11-11-4. IFB 092-25-RM SPECIAL PROVISIONS.docx
DOCX document 16 KB Posted
- Attached to
- Pump Station 43 Improvements
- Solicitation number
- IFB-092-25-RM
- Issued by
- Leon County, Florida
About this file
This document is a Special Provisions file for an infrastructure project involving the City of Tallahassee and Leon County, Florida, specifically detailing permit requirements for a pump station improvement project. The project involves securing multiple permits, including an NPDES Permit, City of Tallahassee Underground Utilities General Utility Permit, Leon County Environmental Management Permit, and Leon County Right of Way Placement Permit. Contractors are required to examine, review, and comply with all permit conditions, anticipating associated costs without consideration for potential project delays.
The document emphasizes contractor responsibilities, including pre-approval of offsite staging areas through the City's Growth Management Department, documentation of pre-existing site conditions through photographs, and potential restoration work at no additional cost to the City. Contractors must secure road closure permits, provide arboricultural mitigation for impacted trees, and maintain traffic control. A mandatory pre-bid meeting is scheduled for July 23, 2025, at 2:00 PM EST via Microsoft Teams, with specific connection details provided for virtual attendance. The project involves infrastructure replacement, including forcemain removal and installation, surge tank installation, bypass pumping components, and surface restoration.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
I. PERMITS
The following permit(s) have been secured by the City (unless otherwise noted) and apply to this Contract.
1. NPDES Permit will be required, and coverage must be obtained by the Contractor.
2. City of Tallahassee Underground Utilities - General Utility Permit, (Appendix A, TEM 220057)
3. Leon County, Environmental Management Permit, (Appendix B, LEM24-062)
4. Leon County, Right of Way Placement Permit, (Appendix C, LRW24088)
Bidders shall examine the permits, review, and understand all permit conditions, and abide by same during execution of the work, and anticipate all costs associated with doing so. No claims for project delays or unanticipated work associated with those tasks will be considered.
In addition to the permit conditions, bidders are advised that the Contractor will be solely responsible for determining what, if any, offsite staging areas will be used, and shall be responsible to the owner of such areas regarding leasing, restoration, traffic control, etc. All staging areas to be used must be pre-approved by the City’s Growth Management Department prior to their use.
The Contractor shall abide by these requirements before final payment will be released. Photographs of deficient areas existing prior to construction shall be produced by the Contractor to document such deficiencies. Otherwise, the Contractor may be required to correct such deficiencies as part of the restoration work at no extra cost to the City.
Appendices A-C on Bonfire