1502000 F Facility Investment rF.pdf

PDF 85 KB Posted

Attached to
Bridgeport BOSC Federal contract opportunity
Solicitation number
N6247322R3616
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document outlines deliverables and performance requirements for facility investment and maintenance services for various government installations. Key deliverables include preventative maintenance summary reports, service order summary reports, preventative maintenance program plans, inspection reports for various building systems, and recurring services program summary reports. These deliverables must be submitted on a monthly, annual, or as-required basis to the Contracting Officer and Contracting Officer's Representative, within timeframes ranging from 7 to 30 days depending on the specific deliverable. The contractor must also submit certifications and licenses within 15 days of award, preventative maintenance schedules 5 days prior to each month, and fuel delivery schedules by the 25th day of preceding months. The opportunity is solicited by the Naval Facilities Engineering Command for services supporting the Marine Corps Mountain Warfare Training Center, Liberty Military Housing Complex, Hawthorne Army Depot and other outlying areas.

View the file

Other files for this federal contract opportunity

Other files attached to Bridgeport BOSC, newest first.
File Type Posted
Attachment J-0200000-10 UnPopulated ELINS MCMWTC Bridgeport BOS rFc.xlsx XLSX spreadsheet
EXHIBIT E.docx DOCX document
Amendment 01.pdf PDF
1606000 J Water rF.pdf PDF
1604000 J Wastewater rF.pdf PDF
1503030 J Integratd Solid Waste Management rF.pdf PDF
1700000 F BSVE rF.pdf PDF
1503020 F Pest Control rF.pdf PDF
1503050 F Grounds Maintenance and Landscaping rF.pdf PDF
EXHIBITS A-F.docx DOCX document
J-L-01 RFI Form.docx DOCX document
0100000 C General Information rF.pdf PDF
1700000 C BSVE Rental rF.pdf PDF
1604000 F Wastewater rF.pdf PDF
1503060-02 J Pavement Clearance rF.xlsx XLSX spreadsheet
1606000 C Water rF.pdf PDF
Sponsorship Form.pdf PDF
1502000 C Facility Investment rF.pdf PDF
1503050 C Grounds Maintenance and Landscaping rF.pdf PDF
1503030 C Integrated Solid Waste Management rF.pdf PDF
0200000 F Management and Administration rF.pdf PDF
1503030 F Integratd Solid Waste Management rF.pdf PDF
1503050-05 J Grounds Maintenance rF.xlsx XLSX spreadsheet
N62473-22-R-3616 Bridgeport BOSC.pdf PDF
1502000 J Facility Investment rF.pdf PDF
1503050 J Grounds Maintenance and Landscaping rF.pdf PDF
Attachment J-0200000-10 UnPopulated ELINS MCMWTC Bridgeport BOS rF.xlsx XLSX spreadsheet
1700000 J BSVE Rental rF.pdf PDF
1503060 F Pavement Clearance rF.pdf PDF
1503020 C Pest Control rFa.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1502000 – Facility Investment

SECTION F: DELIVERIES OR PERFORMANCE

DELIVERABLES

Annex/ Spec Item

Form Attachment

Number Deliverable Title

Date (s) of Submission

Distribution

Frequency Original/ Copies

Number of Copies (including original)

1502000/ 2.2.1

N/A

Certification and Licenses

Within 15 days after award or as requested by the

KO

KO/COR 1

Once for initial submittal, then as requested

1502000/

J-1502000-38 Preventive

Maintenance Summary Report

First work day of each month

KO/COR 2 Monthly

1502000/ 3.1

J-1502000-37 Service Order

Summary Report First work day of each month KO/COR 2 Monthly

1502000/ 3.2

Preventive Maintenance Program Plan

30 calendar days after contract award

KO/COR 2

Annually, Hard Copy

1502000/ 3.2

N/A Monthly PM Work

Schedule

Five work days prior to the beginning of each month

KO/COR 1 Monthly

150200/ 3.2.1

N/A Refrigerant Status

Report As required

KO/COR 2

Within 7 days of Completion of Work, Electronic

150200/ 3.2.7

N/A Fire Inspection

Report (Annual)

Within 30 days of Completion of Work, Electronic

150200/ 3.2.7

N/A Fire Inspection

Report (Five Year) of Completion of Work, Electronic

150200/ 3.2.14

N/A Alerton Inspection of Completion of Work, Electronic

150200/ 3.2.25

N/A Johnson DDC

Inspection Report of Completion of Work, Electronic

1502000/

3.2 and 3.4

Monthly PM, Inspection, Testing, and Certification Summary Report

KO/COR 2 Monthly

3.4

Inspection, Testing, Program Summary

Within 7 days of Completion of Work

3.4

Inspection, Testing

Schedule and a copy of all Equipment

Certifications

With 7 days of Completion of

Work

1502000/ 3.4.1

Boiler/UPV Inspection Report

With 30 days of Completion of

Work

1502000/ 3.4.5

Inspection and Test Report for Vertical

Transportation Equipment (Wheel

Chair Lift)

As required KO/COR 2 Within 7 days of Completion of Work

1502000/ 3.4.8

Oil Water Separator Inspection

As required KO/COR 2 Within 7 days of Completion of Work

1502000/ 3.4.9

Propane Tank Leak Inspection

As required KO/COR 2 Within 30 days of Completion of Work

1502000/ 3.4.11

Roof Inspection

As required KO/COR 2 Within 30 days of Completion of Work

1502000/ 3.5

Other Recurring Services Program Summary Report

First work day of each month

KO/COR 2 Monthly

1502000/ 3.5.10

N/A Diesel Fuel Delivery Schedule/Accountab ility Report Monthly KO/COR 2

By the 25th day of the preceding month

1502000/ 3.5.11

N/A Propane Delivery

Schedule Monthly KO/COR 2

By the 25th day of the preceding month