SECTION_31_23_19_-_Dewatering_R1_0004.pdf

PDF 122 KB Posted

Attached to
Oglala Dam Construction Federal contract opportunity
Solicitation number
140A1623R0026
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This technical specification outlines requirements for dewatering systems for the Oglala Dam Remediation Project. The contractor will be required to design, install, operate, and remove water control structures like sumps, trenches, wells and pumps to manage reservoir water, tailwater, groundwater and surface water during dam construction. The dewatering plan must be designed and stamped by a professional engineer with relevant experience. Systems must control inflow to excavations, collect seepage, and maintain dry working conditions without damaging facilities, foundations or surrounding areas. Upon completion, all dewatering elements will be removed and voids grouted or backfilled. The related federal contract solicitation is for the Oglala Dam Construction project issued by the Bureau of Indian Affairs Central Office.

View the file

Other files for this federal contract opportunity

Other files attached to Oglala Dam Construction, newest first.
File Type Posted
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev3_0006.docx DOCX document
Sol_140A1623R0026_Amd_0006.pdf PDF
SECTION_M_Rev2_0006.docx DOCX document
SECTION_00_41_23_-_Bid_Form_R5_0005.pdf PDF
067_SP-S-14_SERVICE_SPILLWAY_STILLING_BASIN_DETAILS_0005.pdf PDF
SECTION_35_20_17_-_Gate_Hydraulic_Operating_Unit_R3_0005.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log_Round_3_FINAL_0005.pdf PDF
SECTION_01_11_00_-_Summary_of_Work_R2_0004.pdf PDF
G-23_Structural_Standard_Notes_0004.pdf PDF
SECTION_31_56_13_-_Deep_Mix_Method_(DMM)_Walls_R2_0004.pdf PDF
SECTION_13_60_00_-_Manufactured_Home_Installation_R3_0004.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R2_0004.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R2_0004.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0004.pdf PDF
SECTION_00_41_23_-_Bid_Form_R4_0004.pdf PDF
E_Revised_Solicitation_SECTION_M_0004.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log_Round_2_0004.pdf PDF
Sol_140A1623R0026_Amd_0004.pdf PDF
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev_2_0004.pdf PDF
OW-S-01_Outlet_Works_Diversion_Intake_Structure_0004.pdf PDF
SECTION_31_56_23_-_Soil-Cement-Bentonite_Cutoff_Wall_R2_0004.pdf PDF
SECTION_03_30_00_-_Cast_in_Place_Concrete_R3_0004.pdf PDF
G-08_Emergency_Spillway_Site_Plan_0004.pdf PDF
EM-C-11_Embankment_Details_0004.pdf PDF
SECTION_31_23_13_-_Subgrade_Preparation_R1_0003.pdf PDF
SECTION_13_60_00_-_Manufactured_Home_Installation_R2_0003.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0003.pdf PDF
Oglala_As-Built_Drawings_0003.pdf PDF
SECTION_00_41_23_-_Bid_Form_R3_0003.pdf PDF
SECTION_13_54_00_-_Dam_Instrumentation_R1_0003.pdf PDF
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev_1_0003.pdf PDF
SECTION_03_40_00_-_Precast_Concrete_R1_0003.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R1_0003.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R1_0003.pdf PDF
SECTION_03_30_00_-_Cast_in_Place_Concrete_R2_0003.pdf PDF
SECTION_03_34_13_-_Controlled_Low_Strength_Material_R1_0003.pdf PDF
SECTION_02_41_13_-_Selective_Site_Demolition_R1_0003.pdf PDF
Oglala_Dam_GDR_Final_0002.pdf PDF
Sol_140A1623R0026_Amd_0002.pdf PDF
Sol_140A1623R0026_Amd_0001.pdf PDF
B08_A9_SF-25A_Payment_Bond_Form.pdf PDF
B08_A5_DOL_Wage_Determination.pdf PDF
B08_A4_Investing_in_America_Brand_Guide.pdf PDF
B08_A2_SOW_and_Technical_Specifications.pdf PDF
B08_A8_SF-25_Performance_Bond_Form.pdf PDF
B08_A7_SF-24_Bid_Bond_Form.pdf PDF
B08_A1_Pricing_Schedule.pdf PDF
B08_A3_Plans_and_Drawings.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log.xlsx XLSX spreadsheet
Sol_140A1623R0026.pdf PDF
Show all 50

Oglala Dam Construction has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF INDIAN AFFAIRS OGLALA DAM SPILLWAY AND OUTLET WORKS

OGLALA DAM SPILLWAY AND OUTLET WORKS SECTION 31 23 19

JUNE 2023 DEWATERING

FOR BID REV 1 PAGE 1 OF 4

SECTION 31 23 19

DEWATERING

GENERAL

1.01 SCOPE OF WORK

A. This Section specifies the requirements for the following general items of Work:

Design water control systems for the management, collection, and disposal of reservoir water, tailwater, groundwater or surface water for the proper construction of all Work.

It is anticipated that the existing outlet works will be utilized to divert flood flows during Phase 1 construction, and the new outlet works will be utilized to divert flood flows during Phase 2 construction.

Install and maintain pumps, piping, drains, channels, well points, wells, and other facilities for the control, collection, and disposal of groundwater for the proper construction of all Work.

Maintain prepared foundations and all other parts of the Work free from seepage or standing water as required for constructing each part of the Work.

Protect claystone bedrock from saturation from groundwater and surface water during excavation and subgrade preparation.

Comply with all applicable environmental protection laws and requirements in operation of the dewatering system and disposal of collected water.

Remove all components of the dewatering systems when no longer required.

1.02 SUBMITTALS

A. Shop Drawings

Submit a Dewatering Plan at least 14 days prior to mobilization for review and approval by the BIA Representative, including the following requirements:

a. Prepared and stamped by a Registered Professional Engineer with experience in design of dewatering systems and control of water for dam construction projects.

b. Drawings and narrative that provide details regarding anticipated types, sizes, capacities, and locations of water control structures, piping, facilities, and calculations to substantiate designs and selected facilities.

c. Drawings and narrative that describe all supplemental dewatering facilities, such as supplemental drainage channels, sedimentation ponds (if required), and silt barriers.

d. Expected discharge volumes from each water control system and points of discharge.

BUREAU OF INDIAN AFFAIRS SECTION 31 23 19

JUNE 2023 DEWATERING

FOR BID REV 1 PAGE 2 OF 4

e. Methods and procedures to fill openings and voids left by removal of the dewatering system.

B. Administrative

Acquire, maintain, and submit copies of discharge permits as required by Federal and state agencies in accordance with Section 01 57 01 – Permitting Requirements and Environmental Controls.

Acquire, maintain, and submit copies of South Dakota Department of Health Well Permit Documents (if required) in accordance with Section 01 57 01 – Permitting Requirements and Environmental Controls.

PRODUCTS

2.01 DEWATERING SYSTEM

A. Specially designed water collection sumps, trenches, or well points for collecting surface water and reservoir water.

B. Pumps and piping to convey and remove collected water.

EXECUTION

3.01 GENERAL

A. Review available topographic, subsurface, and hydrogeologic data for the Project site.

B. Maintain a dry work environment by use of constructed cofferdam during construction in accordance with Section 01 50 00 – Temporary Facilities and Controls.

3.02 INSTALLATION AND OPERATION

A. Install sumps, ditches, and pump systems to control inflow of surface water to excavations, prevent localized ponding of water in construction site, and to collect seepage flows from valley slopes or excavation slopes.

B. Locate every element of dewatering systems to avoid interference with excavation and construction activities.

Do not allow water to accumulate in Work areas until affected Work is satisfactorily constructed.

Prevent damage to facilities, foundations, and surrounding areas and structures.

Perform dewatering operations so that no disturbance to the bearing units and to soil supporting Work will result.

Prevent loss of fines, boiling, quick conditions, or softening of foundation strata.

JUNE 2023 DEWATERING

FOR BID REV 1 PAGE 3 OF 4

Maintain stability of excavation slopes and bottom of excavation so that every phase of Work can be performed safely and in the dry.

C. If the water management and dewatering system does not meet the specified requirements:

Restore the system to meet specified requirements and improve the system if necessary.

Repair resulting damage to Work, to the satisfaction of the BIA Representative, at no cost to the COR and the BIA Representative.

3.03 REMOVAL

A. Remove all elements of the dewatering systems from Site upon completion of the affected Work in accordance with Section 01 50 00 – Temporary Facilities and Controls.

B. Remove crushed stone or coarse fill materials from dewatering trenches and sumps.

Backfill these areas with Class E or F concrete or grout based on the size of the area to be filled. Alternative methods of completely grouting coarse fill materials in dewatering areas may be proposed but are subject to review and approval by the COR and the BIA Representative.

C. Grout all voids in rock left as a result of the dewatering system.

END OF SECTION

JUNE 2023 DEWATERING

FOR BID REV 1 PAGE 4 OF 4

THIS PAGE INTENTIONALLY LEFT BLANK