This technical specification covers the installation of two manufactured homes for the Bureau of Indian Affairs Oglala Dam Remediation Project. The specification requires furnishing and installing two 1,400 square foot manufactured homes with three bedrooms and two bathrooms at locations to be determined by the agency. The homes must comply with 2003 Model Manufactured Home Installation Standards and all applicable federal, state, and tribal codes. Utilities, foundations, and anchoring systems must be provided. The contractor will also relocate two existing trailers within 20 miles and transport furnishings from those homes. Site preparation and installation work must follow the technical requirements outlined. Centennial Homes The Velocity 187002 model or equivalent serves as the basis for the new manufactured homes.

View the file

Other files

File Type Posted
SECTION_M_Rev2_0006.docx DOCX document
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev3_0006.docx DOCX document
Sol_140A1623R0026_Amd_0006.pdf PDF
SECTION_00_41_23_-_Bid_Form_Rev6_0006.docx DOCX document
SECTION_35_20_17_-_Gate_Hydraulic_Operating_Unit_R3_0005.pdf PDF
069_SP-S-15_SERVICE_SPILLWAY_CVC_DETAILS_0005.pdf PDF
067_SP-S-14_SERVICE_SPILLWAY_STILLING_BASIN_DETAILS_0005.pdf PDF
SECTION_00_41_23_-_Bid_Form_R5_0005.pdf PDF
Sol_140A1623R0026_Amd_0005.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log_Round_3_FINAL_0005.pdf PDF
SECTION_31_56_23_-_Soil-Cement-Bentonite_Cutoff_Wall_R2_0004.pdf PDF
OW-S-01_Outlet_Works_Diversion_Intake_Structure_0004.pdf PDF
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev_2_0004.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0004.pdf PDF
SECTION_33_05_24_-_Welded_Steel_Pipe___Fittings_R1_0004.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R2_0004.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R2_0004.pdf PDF
SECTION_01_45_00_-_Quality_Control_R1_0004.pdf PDF
SECTION_31_56_13_-_Deep_Mix_Method_(DMM)_Walls_R2_0004.pdf PDF
Sol_140A1623R0026_Amd_0004.pdf PDF
SECTION_01_11_00_-_Summary_of_Work_R2_0004.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log_Round_2_0004.pdf PDF
G-19_Dam_Mods_Materials_Distribution_Chart_0004.pdf PDF
SECTION_35_20_17_-_Gate_Hydraulic_Operating_Unit_R1_0004.pdf PDF
SECTION_01_50_00_-_Temporary_Facilities_and_Controls_R1_0004.pdf PDF
SECTION_08_90_00_-_Louvers_and_Vents_R1_0004.pdf PDF
E_Revised_Solicitation_SECTION_M_0004.pdf PDF
SECTION_31_23_19_-_Dewatering_R1_0004.pdf PDF
G-23_Structural_Standard_Notes_0004.pdf PDF
SECTION_03_34_13_-_Controlled_Low_Strength_Material_R1_0004.pdf PDF
SECTION_03_40_00_-_Precast_Concrete_R2_0004.pdf PDF
SECTION_00_41_23_-_Bid_Form_R4_0004.pdf PDF
SECTION_03_30_00_-_Cast_in_Place_Concrete_R3_0004.pdf PDF
G-08_Emergency_Spillway_Site_Plan_0004.pdf PDF
EM-C-11_Embankment_Details_0004.pdf PDF
SECTION_13_54_00_-_Dam_Instrumentation_R1_0003.pdf PDF
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev_1_0003.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R1_0003.pdf PDF
Preliminary_RCC_Mix_Design_Report_0003.pdf PDF
SECTION_03_34_13_-_Controlled_Low_Strength_Material_R1_0003.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0003.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R1_0003.pdf PDF
SECTION_13_60_00_-_Manufactured_Home_Installation_R2_0003.pdf PDF
SECTION_00_41_23_-_Bid_Form_R3_0003.pdf PDF
SECTION_03_40_00_-_Precast_Concrete_R1_0003.pdf PDF
SECTION_31_23_13_-_Subgrade_Preparation_R1_0003.pdf PDF
Oglala_As-Built_Drawings_0003.pdf PDF
SECTION_02_41_13_-_Selective_Site_Demolition_R1_0003.pdf PDF
Sol_140A1623R0026_Amd_0003.pdf PDF
SECTION_03_30_00_-_Cast_in_Place_Concrete_R2_0003.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF INDIAN AFFAIRS OGLALA DAM SPILLWAY AND OUTLET WORKS

OGLALA DAM SPILLWAY AND OUTLET WORKS SECTION 13 60 00

JUNE 2023 MANUFACTURED HOME INSTALLATION

FOR BID REV 2 PAGE 1 OF 2

SECTION 13 60 00

MANUFACTURED HOME INSTALLATION

GENERAL

1.01 SCOPE OF WORK

A. This Section specifies the requirements for furnishing and installing two manufactured homes in new locations determined by the AGENCY and the COR.

1.02 SUBMITTALS

A. Shop Drawings

Shop drawings for the manufactured home including plan and profile views of the foundation and home as well as material cut sheets.

Home Installation Work Plan that includes details of equipment, materials, and construction methods to install the homes.

1.03 DESIGN CRITERIA

A. The manufactured home shall comply with the 2003 Edition of the Model Manufactured Home Installation Standards by the Federal Manufactured Housing Consensus Committee.

B. All home utilities shall be provided.

C. The home locations will be determined by the AGENCY and provided prior to CONTRACTOR mobilization to site.

PRODUCTS

2.01 MANUFACTURED HOME

A. Provide two manufactured homes after inspection of existing manufactured homes matching the square footage, bedrooms, and bathrooms. Based on limited information available, CONTRACTOR shall assume the existing manufactured homes are 16 feet wide by 80 feet long, approximately 1,400 square feet, and have 3 bedrooms and 2 bathrooms.

B. Manufactured home shall be in new condition and materials of construction shall meet federal, state, and Tribal building codes, as applicable.

C. Manufacturer and Model

Basis of bid shall be based on providing manufactured homes with similar floor plan as Centennial Homes The Velocity 187002 as manufactured by Friendship Homes, or

BUREAU OF INDIAN AFFAIRS SECTION 13 60 00

OGLALA DAM SPILLWAY AND OUTLET WORKS SECTION 13 60 00

JUNE 2023 MANUFACTURED HOME INSTALLATION

FOR BID REV 2 PAGE 2 OF 2

equivalent. At least 4 months prior to ordering the homes, CONTRACTOR shall coordinate with the BIA for specific model selection.

Floor plan can be accessed via: https://www.centennialhomes.com/floorplan-detail/230946-2962/centennial-homes-of-aberdeen/aberdeen/velocity-mw/the-velocity-187002-5br/#gallery-detail.

EXECUTION

3.01 RELOCATION OF EXISTING HOMES

A. The contractor shall relocate two trailers located in the emergency spillway to a location not yet identified and within 20 miles of the project site. The homes shall not be damaged.

3.02 SITE PREPARATION

A. Survey the site per Section 01 71 23 – Construction Surveying.

B. Prepare selected home site in collaboration with AGENCY.

3.03 INSTALLATION

A. Comply with all installation criteria in the 2003 Edition of the Model Manufactured Home Installation Standards by the Federal Manufactured Housing Consensus Committee.

B. Provide utility hook-ups, septic facilities, and anchor home to site foundation as needed for complete installation.

3.04 MOVING SERVICES

A. Provide professional moving services to relocate furnishings, clothing, equipment, and other miscellaneous items from the existing manufactured homeowners.

3.05 QUALITY CONTROL

A. Refer to Section 01 45 00 – Quality Control.

END OF SECTION