01 58 00 Project ID.pdf
PDF 63 KB Posted
- Attached to
- Maintenance Dredging, Hudson River, NY Federal Navigation Project, Port of Albany Turning Basin Dredge Area
- Solicitation number
- W912DS21B0007
About this file
This section specification outlines requirements for a project identification sign and safety sign for the Port of Albany Turning Basin dredging project. The successful contractor must erect one project identification sign and one safety sign measuring 6 feet by 4 feet within 15 calendar days of receiving the notice to proceed. The signs must display the daily corrected data and the Corps of Engineers castle logo. The contractor must maintain the signs in good condition throughout the project duration and then remove them upon completion.
The related federal contract opportunity is a solicitation by the US Army Corps of Engineers New York District to perform maintenance dredging of the Hudson River in the Port of Albany Turning Basin dredge area. Offerors will dredge the specified area to the required dimensions.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021
Section 01 58 00
PROJECT IDENTIFICATION
01/07
PART 1 GENERAL
1.1 SUBMITTALS
Not Used.
1.2 QUALITY ASSURANCE
Not Used.
1.3 PROJECT SIGN AND SAFETY SIGN
Prior to initiating any work on site, provide one project identification sign and one safety sign at the location designated. Construct the sign in accordance with project sign detail shown in Attachment C, Section 00 90 01.
The sign shall be 6 feet by 4 feet. The Corps of Engineers castle logo (an
8.5" x 11" red decal) to be used on the sign will be Government furnished.
The Contractor will be given this logo at the time of the preconstruction conference. The decal shall receive a thin coat of clear spar varnish after application. The sign shall be erected as soon as possible and within 15 calendar days after the date of the receipt of the Notice to
Proceed. The data required by the sign shall be corrected daily. No separate payment will be made for erecting and maintaining the safety sign and all costs in connection therewith will be considered the obligation of the contractor. Upon completion of the project, the Contractor shall remove the sign from the work site. Maintain sign throughout the life of the project.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --