carried away from the entrance to a settling area for sediment removal. A dedicated wash area and wash racks will be required if excessive tracking is observed by the inspector. Permittee may be asked to provide additional measures, note paragraph 7
&11 of Sheet 2 Erosion Controls.
b. Sediment controls which are breached due to development activity, rain, or other factors shall be repaired within 24 hours of the breach.
c. Additional silt fences or other sediment/erosion control devices and measures may be required, as specified by the inspector. Proposed staging areas shall be discussed with the inspector and explicitly demarcated within the site.
d. During the discharge of water to offsite areas, water quality must be monitored during dewatering activities to ensure that the discharge does not create adverse impacts. The daily water quality samples shall be analyzed for turbidity using a calibrated field turbidity meter. Turbidity shall not exceed 29 Nephelometric Turbidity Units (NTUs) above background in Class III receiving waters. pH must be within the range of 6.5 to 8.5 SU and must not cause a change in the pH of the receiving water body more than 0.2 SU.
11. All soil excavated as part of this project shall be used on-site or properly disposed of at an approved location. This permit does not include storage of excavated materials on-site.
12. No protected trees shall be impacted.
a. Work within the critical root protection zone (CRPZ) of protected trees shall be minimized to the extent practicable. Any work (including materials or equipment storage) to be performed within the CRPZ of protected trees shall be discussed with and approved by the
County Environmental Inspector prior to beginning the work.
13. Contractor shall adhere to the conditions of Tree Protection Notes, Sheet 3, addressing impacted protected trees, as well as the Arborist Report TR1-TR2, Exhibit A. All mitigation techniques and methods discussed in the arborist report or notes, shall be overseen by a Certified Arborist and followed through the life of the project.
14. Notwithstanding the general and specific conditions contained in this permit, this project will require submittal of the following items to the Director at least 20 days prior to the permittee/applicant’s request for final inspection and ensuing request for final certificate of occupation:
a. Compliance Certification signed/sealed by a Florida licensed Professional Engineer
i. As part of the Compliance Certification, the Engineer of Record shall verify and certify that all items under their supervision including drainage, grades, etc. have been met.
ii. All deviations shall be listed on the certification including changes based on Public
Works requirements.
b. Tree Mitigation report
i. If tree mitigation is required; documentation detailing the mitigation efforts shall be included in the compliance report by the permittee’s registered arborist or landscape architect.
lane Highlight lane Highlight
1/7/2025 LEM24-062 ATTACHMENT A Page 8 of 8
In the event that any condition of this permit is subject to multiple interpretations and becomes the source of conflict that cannot be resolved onsite by the contractor and the environmental inspector, the matter shall be forwarded to the Environmental Services Director for clarification/interpretation.
| PS 43 LC EMP Permit Card LEM24062.pdf |
| 1 |
| PS 43 LC EMP Permit LEM24062.pdf |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
File details come from the government source that posted it. Updated .