09 80 00 Fiberboard Wall Ceiling Treatment_ORCA_0003.pdf

PDF 224 KB Posted

Attached to
ORCA 150025 - Correct Life Safety and Critical Def
Solicitation number
140P2019R0045
Issued by

About this file

This solicitation notice seeks proposals for a construction contract to correct life safety and critical deficiencies at the Oregon Caves Chateau, a National Historic Landmark. The proposed single-phase project includes installing fire suppression and detection systems, improving egress doors and accessibility, adding an elevator, replacing water supply and waste piping, upgrading the main electric service panel, and adding plywood shear walls and steel balconies to meet fire codes. The estimated price range is over $10 million, and the anticipated period of performance is from April 2020 to September 2021. The solicitation will be issued electronically on the Federal Business Opportunities website on or around October 21, 2019. The National Park Service encourages participation from small businesses, veteran-owned small businesses, small disadvantaged businesses, and women-owned small businesses.

View the file

Other files

File Type Posted
01 27 00-Definition of Contract Line Items_ORCA Amend 4_0004.pdf PDF
140P2019R0045 Amend 4 SOC_0004.pdf PDF
07_ContractPriceSchedule_ORCA150025_Amend 4_0004.xls XLS spreadsheet
Sol_140P2019R0045_Amd_0004.pdf PDF
Sol_140P2019R0045_Amd_0003.pdf PDF
B03_Wage_Determination_OR20200039 1-3-2020_0003.pdf PDF
140P2019R0045 Amend 3 SOC_0003.pdf PDF
Sol_140P2019R0045_Amd_0001.pdf PDF
Sol_140P2019R0045_Amd_0002.pdf PDF
00 01 10 Table of Contents_ORCA_r1_0002.pdf PDF
140P2019R0045 Amend 1 SOC.updated_0002.pdf PDF
09 80 00 Fiberboard Wall & Ceiling Treatment_0002.pdf PDF
Sign-in sheet_0002.pdf PDF
L8.03 Landscape Details - A1_0002.pdf PDF
A06_Specs_03_XAPPENDIX-C_ORCA_Chateau_Hazardous_Materials_Report.pdf PDF
A06_Specs_03_XAPPENDIX-D_ORCA_Fire_Protection_Basis_of_Design.pdf PDF
A06_Specs_03_XAPPENDIX-B_ORCA_STRUCT_CALCS_201900913_Pages_1_-_164.pdf PDF
A06_Specs_03_XAPPENDIX-A_ORCA_Geotech_Report.pdf PDF
A06_Specs_03_XAPPENDIX-B_ORCA_STRUCT_CALCS_201900913_Pages_165_-_330.pdf PDF
B08_Solit_PSP_Vol_II_SubKPlanForm_REQD.doc DOC document
B08_Solic_Contract_Price_Schedule_ORCA150025_FINAL.xls XLS spreadsheet
A06_Dwgs_01_ORCA_100CD_FINAL_0_TITLE.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_3_ARCHITECTURE.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_6_PLUMBING.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_8_ELECTRICAL.pdf PDF
B08_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Solic_140P2019R0045_SF_1442_&_Clauses.pdf PDF
A06_Specs_02_ORCA_100CD_FINAL_SPECS-DIV-01.pdf PDF
B08_Solit_PSP_Vol_I_Exp_REQD.docx DOCX document
B08_Solic_SF24-16d.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_7_MECHANICAL.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_4_FIRE_SUPPRESSION.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_2_STRUCTURAL.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_5_FIRE_DETECTION.pdf PDF
A06_Specs_02_ORCA_100CD_FINAL_SPECS-DIV-15-48.pdf PDF
B03_Wage_Determination_OR20190039_8-30-19.pdf PDF
B08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
A06_Specs_02_ORCA_100CD_FINAL_SPECS-DIV-02-14.pdf PDF
A06_Dwgs_01_ORCA_100CD_FINAL_1_LANDSCAPE.pdf PDF
B08_Solit_PSP_Cover.rtf RTF text file
B08_Solit_PSP_Vol_II_Equals.doc DOC document
B08_Solit_PSP_Vol_II_HazMat.doc DOC document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORCA - 150025 09 80 00 - 1

FIBERBOARD WALL & CEILING TREATMENT

SECTION 09 80 00 – FIBERBOARD WALL & CEILING TREATMENT

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Fiberboard Wall and Ceiling Paneling.

1.2 RELATED REQUIREMENTS

A. Section 06 10 00 - Rough Carpentry: wood substrates and structure.

B. Section 09 21 16 - Gypsum Board: Installation and requirements for wall assemblies.

C. Section 09 90 00 - Painting and Coatings: Finish

1.3 REFERENCE STANDARDS

A. ASTM C 209 - Test Methods for Cellulosic Fiber Insulating Board.

B. ASTM C 518 - Standard Test Method for Steady-State Thermal Transmission Properties by

Means of the Heat Flow Meter Apparatus.

C. ASTM E 84 - Test Method for Surface Burning Characteristics of Building Materials.

D. UL listed, File R16381.

E. Forest Stewardship Certification (FSC): CoC Cert no. 5682.

F. ICC-ES Report ESR-1374.

1.4 SUBMITTALS

A. See Section 01 33 23 - Submittal Procedures for submittal procedures.

B. Product Data: Provide Manufacturer's data sheets on each product to be used, including:

1. Preparation instructions and recommendations.

2. Storage and handling requirements and recommendations.

3. Installation methods

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing products specified in this section, with not less than 10 years of documented experience.

B. Not Permitted: formaldehyde or other toxic materials. Refer to Section 01 57 19.11 for additional requirements regarding safety of materials.

ORCA - 150025 09 80 00 - 2

1.6 MOCK-UP

A. Provide mock-up of fiberboard panels at vertical and running bond patterns to illustrate finish, color, joint, and pattern for approval by Contracting Officer. Comply with requirements of

Section 01 33 23 Submittal Procedures.

B. Contracting Officer to determine location of mock up.

C. Mock up may remain as part of work upon approval by Contracting Officer. Work to remain to be protected for duration of construction.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Store products in manufacturer's unopened packaging with labels intact until ready for installation.

B. Inspect the materials upon delivery to assure that specified products have been received. Report damaged material immediately to the delivering carrier and note such damage on the carrier's freight bill of lading.

C. Store materials in a dry place, indoors, on raised platform protected from weather damage

1.8 FIELD CONDITIONS

A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's absolute limits.

B. Climatize panels to existing moisture conditions and for not less than 24 hours before installation. Comply with manufacturer’s recommendations for acclimatization.

PART 2 PRODUCTS

2.1 MANUFACTURERS

A. Basis of Design: Homasote Company; www.homasote.com.

1. Product to match Historic existing panels in size, pattern, and joint condition (beveled most locations – beadboard joint behind lobby desk) per Drawings.

2. Substitutions: Not permitted.

2.2 MATERIALS

A. A. PINnacle Tackboard Panels: Class C fire-rated. Molded, recycled post-consumer paper, cellulose fiber structural panel. Physical properties as follows:

1. Thickness: 1/2 inch (13 mm).

2. Density: 26-28 pcf (416-448 kg/cu. m) tested in accordance with ASTM C 209.

3. Tensile Strength: When tested in accordance with ASTM C 209:

4. Parallel: 450-700 psi (3,100-4,830 kPa).

5. Transverse: 750-1000 psi (5.1171-6.894 kPa).

6. Hardness (Janka Ball): 230 lbs (104 kg) tested in accordance with ASTM D 1037.

7. Water Absorption by Volume: When tested in accordance with ASTM C 209:

a. 2 hour immersion: 7 percent maximum.

http://www.homasote.com/

ORCA - 150025 09 80 00 - 3

8. Expansion: 50 to 90 percent relative humidity, 0.25 % in accordance with ASTM C 209.

9. Thermal Resistance: When tested in accordance with ASTM C 209 per ASTM C 518:

a. R-value: 1.2 for 1/2 inch thick board.

10. Noise reduction coefficient (NRC): 0.20

11. Flame Spread: 76 to 200 tested in accordance with ASTM E 84, Class III or C.

12. Width: Panel width varies per location as indicated on Drawings.

13. Pattern: Pattern varies per location as indicated on Drawings.

14. Edge: Beveled edge in all locations except bead board profile to match existing behind lobby desk as shown on Drawings.

15. Finish: STN-3 and as determined by mock-up per Section 09 90 00 Painting and

Coatings.

2.3 ACCESSORIES

A. Panel Fasteners:

1. Nails, Wood Framing: Length required to penetrate wood framing, 3/4 inch minimum.

2. Screws:

a. General: 20 gauge or heavier, self-tapping drywall type steel screw.

b. Wood Framing: Coarse thread drywall type wood screw, length required to penetrate framing, 3/4 inch minimum.

c. Metal Framing: 22-25 gauge, drywall type steel screw.

B. Drywall fastener for decoupled wall installation: #10 drywall screw or laminating screw.

PART 3 EXECUTION

3.1 EXAMINATION

A. Examine substrates upon which work will be installed.

B. Verify framing member spacing complies with manufacturer’s requirements depending on substrates and installation methods.

C. If substrate preparation is responsibility of another installer, notify Contracting Officer of unsatisfactory preparation before proceeding.

D. Verify what environmental conditions are, and will continue to be maintained in accordance with manufacturer’s recommendations.

E. Fiberboard wall and ceiling panels to exactly replicate existing pattern and joints of historic

“Nu-Wood” panels to be removed at Levels B1 and 1, and the main public corridors of Levels 2 and 3. Contractor to carefully document existing nu-wood panels prior to replacement.

F. Starting work by installer is acceptance of substrate and environmental conditions.

3.2 PREPARATION

A. Follow manufacturer’s instructions by separating and allowing panels to be exposed to environmental temperature and humidity conditions for not less than 24 hours before start of installation.

ORCA - 150025 09 80 00 - 4

3.3 INSTALLATION

A. Install in accordance with manufacturer's instructions.

B. Install only clean dry panels. Do not install wet panels.

C. Wall Panel Installation: Space panel joints 1/8 inch (3 mm) apart; 1/4 inch (6 mm) space at floors, ceilings, and window and door frames. Install gypsum wallboard or other wall finish panels so that finish panel joints are staggered and do not coincide with sound barrier panel joints. Install in accordance with finish panel manufacturer’s installation recommendations.

D. Finish panels with STN-3 per mock-up and Section 09 90 00

3.4 CLEANING

A. Comply with manufacturer's recommendations for repairing damaged panels.

B. Replace panels that cannot be repaired.

3.5 PROTECTION

A. Protect installed products from subsequent construction operations.

B. Touch-up, repair, or replace damaged products before Substantial Completion.

END OF SECTION