01 50 00 Temp Construction Facilites Controls.pdf
PDF 105 KB Posted
- Attached to
- Maintenance Dredging, Hudson River, NY Federal Navigation Project, Port of Albany Turning Basin Dredge Area
- Solicitation number
- W912DS21B0007
About this file
This document contains specifications for temporary construction facilities and controls for a maintenance dredging project of the Port of Albany Turning Basin in the Hudson River in New York. The specifications require the contractor to submit a construction site plan prior to start of work detailing temporary facilities such as site trailers, sanitation facilities, and worker parking. The contractor must also equip all dredges with bridge-to-bridge radio for communication with vessels and display signal lights in accordance with Coast Guard regulations. Personal protective equipment such as hard hats are required for all personnel on site. The specifications further require accommodations for government inspectors onboard dredging vessels or craft. This project is solicited under solicitation number W912DS21B0007 by the Department of the Army Corps of Engineers New York District for maintenance dredging of the Port of Albany Turning Basin dredge area in the Hudson River.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021
SECTION 01 50 00 Page 1
PART 1 GENERAL
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
03/21
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan; ; G
1.2 NAVIGATION AIDS
Notify the Federal Aids to Navigation Officer 30 days prior to the commencement of work.
The Contractor shall not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aids to navigation moved in order to complete dredging operations under this contract, the Contractor shall notify the appropriate Coast Guard
Office, with a copy to the Contracting Officer and/or his Representative, not less than 30 days prior to the need for movement. The Contractor shall notify the appropriate Coast Guard Office of the approximate time of completion of dredging.
The Coast Guard has indicated that the requirements of navigation may make it necessary to establish times other than those requested. IT SHALL BE
THE CONTRACTOR'S RESPONSIBILITY TO COORDINATE HIS PLANS WITH THE COAST
GUARD SUFFICIENTLY IN ADVANCE OF THE PLANNED CLOSING TO PREVENT DELAY TO
THE DREDGING OPERATIONS AND COMPLY WITH THE COAST GUARD REQUIREMENT.
1.3 LAYOUT OF WORK
a. The Government will establish the following base lines and bench marks at the site of the work: (Monuments and bench marks as shown on the drawings.)
b. From the base lines and bench marks established by the Government, complete the layout of the work and provide measurements for the execution of the work to the location and limit marks indicated, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.
c. Provide stakes, templates, platforms, equipment, tools and material, and labor as required for laying out the work from the base lines and bench marks established by the Government. Maintain and preserve all stakes and other marks established by the Contracting Officer until
SECTION 01 50 00 Page 2 authorized to remove them, and if such marks are destroyed by the
Contractor or through his negligence prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
1.4 SUBMERGED PIPELINES
Should it become necessary in the performance of this contract to use a submerged pipelines across a navigable channel, the Contractor must notify the Contracting Officer, in writing to be received in the District Office at least ten working days prior to the desired closure date. This notification shall include the following:
(1) Location (Channel Centerline Stationing) and depth (over the top of the pipeline) at which the submerged line will be placed;
(2) The desired length of time the channel is to be closed for installation of the pipeline;
(3) The date and hour placement or removal will commence;
(4) The date and hour of anticipated completion; and
(5) The name and telephone number of the person to be contacted for information and response to any emergency condition.
The requirements of navigation may make it necessary to establish times other than those requested. It is the contractor's responsibility to coordinate his/her plans with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements.
1.5 FLOATING PIPELINE
Design rubber float lines to minimize the number of connections in the discharge line and reduce the need to disconnect the float line from the submerged line in moderate storm conditions. Provide an information-only design submittal prior to starting this Definable Feature of Work.
Floating pipeline, used as access ways, shall be equipped with walkways and guard rails. The walkway must be securely anchored to the pipeline and a guard rail equivalent in strength to a wood rail 2 inch by 4 inch must be provided on at least one side of the walkway and must be secured to upright at intervals of not more than 8 feet and of not less than 36 nor more than 42 inches in height above the walkway. Float pipelines not equipped with walkways must be barricaded to prevent personnel access.
1.6 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction
SECTION 01 50 00 Page 3 fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.7 BRIDGE-TO-BRIDGE RADIO-TELEPHONE EQUIPMENT
In order that radio-telephone communication may be made with passing vessels, all dredges engaged in work under the contract shall be equipped with and operate bridge-to-bridge radio-telephone equipment on VHF Channel
13 (156.65 MHz with low power output having a communication range of approximately ten (10) miles). The Federal Communication Commission has approved the frequency.
1.8 HEAD PROTECTION AREA
THE ENTIRE WORK SITE UNDER THIS CONTRACT IS DESIGNATED AS A HARD HAT AREA.
The Contractor shall post the area in accordance with the requirements of paragraph 05.D.01, EM 385-1-1, and shall ensure that all prime and subcontractor personnel, vendors, and visitors utilize hard hats while within the project area. (EM 385-1-1 30 Nov. 2014)
1.9 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no light signals can be displayed. Vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipelines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels or floating plant working in navigable channels, as approved by the Commandant, U.S. Coast
Guard with respect to vessels on the high seas (33 CAR 81 App. A-72
COLREGS, Part C), vessels in inland waters (33-CFR 93.18 - 93.31a), and vessels in western rivers (33 CFR 95.5.51 - 95.70)), as applicable.
(DAEN-PRP Ind dtd. 12 Sep. 83)
1.10 REVERSE SIGNAL ALARM
a. All construction equipment, except light service trucks, panels, pickup trucks, station wagons, crawler-type cranes, power shovels and draglines, whether moving alone or in combination shall be equipped with reverse signal alarms. The alarm shall be mounted on the rear of the equipment and shall be protected or constructed as to withstand severe wear and tear, adverse weather and unfavorable environmental working conditions and shall be certified by the manufacturer to fully meet the following performance standards.
b. The alarm shall produce a relatively pure tone which shall peak within the American National Std's. Inst. standard octave pass band of
600 to 2400 cycles per second and shall produce a 0.2 to 0.5 second audible warning within the initial three (3) feet of backward movement of the vehicle on which it is mounted and at regular intervals, not to exceed three (3) seconds throughout the backward movement. The alarm shall automatically stop when backward movement ceases. The sound intensity of the alarm shall range from and not exceed 90-100 db
(decibels) at a horizontal distance of five feet from the alarm.
c. Actuation of the alarm shall be automatic by direct connections to
SECTION 01 50 00 Page 4 any part of the equipment that moves or acts in a manner distinctive only to the rearward movement of the vehicle with no manual controls of any kind between the source of actuation and the alarm. Where application of this requirement to specific types of the equipment has impractical application, other means of actuation may be used upon written approval of the Contracting Officer and/or his Representative.
d. The use of the alarm shall be in the addition to prescribed requirements for signalmen.
1.11 INSPECTION
The inspectors will assess whether the gauges, ranges, location marks and limit marks are maintained in proper order; but the presence of the inspector shall not relieve the Contractor of the responsibility for the proper execution of the work in accordance with the specifications. The
Contractor will be required:
a. To furnish, on the request of the Contracting Officer and/or his
Representative or any inspector, the use of such boats, boatmen, laborers, a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the work. However, the Contractor will not be required to furnish such facilities for the surveys prescribed in the clause entitled: "Final Examination and Acceptance."
b. To furnish, on the request of the Contracting Officer or the
Contracting Officer's Representative or any inspector, suitable transportation from all points on shore designated by the Contracting
Officer and/or his Representative to and from the various pieces of plant and to and from the placement area. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting
Officer or Contracting Officer Representative, and the cost thereof will be deducted from any amounts due or to become due to the
Contractor.
PART 2 PRODUCTS
2.1 ACCOMMODATIONS FOR GOVERNMENT INSPECTORS
The Contractor shall furnish regularly to Government inspectors onboard the dredge or other craft upon which they are employed a suitable separate room for an office. The room shall be fully equipped and maintained to the satisfaction of the Contracting Officer and/or his Representative; it shall be properly heated, ventilated, and lighted, and shall have a desk which can be locked, and a chair for each inspector, beverage (e.g. water, coffee and tea) and bathroom conveniences. In addition, the Contractor shall provide a suitable sleeping area for use by the Government inspector when weather or sea conditions preclude safe transfer to shore. The entire cost to the Contractor for furnishing, equipping and maintaining the foregoing accommodations shall be included in the contract price. If the Contractor fails to meet these requirements, the Contracting Officer and/or his
Representative will secure the facilities referred to above, and the cost thereof will be deducted from payments to the Contractor.
SECTION 01 50 00 Page 5
2.2 TEMPORARY SIGNAGE
2.2.1 Safety Sign
The Contractor shall construct a safety sign at a location directed by the
Contracting Officer and/or his Representative. The sign shall be 6 feet by
4 feet and shall conform to the requirements as specified in Section 00 90
01, Attachment B, Project Identification and Safety Signs. The Corps of
Engineers castle logo (an 8.5" x 11" red decal) is to be used on the sign.
The decal shall receive a thin coat of clear spar varnish after application. The sign shall be erected as soon as possible and within 5 calendar days after the date of the receipt of the Notice to Proceed. The data required by the sign shall be corrected daily. No separate payment will be made for erecting and maintaining the safety sign and all costs in connection therewith will be considered the obligation of the contractor.
Upon completion of the project, the Contractor shall remove the sign from the work site.
2.2.2 Project Sign
The Contractor shall furnish and erect a project sign at a location directed by the Contracting Officer or Contracting Officer's
Representative. The project sign shall conform with all requirements as specified in Section 00 90 01, Attachment B, Project Identification and Safety Signs. The Corps of Engineers' castle logo and other logos (8.5" x
11") to be used on the sign will be Government furnished. The Contractor will be given these logos at the time of the preconstruction conference.
The decal(s) shall receive a thin coat of clear spar varnish after application. The Contractor shall maintain the sign in good condition throughout the construction period. No separate payment will be made for erecting and maintaining the project sign, and all costs in connection therewith will be considered the obligation of the Contractor. Upon completion of the project, the Contractor shall remove the sign from the work site.
2.2.3 Bulletin Board
Within one calendar day of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the
Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health
Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.
2.2.4 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the
EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site.
Correct the data required by safety signs daily.
SECTION 01 50 00 Page 6
PART 3 EXECUTION
3.1 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
File details come from the government source that posted it. Updated .