SECTION_00_41_23_-_Bid_Form_R5_0005.pdf

PDF 438 KB Posted

Attached to
Oglala Dam Construction Federal contract opportunity
Solicitation number
140A1623R0026
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This bid form requests pricing for construction services for the Oglala Dam Remediation Project. The Bureau of Indian Affairs is soliciting bids to complete spillway and outlet works construction, which includes mobilization, excavation, embankment construction, a service spillway built with roller compacted concrete, an outlet works, and emergency spillway features. Bidders must provide unit pricing or lump sums for 41 separate line items covering tasks such as clearing, concrete work, piping installation, road construction, and home relocation. Submissions are due by July 2023 according to the solicitation number 140A1623R0026. Award will be made based on bidder qualifications and total proposed pricing.

View the file

Other files for this federal contract opportunity

Other files attached to Oglala Dam Construction, newest first.
File Type Posted
SECTION_00_41_23_-_Bid_Form_Rev6_0006.docx DOCX document
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev3_0006.docx DOCX document
Sol_140A1623R0026_Amd_0006.pdf PDF
069_SP-S-15_SERVICE_SPILLWAY_CVC_DETAILS_0005.pdf PDF
Sol_140A1623R0026_Amd_0005.pdf PDF
SECTION_35_20_17_-_Gate_Hydraulic_Operating_Unit_R3_0005.pdf PDF
067_SP-S-14_SERVICE_SPILLWAY_STILLING_BASIN_DETAILS_0005.pdf PDF
SECTION_01_50_00_-_Temporary_Facilities_and_Controls_R1_0004.pdf PDF
SECTION_35_20_17_-_Gate_Hydraulic_Operating_Unit_R1_0004.pdf PDF
SECTION_08_90_00_-_Louvers_and_Vents_R1_0004.pdf PDF
G-19_Dam_Mods_Materials_Distribution_Chart_0004.pdf PDF
SECTION_01_45_00_-_Quality_Control_R1_0004.pdf PDF
SECTION_03_40_00_-_Precast_Concrete_R2_0004.pdf PDF
SECTION_03_34_13_-_Controlled_Low_Strength_Material_R1_0004.pdf PDF
SECTION_33_05_24_-_Welded_Steel_Pipe___Fittings_R1_0004.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R2_0004.pdf PDF
SECTION_31_23_19_-_Dewatering_R1_0004.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R2_0004.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0004.pdf PDF
SECTION_00_41_23_-_Bid_Form_R4_0004.pdf PDF
E_Revised_Solicitation_SECTION_M_0004.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log_Round_2_0004.pdf PDF
Sol_140A1623R0026_Amd_0004.pdf PDF
SECTION_01_11_00_-_Summary_of_Work_R2_0004.pdf PDF
G-23_Structural_Standard_Notes_0004.pdf PDF
SECTION_31_56_13_-_Deep_Mix_Method_(DMM)_Walls_R2_0004.pdf PDF
SECTION_03_34_13_-_Controlled_Low_Strength_Material_R1_0003.pdf PDF
SECTION_02_41_13_-_Selective_Site_Demolition_R1_0003.pdf PDF
Preliminary_RCC_Mix_Design_Report_0003.pdf PDF
Sol_140A1623R0026_Amd_0003.pdf PDF
SECTION_03_40_00_-_Precast_Concrete_R1_0003.pdf PDF
SECTION_02_41_20_-_Piezometer_Abandonment_R1_0003.pdf PDF
SECTION_01_51_38_-_Diversion_and_Care_of_Water_R1_0003.pdf PDF
SECTION_31_23_13_-_Subgrade_Preparation_R1_0003.pdf PDF
SECTION_13_60_00_-_Manufactured_Home_Installation_R2_0003.pdf PDF
SECTION_03_37_23_-_Roller-Compacted_Concrete_R1_0003.pdf PDF
Oglala_As-Built_Drawings_0003.pdf PDF
SECTION_00_41_23_-_Bid_Form_R3_0003.pdf PDF
SECTION_01_20_00_-_Price_and_Payment_Procedures_Rev_1_0003.pdf PDF
Oglala_Dam_GDR_Final_0002.pdf PDF
Sol_140A1623R0026_Amd_0001.pdf PDF
B08_A6_Solicitation_Questions_and_Answers_Log.xlsx XLSX spreadsheet
Sol_140A1623R0026.pdf PDF
B08_A8_SF-25_Performance_Bond_Form.pdf PDF
B08_A7_SF-24_Bid_Bond_Form.pdf PDF
B08_A1_Pricing_Schedule.pdf PDF
B08_A9_SF-25A_Payment_Bond_Form.pdf PDF
B08_A5_DOL_Wage_Determination.pdf PDF
B08_A4_Investing_in_America_Brand_Guide.pdf PDF
B08_A2_SOW_and_Technical_Specifications.pdf PDF
Show all 50

Oglala Dam Construction has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF INDIAN AFFAIRS OGLALA DAM SPILLWAY AND OUTLET WORKS

SECTION 00 41 23

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 1 OF 6

SECTION 00 41 23

BID FORM

GENERAL

1.01 SCOPE OF WORK

A. This Section specifies the requirements for completing the bid form and bid schedule required by the bidding CONTRACTOR.

1.02 GENERAL REQUIREMENTS

A. Offers will be considered for award on the following schedule, but no offer will be considered for award on only a part of the schedule.

Offerors not responding to all bid schedule line items will be considered nonresponsive and will not be evaluated for award.

Offers will be evaluated based on CONTRACTOR qualifications and the total of the Bid Schedule. Award will be made to the responsive offer which brings the best value.

The COR may remove items from the schedule based on available funds.

B. All offers are subject to the terms and conditions of this solicitation.

C. The quantities in the schedule are estimated quantities for comparison of offers only and except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.

D. See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work.

E. Offerors’ submitted bid schedule shall include all items necessary to complete all construction and Contractor requirements presented in the Drawings and Specifications.

Work items not specifically identified in the Bid Schedule shall be incorporated into the Offerors’ lump sum line item pricing for related work.

1.03 BID SCHEDULE

A. The following table includes the Project Bid Schedule:

BUREAU OF INDIAN AFFAIRS SECTION 00 41 23

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 2 OF 6

Item Supplies or Services Description Estimated

Quantity Unit Unit Price Amount

GENERAL

1 Mobilization/Demobilization

Preparing site access, mobilizing equipment and personnel, setting up equipment and facilities for the Work, cleanup and disposal of waste materials, restoration of the site upon completing the Work, and demobilizing. Item also includes bonds, insurance, permitting, and project management.

1 Lump Sum $ $

2 Temporary Works

Construction and maintenance of temporary construction access roads with road base material, erosion and sediment control, traffic control, site security, and staging areas within construction limits as required.

1 Lump Sum $ $

3 Diversion & Care of Water

Providing labor, materials, and equipment necessary to control and manage storm and reservoir inflows during construction.

Includes design and construction of cofferdams, temporary diversion piping, valves, and incidental items to provide a complete diversion system through all phases of construction.

1 Lump Sum $ $

Clearing, Grubbing & Stripping

Removing trees, vegetation, rubbish, and other deleterious items within the required excavations. Excavating and stockpiling topsoil within the limits of site disturbance. Onsite disposal of excess or unsuitable material is considered incidental to the cost of the Work.

1 Lump Sum $ $

5A Subgrade Preparation – Foundation Protection

Furnishing and installing protective cover over foundation prior to concrete or fill placement as directed by the COR or BIA Representative. Includes initial and final foundation cleanup, removal of loose material and water, cleaning with compressed air or vacuuming, and installation of slush grout where necessary and a mud mat.

3,055 Square Yard $ $

5B Subgrade Preparation – Dental Concrete

Furnishing and placing dental concrete within the footprint of the service spillway and embankments as directed by the COR or BIA Representative. Paid by truck cubic yard as delivered.

1,330 Cubic Yard $ $

6 Dewatering Providing labor, materials, and equipment necessary to control surface water from within the site and seepage infiltration into required excavations.

1 Lump Sum $ $

7 Demolition & Disposal

Demolition, removal, and hauling of materials and structures offsite for disposal. Includes existing spillway, outlet works, metal conduits, fencing and gates, guardrail, and miscellaneous structures.

1 Lump Sum $ $

Left Embankment Access Roads

Construction of the permanent Access Roads on the left embankment.

1 Lump Sum $ $

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 3 OF 6

Item Supplies or Services Description Estimated

Quantity Unit Unit Price Amount

9 Excavation

Excavating, hauling and stockpiling materials within the required excavation limits to the lines and grades shown. Onsite disposal of excess material below the normal water surface of the reservoir to result in the required “zero loss/gain of water storage” within the reservoir is considered incidental to the cost of the Work. Includes the embankments, spillway, approach and discharge channels, and appurtenant structures.

374,360 Cubic Yard $ $

Excavation Removal to Designated On-site Disposal Areas Outside of the Reservoir Normal High Water Line

Removing, hauling and spreading of excess excavated materials and materials not suitable for construction to designated areas outside of the reservoir boundary. Stripping and site restoration of on-site disposal areas paid under separate line items.

91,430 Cubic Yard $ $

11 Site Restoration Furnishing and placing seed to revegetate areas for reclamation, including borrow areas and other disturbed areas. Seeding not required below normal high water line of the reservoir.

1 Lump Sum $ $

TERO and Business License

Includes TERO Business License fees. 1 Lump Sum $ $

13 All Unlisted Items Includes all expenses required in the Drawings and Specifications not paid for under one of the unit price or lump sum items of work.

1 Lump Sum $ $

SERVICE SPILLWAY

14 RCC Test Section

Furnishing, placing, and testing a roller compacted concrete (RCC) test section. Includes all RCC materials, including cement, supplementary cementitious material (SCM), aggregates, admixtures and required testing.

1 Lump Sum $ $

15 Service Spillway RCC Furnishing aggregate and water, mixing, batching, and placing RCC, forms and materials for the construction of spillway.

17,650 Cubic Yard $ $

16 Cement for RCC Furnishing, hauling, and storing cement material.

31,000

CWT $ $

SCM for RCC and CVC Facing

Furnishing, hauling, and storing SCM material.

31,000

CWT $ $

18 Admixtures for RCC Furnishing, hauling, and storing admixtures. Includes AEA, WRA, HRWR, and LRWR. 1,450

Gallon $ $

Service Spillway Conventional Concrete

Furnishing and placing reinforced Class C concrete, Class D concrete, and Class B concrete, as well as forms and materials for the construction of spillway. Includes all concrete materials and admixtures.

6,430 Cubic Yard $ $

Post-Construction Core Testing

Performing one post-construction core test of the installed RCC.

Includes coring, testing the samples, and grout backfill of core hole.

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 4 OF 6

Item Supplies or Services Description Estimated

Quantity Unit Unit Price Amount

21 Downstream Guardrail Furnishing and installing new guardrail and posts along the downstream crest of the spillway. Includes furnishing an additional 50 feet of replacement guardrail for future use.

2,000 Linear Foot $ $

OUTLET WORKS

22 Outlet Works

Furnishing a complete outlet works system as indicated on the Drawings, including placing reinforced concrete, Class B Concrete and CLSM for outlet works structures (inlet tower, and ductbank for vent pipe and HDPE conduits), precast concrete structures (control building and diversion intake structure), trashracks, stainless steel sluice gate and hydraulic actuation system, conduits for hydraulic lines, and piping (48-inch-diameter steel outlet works conduit, 8-inch-diameter steel vent pipe, and 36-inch-diameter HDPE permanent diversion pipe and blind flange).

Includes all leveling concrete, formwork, thimbles, and embedded parts.

1 Lump Sum $ $

EMBANKMENTS

23 Embankment Fill Furnishing, hauling, stockpiling, placing, spreading, and compacting Embankment Fill materials.

151,310 Cubic Yard $ $

24 Common Fill Furnishing, hauling, stockpiling, placing, spreading, and compacting Common Fill materials.

47,500 Cubic Yard $ $

25 Riprap Furnishing, hauling, stockpiling, and placing riprap. 8,140 Cubic Yard $ $

26 Riprap Bedding Furnishing, hauling, stockpiling, and placing riprap bedding. 3,980 Cubic Yard $ $

27 Filter Sand Furnishing, hauling, stockpiling, and placing filter sand. 12,600 Cubic Yard $ $

28 Toe Drain Pipe

Furnishing, stockpiling, and placing slotted and non-slotted toe drain pipe with clean outs. Included in this item is furnishing and installing precast concrete toe drain manholes as indicated on the Drawings.

800 Linear Foot $ $

29 Drain Gravel Furnishing, hauling, stockpiling, and placing drain gravel. 1,370 Cubic Yard $ $

30 Aggregate Base Course Hauling, stockpiling, placing, spreading, and compacting road surface materials on the embankment crest and stilling basin access roads. Includes installation of separation geotextile.

920 Cubic Yard $ $

31 Bank Stone Protection Furnishing, stockpiling, and placing bank stone protection and filter fabric.

60 Cubic Yard $ $

Shear Wall Mix Design Study

Develop Deep Mix Method (DMM) mix design for shear walls.

Include site assessment and recovery of soils.

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 5 OF 6

Item Supplies or Services Description Estimated

Quantity Unit Unit Price Amount

Deep Mix Method (DMM) Shear Walls

Furnishing and stockpiling material, mixing, testing, and placing DMM for shear walls. Include removal of all spoils from site including necessary treatment for disposal.

71,033 Square Foot $ $

Soil-Bentonite-Cement Cut-Off Wall

Furnishing and stockpiling material, mixing, testing, and placing Soil-bentonite-cement cut-off walls. Include removal of all spoils from site including necessary treatment for disposal.

125,510 Square Foot $ $

EMERGENCY SPILLWAY

Emergency Spillway Training Berms

Furnishing, stockpiling, placing, spreading, and compacting fill materials.

29,300 Cubic Yard $ $

Emergency Spillway Cut-Off

Furnishing and installing two Class F concrete cutoff walls to the dimensions indicated on the drawings.

2,710 Cubic Yard $ $

Emergency Spillway Clay Blanket Slope Protection

Furnishing, stockpiling, placing, spreading, and compacting clay fill between emergency spillway cut-off walls to dimensions indicated on the drawings.

13,520 Cubic Yard $ $

Home Removal & Replacement

Relocating and replacing two existing homes located within the Emergency Spillway channel. New home locations will be determined by BIA. Basis of bid shall be new home site locations are within 20 miles of dam site and utility hook-ups will be required.

1 Lump Sum $ $

UTILITIES & INSTRUMENTATION

39 Instrumentation

Furnishing and installing survey monuments, structural monitoring points, staff gages, toe drain weir boxes, and piezometers.

Includes furnishing and installing PVC pipe for EWS equipment.

EWS equipment will be installed by others. Includes bollards as indicated on the Drawings.

1 Lump Sum $ $

40 Utility Relocation Locating, removing, and relocating all utilities as shown on the Drawings which includes disposal, furnishing and installation.

Excludes site electrical.

1 Lump Sum $ $

41 Site Electrical Furnishing and installing all electrical components. 1 Lump Sum $ $

TOTAL FOR BID SCHEDULE $ ______________________________________

BID FORM

OGLALA DAM SPILLWAY AND OUTLET WORKS

JULY 2023

FOR BID REV 5 PAGE 6 OF 6

PRODUCTS

NOT USED

EXECUTION

NOT USED

END OF SECTION

File details come from the government source that posted it. Updated .