This document is a FEMA First Article Inspection checklist for Manufactured Housing Units (MHUs), designed to comprehensively evaluate the quality and condition of mobile housing units during initial production inspection. The checklist covers extensive exterior and interior inspection criteria across multiple domains, including:

Exterior inspection items include assessment of tires, rims, axles, frame components, hitch and coupler integrity, brake wiring, bottom board condition, wind diverters, vinyl siding, windows, doors, and shingles. Interior inspection criteria encompass vinyl flooring, wall finishes, trim, windows, doors, ceiling finish, plumbing, appliances, furniture inventory, key sets, NOAA radios, window screens, bath exhaust fans, lever handles, and electrical/water line tests. The form allows inspectors to systematically mark each line item as "Pass" or "Fail" and provides space to document specific failure descriptions, with detailed layout diagrams to help pinpoint and record the location of any deficiencies discovered during the first article inspection process.

View the file

Other files

File Type Posted
2.1.1 Attachment 1 NextGen MHU Pricing Structure (for Offerors) 02.26.25.xlsx Rev. 2_August 3, 2025.xlsx XLSX spreadsheet
2.1.1 Attachment 1 NextGen MHU Pricing Structure (for Offerors) 02.26.25.xlsx_Rev. 2_August 3, 2025.xlsx XLSX spreadsheet
Sol_70FB8025R00000018_Amd_0005.pdf PDF
Sol_70FB8025R00000018_Amd_0004.pdf PDF
2.1.1 Attachment 1 NextGen MHU Pricing Structure (for Offerors) 02.26.25.xlsx_Rev. 1_August 1, 2025.xlsx XLSX spreadsheet
2.1.1+Attachment+12+MHU+Solicitation+and+Comment+Matrix+02.20.25_August 1, 2025.xlsx XLSX spreadsheet
Sol_70FB8025R00000018_Amd_0003.pdf PDF
Amendment 2_ 2.1.1 Attachment 12 MHU Solicitation and Comment Matrix 02.20.25_Responses July 8 2025_AC.xlsx XLSX spreadsheet
Sol_70FB8025R00000018_Amd_0002.pdf PDF
Sol_70FB8025R00000018_Amd_0001.pdf PDF
2.1.1 70FB8025R00000018_MHU Soliciation 2025_Final_Rev2_June 27, 2025.pdf PDF
2.1.1 70FB8025R00000018_MHU Soliciation 2025_Final_Rev1.pdf PDF
2.1.1 Attachment 3 - 1BR NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - Express Cal Wildfire NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 9 Acronyms NextGen Rev 2.20.25.pdf PDF
2 - Appendix C - FEB-03-2025.pdf PDF
2.1.1 Attachment 12 MHU Solicitation and Comment Matrix 02.20.25.xlsx XLSX spreadsheet
2.1.1 Attachment 6 MHU Delivery Schedule and Daily Production Report Template 02.20.25.xlsx XLSX spreadsheet
2 - Appendix B Revision Log - FEB-03-2025.pdf PDF
2.1.1 Attachment 14 NextGen Warranty Repairs In The Field List 02.26.25.pdf PDF
2 - Appendix A Revision Log - FEB-03-2025.pdf PDF
2.1.1 Attachment 3 - 2 BR NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 3BR NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 2BR NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 3 BR NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2 - Appendix A Typical NextGen MHU Details - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 13 DAPIA Concurrence Letters Rev 02.20.25.pdf PDF
2.1.1 Attachment 11 MHU_Past Performance Questionnaire 02.20.25.docx DOCX document
2 - Appendix C Revision Log - FEB-03-2025.pdf PDF
2.1.1 Attachment 3 - 1BR Cal Wildfire NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 70FB8025R00000018_MHU Soliciation 2025_Final.pdf PDF
2.1.1 Attachment 15 Misc Parts and Materials 02.26.25.pdf PDF
2 - Appendix B Typical NextGen Cut Sheets - FEB-03-2025.pdf PDF
2.1.1 Attachment 3 - 3BR Cal Wildfire NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 2BR Cal Wildfire NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - Express Cal Wildfire HVAC Wall Mounted Revision Log - FEB-03-2025.pdf PDF
2.1.1 Attachment 3 - Express NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 2BR Cal Wildfire NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 5 NextGen MFG_shipment_Notification 02.20.25.xlsx XLSX spreadsheet
2.1.1 Attachment 7 Invoice-Sample_Blank 02.20.25.xlsx XLSX spreadsheet
2.1.1 Attachment 3 - 1BR Cal Wildfire NextGen CAD Drawings HVAC Wall Mounted - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 1 NextGen MHU Pricing Structure (for Offerors) 02.26.25.xlsx XLSX spreadsheet
2 - FEMA NextGen MHU Additional Requirements - Version 1 - FEB-03-2025.pdf PDF
2.1.1 Attachment 10 MHU_Quality_Assurance_Plan 28July2020 Rev.1 02.20.25.pdf PDF
1.1.3 Attachment 2 NextGen Statement of Work - Final.pdf PDF
2 - FEMA NextGen MHU Additional Requirements - Version 1 Revision Log - FEB-03-2025.pdf PDF
2.1.1 Attachment 3 - 1BR NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - Express NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 3 - 3BR Cal Wildfire NextGen CAD Drawings Furnace-AC System - FEB-03-2025 PE Sealed.pdf PDF
2.1.1 Attachment 4 MHU Intake-Transfer Inspection Checklist (08.04.22) Rev 02.20.25.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEMA First Article Inspection

9. MHU Manufacturer Info 10. Appliances Manufacturer: Model: Type Manufacturer Model Serial Number

Vendor: Year: Furnace

11. Printed Name of Exterior Inspector 12. Signature of Exterior Inspector 13. Date (MM/DD/YY)Air Conditioner

TPS

14. Printed Name of Interior Inspector 15. Signatue of Interior Inspector 16. Date (MM/DD/YY)Refrigerator

Range

17. Type of Inspection: First Article Storage Shipment Water Heater

18. Final Acceptance Printed Name 19. Final Acceptance Signature Name 20. Recommendation:

Accept MHU Reject MHU

Line Item Pass Fail Line Item

Bottom board tire blowout protection - Free from damage.

HUD Label - Present on road side of MHU.

Vendor serial number - Legible on front header and stenciled on hitch.

5. Date of Inspection (MM/DD/YY)

6. Manufacturer Location 7. Temperature and Climate Conditions (Circle one of the icons)

1. FEMA MHU Identification Number 2. Serial Number 3. Bar Code 4. HUD Number

Rims - Same color, do not have any gouges or cracks. Axle drums do not have any missing threaded studs or nuts.

Axles, Springs, Spring Hangers - Free from damage.

Main I-Beams - Not buckled, bent or twisted.

Cross Members and Outriggers - Not buckled, bent or twisted.

Exterior Inspection Item Description

Tires - Free from cracks, cuts, gouges, bumps or any tread separtation.

No tire belts or plys exposed.

Description of Failure Enter Line item number and a brief description of failure. Circle location of failure on corresponding diagram on page 3 of 3.

8. Unit Type (Circle one) F - Furnace B - Package System

8F 8P

8 Wide Express - Battery Box mounted to hitch assembly with battery.

Battery shows no signs of leakage.

Hitch, Coupler and Jack - Free from damage.

Frame - All exposed surfaces are painted and no rust.

Drawbar - Painted Green.

Brake axle wiring harness - No exposed wires and can be reconnected to another towing vehicle.

Bottom board - Free from tears and/or rips. Patches are secure. No exposed insulation.

Wind diverters and plastic wrap - Present & free from damage

Furnace only - A/C condensor Hold down clips, vibration damping pad & protective cover with no visable wear or rubbing.

Vinyl siding and trim - Buckled, cracked, bowed or missing.

Windows and Doors - Damaged, cracked glass, bowed or missing parts or trim.

Vinyl siding wind protection strips - Present & free from damage.

Furnace only - Protective pipe friction fitted into header. A/C lines & electrical conduit for exterior A/C show no wear or rubbing.

Shingles - Missing, cracked or exposed fasteners.

14F - 1BR

14F - 2BR

14F - 3BR

14B - 1BR

14B - 2BR

14B - 3BR

SOLICITATION

ATTACHMENT 8

Line Item Bath #1 Bath #2 Hallway

45 Vinyl Flooring - Free from gouges, cuts, bumps or repair patches. P F P F P F P F P F P F P F P F 46 P F P F P F P F P F P F P F P F

47 P F P F P F P F P F P F P F P F

48 P F P F P F P F P F P F P F P F

49 P F P F P F P F P F P F P F P F

50 P F P F P F P F P F P F P F P F

51 P F P F P F

52 P F 53 P F P F P F P F P F P F P F P F 54 P F P F P F P F P F P F P F P F 55 P F P F P F P F P F P F P F P F

Line Item Pass Fail Line Item

59 Furniture - Account for all furniture as shown on Ship Loose drawing

BR #3BR #2BR #1Living Room

Plumbing - Fixtures, visable piping, fixtings, connections and supports are free from damage.

Appliances - Free from scratches, dents and visable damage.

Window screens - 1 per each operable window (Stored under BR #1 bed).

Bath Exhaust Fan Timer - One each bathroom.

Lever Handles - All interior doors have lever handles.

NOAA Radio's - 1 radio per bedroom.

Shower rod and curtain - One each bathroom.

Sprinkle system tools and red storage box Red sprinkler document storage box.

Electrical test - Operational and polarity Water line air test - Water heater bypass valve in "off" position

Microwave - Microwave in MHU Bedeoom 1 closet.

Mini-blinds - Full length mini-blinds at each window.

Inspection Item Description MHU entry keys - 3 sets of keys (Total of 6 keys) in kitchen drawer with ID tags (MHU Bar code on one side / MHU Serial number on other side.

Drain line test - Winterize after passing test.

Doors - Operate freely and UFAS threshold not damaged or bowed up.

Ceiling Finish - Free from damage, not buckled, cracked, bowed, sagging, no separations, loose or poped panels.

Kitchen

Wall Finish - Free from popped panels, gouges, cuts or visable damage.

Trim - All wall, window and door trim is caulked and free from damage.

Interior Inspection Item Description

Windows - Operate freely without binding and free from damage.

P = Pass F = Fail

Enter Line item number and a brief description of failure. Circle location of failure on corresponding diagram on page 3 of 3.

Description of Failure

Frame 1. Circle general area where failure occurred that is documented on page 1. |

2. Add corresponding line item number next to circle

1. Circle general area where failure occurred that is documented on page 2.

2. Add corresponding line item number next to circle

Left Side (Curb Side)

Right Side (Street Side)

1. Circle general area where failure occurred that is documented on page 2.

2. Add corresponding line item number next to circle

Front Elevation Rear Elevation

Roof

1 Bedroom MHU Layout

3 Bedroom MHU Layout

2 Bedroom MHU Layout

Interior Layouts

8' Wide Express MHU

14' Wide MHU

Exterior Layouts and Elevations

File details come from the government source that posted it. Updated .