1604000 F Wastewater rF.pdf

PDF 95 KB Posted

Attached to
Bridgeport BOSC Federal contract opportunity
Solicitation number
N6247322R3616
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document outlines deliverables and reporting requirements for a wastewater treatment services contract. The contractor must submit copies of state certification and business licenses prior to award and upon renewal. Permits must be submitted 5 days prior to work requiring permits. Within 30 days of award and within 5 days of any changes, the contractor must provide standard operating procedures and a critical spare parts inventory. The contractor must submit monthly wastewater effluent reports within 4 days of month end or 2 days if non-compliant. Other required recurring deliverables include operator attendance schedules prior to start of work and within 2 days of request, and monthly wastewater treatment operating records, logs and reports within 3 days of month end.

View the file

Other files for this federal contract opportunity

Other files attached to Bridgeport BOSC, newest first.
File Type Posted
Attachment J-0200000-10 UnPopulated ELINS MCMWTC Bridgeport BOS rFc.xlsx XLSX spreadsheet
EXHIBIT E.docx DOCX document
Amendment 01.pdf PDF
1606000 J Water rF.pdf PDF
1604000 J Wastewater rF.pdf PDF
1503030 J Integratd Solid Waste Management rF.pdf PDF
1700000 F BSVE rF.pdf PDF
1503020 F Pest Control rF.pdf PDF
1503050 F Grounds Maintenance and Landscaping rF.pdf PDF
EXHIBITS A-F.docx DOCX document
J-L-01 RFI Form.docx DOCX document
0100000 C General Information rF.pdf PDF
1700000 C BSVE Rental rF.pdf PDF
1503060-02 J Pavement Clearance rF.xlsx XLSX spreadsheet
1606000 C Water rF.pdf PDF
1502000 J Facility Investment rF.pdf PDF
1503050 J Grounds Maintenance and Landscaping rF.pdf PDF
Attachment J-0200000-10 UnPopulated ELINS MCMWTC Bridgeport BOS rF.xlsx XLSX spreadsheet
1700000 J BSVE Rental rF.pdf PDF
1502000 F Facility Investment rF.pdf PDF
1503060 F Pavement Clearance rF.pdf PDF
1503020 C Pest Control rFa.pdf PDF
Sponsorship Form.pdf PDF
1502000 C Facility Investment rF.pdf PDF
1503050 C Grounds Maintenance and Landscaping rF.pdf PDF
1503030 C Integrated Solid Waste Management rF.pdf PDF
0200000 F Management and Administration rF.pdf PDF
1503030 F Integratd Solid Waste Management rF.pdf PDF
1503050-05 J Grounds Maintenance rF.xlsx XLSX spreadsheet
N62473-22-R-3616 Bridgeport BOSC.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1604000 – Wastewater

SECTION F: DELIVERIES OR PERFORMANCE

Note: Contractor shall be responsible for all reports not shown or missed to be included under this Section F, yet required for submittals under this contract. See other Sections within this Solicitation for further processes and procedures. It is the Contractor’s responsibility to ensure that all records and reports are provided in a timely manner.

Reports are the Contractor’s responsibility. The Contractor shall submit reports in accordance with the requirements and applicable references specified in other paragraphs within this Solicitation.

DELIVERABLES

Annex/Spec Item

Form Attachment

Number Deliverable Title

Date (s) of Submission

Distribution

Frequency Original/ Copies

Number of Copies

(including original)

1604000/ 2.2.1

N/A

Copy of State Certification for Contractor Personnel

15 calendar days prior to start of work. Copies of renewed certifications shall also be submitted.

KO/COR 2 As required

1604000/ 2.3.3

N/A

Copy of Local/State Business License

Prior to contract award. Copies of renewed licenses shall also be submitted.

KO/COR 2 1 per state

1604000/ 2.3.4

N/A Permits 5 days prior to the start of work requiring permits.

KO/COR 2 As required

1604000 / 3 N/A Critical Spare

Parts Inventory 15 days after award KO/COR 4

Annually.

Update if the requirements change.

1604000 / 3.1 N/A Standard Operation Procedures

Within 30 days after contract start and within five days after making changes to any plant operating procedure, equipment or component.

KO/COR 4

Once.

Update if the requirements change.

1604000 / 3.1.1 N/A

Laboratory Analysis of Wastewater

Effluent Report

Within 2 days of discovery when found non-compliant.

4 days after the end of the month if compliant.

KO/COR 4

Monthly or within 2 days if found non-compliant

DELIVERABLES

Annex/Spec Item

Form Attachment

Number Deliverable Title

Date (s) of Submission

Distribution

Frequency Original/ Copies

Number of Copies

(including original)

1604000 / 3.1.2 N/A Schedule of

Operator Attendance

7 days prior to the start of work Within

2 days of Request

KO/COR 4

7 days prior to the start of work and as requested

1604000 / 3.1.3 N/A

Wastewater Treatment Operating

Records, Logs and Reports

3 days after the end of the month during which work is performed

KO/COR 4

Monthly