This document outlines a federal contract opportunity to construct a chiller plant for the Columbus VA Medical Center in Ohio. The solicitation number is 36C25023B0049 and was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10. It is a SDVOSB set-aside seeking construction services to build a new chiller plant at the Columbus VAACC campus. The final bid/proposal submission date is not specified in this file but other key details include the opportunity type of solicitation and that it is for a construction project to develop a new chiller plant facility.

View the file

Other files

File Type Posted
36C25024C0013 SAM Award Notice 1.0.pdf PDF
36C25023B0049 - Amendment 3.docx DOCX document
36C25023B0049 - Amendment 2.pdf PDF
36C25023B0049 - Amendment 1.docx DOCX document
Single Source Justification MPT to SAT - Wattstopper - Pricing Removed - Signed.pdf PDF
VHA Directive 1192.01, Seasonal Influenza Prevention Program for VHA Health Care Personnel.pdf PDF
18912 Columbus VAMC Chiller BC Sole Source Redacted.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-8.pdf PDF
VAAR 852.219-75 - To Be Submitted With Bid.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-5.pdf PDF
VAACC Health Requirements - Bid Ready 2023.pdf PDF
36C25023B0049 - Ready.docx DOCX document
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-4.pdf PDF
Single Source Justification MPT to SAT - Simplex - 2.0 Price Removed - Signed.pdf PDF
18912 Columbus VA Chiller Plant Revision Final B_C Re-Revised - PM Vol 1 of 2.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-2.pdf PDF
Franklin DB - Current as of 07.13.2023.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-9.pdf PDF
Single Source Justification MPT to SAT - Software House - Pricing Removed - Signed.pdf PDF
Single Source Justification MPT to SAT - Russ Electric Price Removed - Signed.pdf PDF
18912 Columbus DVAMC Chiller FB_C PM Volume 2 of 2.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-6.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-7.pdf PDF
Hca Signed NCO 10 Caterpillar - Sole Source - Pricing Removed.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-10.pdf PDF
18912 Columbus VA Chiller Plant Revision Final BC Revised - Drawings - Part-3.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHAPTER 3 - USE GROUP:

USE GROUP

CHAPTER 4 - SPECIAL DETAILED REQUIREMENTS:

DETAILED REQUIREMENTS IF NEEDED

ALLOWABLE HEIGHT AND BUILDING AREA - TABLE 503:

EXISTING CONSTRUCTION TYPE: IIB

NEW CONSTRUCTION TYPE: IIB

BUILDING HEIGHT ALLOWABLE: 75'

BUILDING HEIGHT ACTUAL: 34' - EXISTING BUILDING

23' - NEW ADDITION

BUILDING AREA ALLOWABLE:

FIRST FLOOR: 46,500 SF

SECOND FLOOR: 46,500 SF

BUILDING AREA ACTUAL - EXISTING:

FIRST FLOOR: 10,482 SF

SECOND FLOOR: 3,067 SF

SEPARATION OF OCCUPANCIES - TABLE 508.3.3:

SEPARATION IF NEEDED OR NON-SEPARATED MIXED USE

FIRE-RESISTANCE RATINGS REQUIREMENTS - TABLE 601:

CONSTRUCTION TYPE: IIB

STRUCTURAL FRAME: 0 HRS

BEARING WALLS:

EXTERIOR: 0 HRS

INTERIOR: 0 HRS

NON BEARING WALLS & PARTITIONS:

EXTERIOR: 0 HRS

INTERIOR: 0 HRS

FLOOR CONSTRUCTION: 0 HRS

ROOF CONSTRUCTION: 0 HRS

CHAPTER 7 - FIRE-RESISTANCE-RATED CONSTRUCTION:

SHAFT ENCLOSURES: 1 HRS

EXIT ENCLOSURES: 1 HRS

EXIT PASSAGEWAYS: 1 HRS

CHAPTER 8 - INTERIOR FINISHES:

EXIT ENCLOSURES & PASSAGEWAYS: CLASS C

CORRIDORS: CLASS C

ROOMS & ENCLOSED SPACES: CLASS C

INTERIOR FLOOR FINISH: MINIMUM CLASS 2

CHAPTER 9 - FIRE PROTECTION SYSTEMS:

SPRINKLER SYSTEM: NFPA 13

FIRE ALARM SYSTEM: NFPA 72

FIRE EXTINGUISHERS:

TYPE: 10-B

MAXIMUM TRAVEL DISTANCE: 30'-0"

CHAPTER 10 - MEANS OF EGRESS:

DOOR WIDTH: 32" MINIMUM CLEAR WIDTH

CORRIDOR WIDTH: .2" PER OCCUPANT, BUT NOT LESS THAN 44"

LENGTH OF EXIT TRAVEL: 200'

DESIGN OCCUPANT LOAD:

EXISTING FIRST FLOOR OCCUPANT LOAD: 93 PERSONS

EXISTING SECOND FLOOR OCCUPANT LOAD: 28 PERSONS

F-1 (FACTORY INDUSTRIAL)

BUILDING AREA ACTUAL - PROJECT:

FIRST FLOOR: 5,180 SF

NEW FIRST FLOOR OCCUPANT LOAD: 52 PERSONS

TOTAL FIRST FLOOR OCCUPANT LOAD: 144 PERSONS

TOTAL SECOND FLOOR OCCUPANT LOAD: 28 PERSONS

NFPA 10

PROJECT AREA

OCCUPANCY

INDUSTRIAL

FIRE SUPPRESSION: FULLY SPRINKLERED

(6.1.12.1)

FIRST FLOOR: 5,180 S.F.

PORTABLE FIRE EXTINGUISHERS (NFPA 10, TABLE 6.2.1.1)

ORDINARY HAZARD OCCUPANCY:

MAX. TRAVEL DISTANCE

TO EXTINGUISHER: 30 FT.

OCCUPANT LOAD FACTORS (SF PER PERSON-TABLE 7.3.1.2)

GENERAL & HIGH HAZARD INDUSTRIAL:

EGRESS CAPACITY (WIDTH/PERSON) (7.3.3.1)

STAIRWAYS:

LEVEL COMPONENTS AND RAMPS:

10-B EXTINGUISHER

COMMON PATH LIMIT:

DEAD-END LIMIT:

TRAVEL DISTANCE LIMIT:

NOT TO EXCEED 100'-0"

NOT TO EXCEED 50'-0"

NOT TO EXCEED 250'-0"

MEANS OF EGRESS REQUIREMENTS (TABLE 7.6)

100 FT2 / PERSON

5180 SF/100 = 52 OCCUPANTS

0.3" 0.2"

CONSTRUCTION / FIRE RESISTANT RATINGS (Table 8.2.1.2)

TYPE OF CONSTRUCTION:

EXTERIOR BEARING WALLS:

INTERIOR BEARING WALLS SUPPORTING > 1 FLOOR:

INTERIOR BEARING WALLS SUPPORTING 1 FLOOR & ROOF:

COLUMNS AND BEAMS SUPPORTING > 1 FLOOR:

COLUMNS AND BEAMS SUPPORTING 1 FLOOR & ROOF:

FLOOR - CEILING ASSEMBLIES:

ROOF - CEILING ASSEMBLIES:

INTERIOR NONBEARING WALLS:

EXTERIOR NONBEARING WALLS

II (000)

0 HRS

0 HRS

0 HRS

0 HRS

0 HRS

0 HRS

0 HRS

0 HRS

0 HRS

NFPA 10 PORTABLE FIRE EXTINGUISHERS 2018

NFPA 70 NATIONAL ELECTRICAL CODE 2020

NFPA 99 HEALTH CARE FACILITIES CODE 2018

NFPA 101 LIFE SAFETY CODE 2018

PG-18-3 DESIGN AND CONSTRUCTION PROCEDURES JULY 2004

PG-18-5 EQUIPMENT GUIDE LIST JANUARY 2019

PG-18-9 SPACE PLANNING CRITERIA OCTOBER 2015

PG-18-12 PACT SPACE MODULE DESIGN GUIDE JUNE 2015

PG-18-13 VA BARRIER FREE DESIGN STANDARD JANUARY 2017

PG-18-15 MINIMUM REQUIREMENTS FOR A/E SUBMISSIONS MAY 2006

HVAC DESIGN MANUAL MARCH 2020

PLUMBING DESIGN MANUAL MAY 2018

FIRE PROTECTION DESIGN MANUAL DECEMBER 2015

PHYSICAL SECURITY AND RESILIENCY DESIGN MANUAL JANUARY 2015

Bid Item 1 (Base Bid): Work includes general construction, alterations, roads, walks, grading, drainage, mechanical, electrical, plumbing, technology and other work as indicated on the Construction Drawings and Specifications.

Period of Performance: 425 calendar days from Notice to Proceed (NTP).

Bid Item 2 (Alternate 1): All work indicated in Bid Item 1 (Base Bid) except, remove Work associated with electrical connections related to a futuer temporary chiller (including exterior connections box and electrical feeder) as indicated on the drawings.

Period of Performance: 425 calendar days from NTP.

Bid Item 3 (Alternate 2): All work indicated in Bid Item 2 (Alternate 1) except, remove Work associated with RTU-15 conversion from DX cooling to central plant chilled water cooling and as indicated on the Drawings.

Period of Performance: 425 calendar days from NTP.

Bid Item 4 (Alternate 3): All work indicated in Bid Item 3 (Alternate 2) except, remove Work associated with converting RTU-14 to central plant chilled water cooling and as indicated on the Drawings.

Period of Performance: 411 calendar days from NTP.

Bid Item 5 (Alternate 4): All work indicated in Bid Item 4 (Alternate 3) except, remove Work associated with the existing 1750 kW emergency power and as indicated on the Drawings.

Period of Performance: 390 calendar days from NTP.

Bid Item 6 (Alternate 5): All work indicated in Bid Item 5 (Alternate 4) except, remove Work associated with Chiller number 4 and associated branch piping and as indicated on the Drawings.

Period of Performance: 369 calendar days from NTP.

INTERNATIONAL BUILDING CODE SUMMARY (2018)

ARCHITECTURE

A-100 DEMOLITION SITE PLAN / ROOF PLAN

A-101 DEMOLITION PLANS AND ELEVATIONS

A-110 PARTIAL FIRST FLOOR DEMOLITION REFLECTED CEILING PLAN

(SURGERY CENTER) - BID ALTERNATE NO. 3

A-200 ARCHITECTURAL SITE PLAN

A-201 FIRST FLOOR PLAN AND DETAILS

A-202 FIRST FLOOR EQUIPMENT PLAN

A-203 OVERALL ROOF PLAN

A-204 ROOF PLAN

A-301 EXTERIOR ELEVATIONS

A-302 BUILDING SECTIONS

A-401 WALL SECTIONS AND DETAILS

A-402 WALL SECTONS AND DETAILS

A-403 ENLARGED DETAILS

A-404 ENLARGED DETAILS

A-405 CHILLED WATER PIPING ENCLOSURE ELEVATION AND SECTION

A-501 FIRST FLOOR REFLECTED CEILING PLAN

A-502 PARTIAL FIRST FLOOR REFLECTED CEILING PLAN (SURGERY CENTER)

- BID ALTERNATE NO. 3

A-601 STAIR DETAILS

A-602 ENLARGED DETAILS

A-701 ROOM & DOOR SCHEDULES, DETAILS

PROJECT NUMBER:

SUBMITTAL FOR:

DRAWING INDEX: CODE DATA:LOCATION MAP:

LOCATION MAP:

CONSTRUCT CHILLER PLANT

420 N. JAMES ROAD, COLUMBUS, OHIO 43219

757-15-102

BID & CONSTRUCTION (REVISED)

NFPA 101 LIFE SAFETY CODE SUMMARY (2018)420 N. JAMES ROAD

COLUMBUS, OH 43219

AREA OF WORK

GENERAL

G-100 COVER SHEET

G-101 NOTES AND SYMBOLS

G-102 LIFE SAFETY PLAN

G-103 PENETRATION FIRE STOPPING DETAILS

G-104 PENETRATION FIRE STOPPING DETAILS

G-105 PENETRATION FIRE STOPPING DETAILS

G-106 PENETRATION FIRE STOPPING DETAILS

STRUCTURAL

S-001 GENERAL NOTES

S-101 FOUNDATION AND ROOF FRAMING PLANS

S-102 FRAMING PLANS

S-103 CHP BOILER PLANT PIT

S-104 SURGERY CENTER PIPE ENCLOSURE & PIT

S-105 PARTIAL EXISTING 3RD FLOOR PIPE SUPPOT LAYOUT PLAN

S-301 SECTIONS

S-302 SECTIONS

S-303 SECTIONS

S-501 TYPICAL DETAILS

S-502 TYPICAL DETAILS

FIRE PROTECTION

FP-001 FIRE PROTECTION SYMBOLS, NOTES, & DETAILS

FP-101 FIRE PROTECTION PLAN - FIRST FLOOR

FP-102 FIRE PROTECTION PLAN - CHILLER PLANT FLOOR

PLUMBING

P-001 PLUMBING SYMBOLS AND NOTES

PD-153 ACC THIRD FLOOR PLUMBING DEMOLITION PLAN

P-101 PLUMBING PLAN - UNDERSLAB

P-102 PLUMBING PLAN - CHILLER PLANT FLOOR

P-103 PLUMBING PLAN - ROOF

P-501 PLUMBING DETAILS

P-502 PLUMBING DETAILS

P-601 PLUMBING SCHEDULES AND ISOMETRICS

MECHANICAL

M-001 MECHANICAL SYMBOLS AND NOTES

MD-123 BOILER ROOM HVAC PIPING DEMOLITION PLAN

MD-151A ACC FIRST FLOOR MECHANICAL DEMOLITION PLAN

MD-151B ACC FIRST FLOOR HVAC PIPING DEMOLITION PLAN

MD-152 ACC SECOND FLOOR HVAC PIPING DEMOLITION PLAN

MD-153 ACC THIRD FLOOR HVAC PIPING DEMOLITION PLAN

MD-154 ACC FOURTH LEVEL ROOF HVAC DEMOLITION PLAN

M-111 HVAC DUCTWORK PLAN - CHILLER PLANT FLOOR

M-121 ENLARGED HVAC PIPING PLAN - CHILLER PLANT FLOOR - NORTH

M-122 ENLARGED HVAC PIPING PLAN - CHILLER PLANT FLOOR - SOUTH

M-123 BOILER ROOM AND UNDERGOUND CHILLED WATER PIPING PLAN

M-131 MECHANICAL PLAN - CHILLER PLANT ROOF

M-141 FUEL OIL PIIPING PLAN

M-151A ACC FIRST FLOOR MECHANICAL PLAN

M-151B ACC FIRST FLOOR HVAC PIPING PLAN

M-152 ACC SECOND FLOOR HVAC PIPING PLANS

M-153A ACC THIRD FLOOR / ROOF HVAC PIPING PLAN

M-153B ACC THIRD FLOOR / ROOF HVAC PIPING PLAN

M-153C ACC THIRD FLOOR / ROOF HVAC PIPING PLAN

M-301 MECHANICAL SECTIONS

M-302 MECHANICAL SECTIONS

M-303 MECHANICAL SECTIONS

M-501 MECHANICAL DETAILS

M-502 MECHANICAL DETAILS

M-503 MECHANICAL DETAILS

M-504 MECHANICAL DETAILS

M-601 MECHANICAL SCHEDULES

M-602 MECHANICAL SCHEDULES

M-603 PIPING DIAGRAMS

M-604 ACC BUILDING TEST AND BALANCE AND TEMP CONTROLS PLAN

M-605 FUEL OIL PIPING DIAGRAM

M-701 TEMPERATURE CONTROLS

M-702 TEMPERATURE CONTROLS

M-703 TEMPERATURE CONTROLS

M-704 EMERGENCY GENERATOR FUEL OIL SYSTEM CONTROLS

ELECTRICAL

E-001 ELECTRICAL LEGEND AND GENERAL NOTES

E-002 TECHNOLOGY LEGEND AND GENERAL NOTES

E-003 LIGHTING FIXTURE SCHEDULE AND DETAILS

ED-101 PARTIAL MAIN BUILDING FIRST FLOOR ELECTRICAL DEMOLITION PLAN - AREA B

ED-102 PARTIAL MAIN BUILDING FIRST FLOOR ELECTRICAL DEMOLITION PLAN - AREA A

ED-103 PARTIAL MAIN BUILDING SECOND FLOOR DEMOLITION PLAN

ED-104 PARTIAL MAIN BUILDING THIRD FLOOR ROOF ELECTRICAL DEMOLITION PLAN

ED-105 PARTIAL MAIN BUILDING FOURTH FLOOR ROOF ELECTRICAL DEMOLITION PLAN

ED-106 BOILER PLANT / CHILLER PLANT ELECTRICAL DEMOLITION PLAN

E-101 PARTIAL ELECTRICAL SITE PLAN

E-102 PARTIAL MAIN BUILDING THIRD FLOOR ELECTRICAL PLAN

E-103 BOILER PLANT / CHILLER PLANT ELECTRICAL SITE PLAN

E-104 BOILER PLANT / CHILLER PLANT ROOF LIGHTING AND FIRE ALARM PLAN

E-105 BOILER PLANT / CHILLER PLANT POWER AND TECHNOLOGY PLAN

E-106 BOILER PLANT SECOND FLOOR / CHILLER PLANT ROOF ELECTRICAL PLAN

E-107 BOILER PLANT / CHILLER PLANT MECHANICAL CONNECTIONS PLAN

E-108 BOILER PLANT / CHILLER PLANT ROOF MECHANICAL CONNECTIONS PLAN

E-109 BOILER PLANT / CHILLER PLANT GROUNDING SITE PLAN

E-201 PARTIAL SECOND FLOOR ELECTRICAL EQUIPMENT AND RACEWAY LAYOUT

PLAN - SOUTH

E-202 PARTIAL SECOND FLOOR ELECTRICAL EQUIPMENT AND RACEWAY LAYOUT

PLAN - NORTH

E-501 ELECTRICAL DETAILS

E-502 ELECTRICAL DETAILS

E-503 ELECTRICAL DETAILS

E-504 ELECTRICAL DETAILS

E-505 TECHNOLOGY DETAILS

E-506 SUBSTATION DETAIL AND GENERAL NOTES

E-600 ELECTRICAL ONE LINE LEGEND AND GENERAL NOTES

E-601 MAIN BUILDING EXISTING ONE-LINE DIAGRAM

E-602 BOILER PLANT / CHILLER PLANT ONE-LINE DIAGRAM

E-603 GENERATOR CONTROL WIRING DIAGRAM

E-604 ELECTRICAL GROUNDING SYSTEM DIAGRAM

E-605 FUEL OIL TRANSFER PUMP PACKAGE

E-701 PANEL SCHEDULES (1 OF 2)

E-702 PANEL SCHEDULES (2 OF 2)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS

321 4 5 6 7 8 9 10

757-15-102

7850 Freeway Circle

440.243.2000 t

Cleveland, OH 44130

440.243.3305 f

Arch. Proj. No.:

C U s e rs

\j c h o \D o c u m e n ts

\R e v it M o d e ls

\1

R

V A

C o lu m b u s C h ill e r

P la n t R e v is io n

C e n tr a l_ jd c h o

.r v t

/5

/2

:0

:4

A

M

G-100

COVER SHEET CONSTRUCT CHILLER PLANT

420 N. JAMES ROAD, COLUMBUS,

OHIO 43219

05/06/2022 RG jdc

BID & CONSTRUCTION

(REVISED)18912

CIVIL

VF101 TOPOGRAPHIC SURVEY (FOR REFERENCE ONLY)

VF102 TOPOGRAPHIC SURVEY (FOR REFERENCE ONLY)

VF103 TOPOGRAPHIC SURVEY (FOR REFERENCE ONLY)

C-100 SITE PLAN

C-200 NOTES & DETAILS

C-300 EROSION & SEDIMENT CONTROL NOTES & DETAILS

C-301 EROSION & SEDIMENT CONTROL NOTES & DETAILS

BUILDING CODE / PROJECT MANUALS

DESCRIPTION OF WORK

Revisions: Date:

FINAL BID & CONSTRUCTION 11/24/2021

FINAL BID & CONSTRUCTION (REVISED) 05/06/2022

File details come from the government source that posted it. Updated .