This document contains a quality control plan section for a federal construction contract to perform maintenance dredging of the Port of Albany Turning Basin in the Hudson River in New York. The quality control plan outlines requirements for contractor personnel qualifications and certifications, three phases of quality control procedures during preparatory, initial and follow up phases of work, submittal review and approval processes, testing and inspection requirements, documentation and reporting standards, and completion inspection procedures. It specifies that the contractor must appoint a qualified QC manager and alternate to implement a thorough quality control program encompassing oversight of subcontractors, regular quality control meetings, and certification of work compliance.

View the file

Other files

File Type Posted
Bid Abstract_05-27-2021.pdf PDF
Amendment 0005_Houghtaling Island Topo.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment_0002_Site Visit Sign In Sheet.pdf PDF
Amendment_0002.pdf PDF
Amendment 0001_Pre-bid site vist_directions and instructions.pdf PDF
Amendment 0001.pdf PDF
00 01 15 list of drawings.pdf PDF
00 90 01 AA list of documents.pdf PDF
00 90 01 E- Report of Operations Pipeline Dipper or Bucket Dredges.pdf PDF
AFO - 6 - Index_Notes.pdf PDF
00 90 01 C 33CFR Oil Hazardous Form.pdf PDF
00 90 01 J-Location of Ice Houses.pdf PDF
00 90 01 F-Transportation and Placement Log Mechanical Dredges.pdf PDF
01 50 00 Temp Construction Facilites Controls.pdf PDF
01 58 00 Project ID.pdf PDF
01 57 20.00 10 Environmental protection.pdf PDF
00 90 02 AA WQC PARKS .pdf PDF
01 30 00 Admin Requirments.pdf PDF
W912DS21B0007.pdf PDF
00 90 01 K-Control Points.pdf PDF
01 78 00 clouseout Submittal.pdf PDF
00 90 01 I-Sediment_Physical and Chemistry Data Reports.pdf PDF
35 20 23 dredging.pdf PDF
AFO - 3 - Houghtaling Island Topo and Site.pdf PDF
01 33 00 Submittal Procedures.pdf PDF
01 32 01.00 10 Project Schedule.pdf PDF
00 90 01 L-SUBMITTAL REGISTER_EXAMPLE ONLY.pdf PDF
00 90 01 H-Standard specifications for silt fence.pdf PDF
01 20 00 Tech Spec3.pdf PDF
01 42 00 Sources of Reference.pdf PDF
AFO - 5 - ATB HYDRO.pdf PDF
01 22 00.00 10 measurement and payment.pdf PDF
AFO - 4 - Houghtaling Offshore Hydro.pdf PDF
00 90 02 PARKS Permit Attachement.pdf PDF
00 90 01 A-CQC Report Example.pdf PDF
00 90 01 D-Guidelines for Preparing Accident Prevention Plan.pdf PDF
01 35 26 Gov Safety Requirment.pdf PDF
35 20 29 dredge material transport.pdf PDF
AFO - 2 -location.pdf PDF
01 20 00.00 20 price and payment procedures.pdf PDF
AFO - 1 - Index.pdf PDF
00 90 01 G-Daily Site Safety and Health Inspection Log.pdf PDF
00 90 01 B-Project Sign and Safety Sign.pdf PDF
00 90 02 WQC Attachement.pdf PDF
01 11 00 summary of work2.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021

SECTION 01 45 00.00 20 Page 1

PART 1 GENERAL

1.1 REFERENCES

SECTION 01 45 00.00 20

QUALITY CONTROL

11/11

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements

Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals; G

Construction Quality Control (QC); Plan G

Submit a Construction QC Plan 7 days prior to preconstruction meeting.

Letter Appointing Superintendent; G

1.3 INFORMATION FOR THE CONTRACTING OFFICER

Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer.

The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality

Control (CQC) Report, (CQC) Report (Continuation Sheet), Preparatory Phase

Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and

Log.

Deliver the following to the Contracting Officer during Construction:

a. CQC Report: Submit the Report electronically by 10:00 AM the next day after each day that work is performed and after each day of no-work along with explanation for the work stoppage. CQC Report submittal shall commence on the day following the Notice To Proceed (NTP) and continue until completion of demobilization.

b. Contractor Production Report: Submit the Report electronically by

10:00 AM the next day after each day that work is performed and after each day of no-work with explanation for the work stoppage. The

Production Report submittal shall commence the day following the start of dredging and continue until completion of dredging.

SECTION 01 45 00.00 20 Page 2

c. Preparatory Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Preparatory Phase held.

d. Initial Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Initial Phase held.

e. Field Test Reports: Within two working days after the test is performed, submit the report as an electronic attachment to the CQC

Report.

f. CQC Meeting Minutes: Within two working days after the meeting is held, submit the report as an electronic attachment to the CQC Report.

g. QC Certifications: As required by the paragraph entitled "QC

Certifications."

1.4 QC PROGRAM REQUIREMENTS

Establish and maintain a QC program as described in this section. This QC program is a key element in meeting the objectives of NAVFAC Commissioning.

The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, and QC certifications and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program must cover on-site and off-site work and be keyed to the work sequence. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager.

The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.

1.4.1 Acceptance of the Construction Quality Control (QC) Plan

Acceptance of the QC Plan is required prior to the start of construction.

The Contracting Officer reserves the right to require changes in the QC

Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications. All QC organization personnel are subject to acceptance by the Contracting Officer. The Contracting Officer may require the removal of any individual for non-compliance with quality requirements specified in the Contract.

1.4.2 Preliminary Construction Work Authorized Prior to Acceptance

The only construction work that is authorized to proceed prior to the acceptance of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying.

1.4.3 Notification of Changes

Notify the Contracting Officer, in writing, of any proposed changes in the

QC Plan or changes to the QC organization personnel, a minimum of 10 work days prior to a proposed change. Proposed changes are subject to

SECTION 01 45 00.00 20 Page 3 acceptance by the Contracting Officer.

1.5 PERFORMANCE EVALUATION OF CONTRACTOR

a. As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work. However, interim evaluation may be prepared at any time during contract performance when determined to be in the best interest of the Government.

b. The Contractor will be rated either Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory in the areas of Contractor

Quality Control, Timely Performance, Effectiveness of Management, Compliance with Labor Standards, and Compliance with Safety Standards.

The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be maintained as part of the official record. Performance Evaluation Reports will be available to all DOD contracting offices for their future use in determining

Contractor responsibility, in compliance with FAR 36.201 (c).

c. The Federal Acquisition Regulation (FAR) requires that Past

Performance Information (PPI) be collected on DoD contracts. The

Contractor Performance Assessment Reporting System (CPARS) is a web-enabled application the supports the completion, distribution and retrieval of all contract performance evaluations. Contractor

Representative is responsible for reviewing and commenting on evaluations submitted on the Contractor Performance Assessment

Reporting System (CPARS) website at https://www.cpars.gov/index.htm.

1.6 QC ORGANIZATION

1.6.1 QC Manager

1.6.1.1 Duties

Provide a QC Manager at the work site to implement and manage the QC program. The only duties and responsibilities of the QC Manager are to manage and implement the QC program on this Contract. The QC Manager shall not hold any other positions or perform any other duties on this contract.

The QC Manager is required to attend the partnering meetings, QC Plan

Meetings, Pre-Construction Conference, Coordination and Mutual

Understanding Meeting, conduct the QC meetings, perform the three phases of control except for those phases of control designated to be performed by QC

Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this

Contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by the QC Specialists, testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities.

1.6.1.2 Qualifications

A graduate of a four year accredited college or university program in one of the following disciplines: Engineering, Architecture, Construction

Management, Engineering Technology, Building Construction, or Building

Science, with a minimum of 10 years experience as a Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major http://www.cpars.gov/index.htm

SECTION 01 45 00.00 20 Page 4 trades that are part of this Contract. The individual must have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability.

1.6.1.3 Construction Quality Management Training

In addition to the above experience and education requirements, the QC

Manager must have completed the course entitled "Construction Quality

Management (CQM) for Contractors." If the QC Manager does not have a current certification, they must obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of

Engineers. Contact the Contracting Officer for information on the next scheduled class.

1.6.2 Alternate QC Manager Duties and Qualifications

Designate an alternate for the QC Manager at the work site to serve in the event of the designated QC Manager's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year. The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.

1.7 QUALITY CONTROL (QC) PLAN

1.7.1 Construction Quality Control (QC) Plan

1.7.1.1 Requirements

Provide, for acceptance by the Contracting Officer, a Construction QC Plan submitted in a three-ring binder that includes a table of contents, with major sections identified with tabs, with pages numbered sequentially, and that documents the proposed methods and responsibilities for all QC personnel activities including testing, during the construction of the project, which include:

a. QC ORGANIZATION: A chart showing the QC organizational structure.

b. NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, for each person in the QC organization. Include the CQM for

Contractors course certifications for the QC Manager and Alternate QC

Manager and QC personnel as required by the paragraphs entitled

"Construction Quality Management Training" and "Alternate QC Manager

Duties and Qualifications". In addition, if construction must be performed at multiple locations, additional QC personnel meeting all requirement will be tasked to do these additional locations. No work is to be performed at any location without the a QC present. If the

Contractor elects to work multiple shifts per day, A QCM must be present for each shift. No individual can work more than than 12 hour shift per day.

c. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.

d. OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide. NOTE: These entities fall under the realm of Sub-Contractors

SECTION 01 45 00.00 20 Page 5 to this Construction Contract and are subject to the Prime Contractor's policies and procedures listed in the QC Plan to include Safety

Compliance.

e. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager and stating that they are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility of the QC Manager and Alternate QC Manager to implement and manage the three phases of control, and their authority to stop work which is not in compliance with the Contract and/or Safety compliance. Letters of direction are to be issued by the QC Manager to all other QC Alternate

Managers, Specialists and QC personnel outlining their duties, authorities, and responsibilities. Include copies of the letters in the QC Plan.

f. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the

Submittal Register as specified in Section 01 33 00 SUBMITTAL

PROCEDURES.

g. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs entitled "Accreditation Requirements", as applicable.

h. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test. Use

Government forms to log and track tests.

i. PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track, and complete rework items. Use Government forms to record and track rework items.

j. DOCUMENTATION PROCEDURES: Use Government form.

k. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines and is an item or activity on the construction schedule. Include in the list of DFOWs, but not be limited to, all critical path activities on the Network Analysis

Schedule (NAS). Include all activities for which this specification requires QC Specialists or specialty inspection personnel. Provide separate DFOWs in the Network Analysis Schedule for each design development stage and submittal package.

l. PROCEDURES FOR PERFORMING THE THREE PHASES OF CONTROL: Identify procedures used to ensure the three phases of control to manage the quality on this project. For each DFOW, a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. Conduct the Preparatory and Initial Phases and meetings with a view towards obtaining quality construction by planning ahead and identifying potential problems for each DFOW. Provide GDA ample notification of meeting for attendance.

m. PERSONNEL MATRIX: A personnel matrix showing for each section of the

SECTION 01 45 00.00 20 Page 6 specification who will review and approve submittals, who will perform and document the three phases of control, and who will perform and document the testing.

n. PROCEDURES FOR COMPLETION INSPECTION: Procedures for identifying and documenting the completion inspection process. Include in these procedures the responsible party for punch out inspection, pre-final inspection, and final acceptance inspection.

o. TRAINING PROCEDURES AND TRAINING LOG: Procedures for coordinating and documenting the training of personnel required by the Contract. Include a sample record of training for reporting what systems were included in training, who provided training, when and where training was preformed and who attended training.

p. ORGANIZATION AND PERSONNEL CERTIFICATIONS LOG: Procedures for coordinating tracking and documenting all certifications on subcontractors, testing laboratories, suppliers, personnel, vessels etc. QC Manager will ensure that certifications are current, appropriate for the work being performed, and will not lapse during any period of the contract that the work is being performed.

1.8 QC PLAN MEETINGS

Prior to submission of the QC Plan, the QC Manager will meet with the

Contracting Officer to discuss the QC Plan requirements of this Contract.

The purpose of this meeting is to develop a mutual understanding of the QC

Plan requirements prior to plan development and submission and to agree on the Contractor's list of DFOWs.

1.9 COORDINATION AND MUTUAL UNDERSTANDING MEETING

After submission of the QC Plan, and prior to the start of construction, the QC Manager will meet with the Contracting Officer to present the QC program required by this Contract. When a new QC Manager is appointed, the coordination and mutual understanding meeting shall be repeated.

1.9.1 Purpose

The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, design intent, Cx, environmental requirements and procedures, coordination of activities to be performed, and the coordination of the

Contractor's management, production, and QC personnel. At the meeting, the

Contractor will be required to explain in detail how three phases of control will be implemented for each DFOW, as well as how each DFOW will be affected by each management plan or requirement as listed below:

a. Waste Management Plan.

c. Procedures for noise and acoustics management.

d. Environmental Protection Plan.

e. Environmental regulatory requirements.

SECTION 01 45 00.00 20 Page 7

1.9.2 Attendees

As a minimum, the Contractor's personnel required to attend include an officer of the firm, the Project Manager, Project Superintendent, QC

Manager, Alternate QC Manager, Environmental Manager, and sub-Contractor's representatives. Each subcontractor who will be assigned QC responsibilities shall have a principal of the firm at the meeting.

Minutes of the meeting will be prepared by the QC Manager and signed by the

Contractor and the Contracting Officer. Provide a copy of the signed minutes to all attendees and shall be included in the QC Plan.

1.10 QC MEETINGS

After the start of construction, conduct weekly QC meetings by the QC

Manager at the work site with the Project Superintendent, QC Personnel, and alternate QCM, and the foremen who are performing the work of the DFOWs.

The QC Manager is to prepare the minutes of the meeting and provide a copy to the Contracting Officer within two working days after the meeting. The

Contracting Officer may attend these meetings. As a minimum, accomplish the following at each meeting:

a. Review the minutes of the previous meeting.

b. Review the schedule and the status of work and rework.

c. Review the status of submittals.

d. Review the work to be accomplished in the next two weeks and documentation required.

e. Resolve QC and production problems (RFI, etc.).

f. Address items that may require revising the QC Plan.

g. Review Accident Prevention Plan (APP).

h. Review environmental requirements and procedures.

i. Review Waste Management Plan.

j. Review IAQ Management Plan.

k. Review Environmental Management Plan.

l. Review the status of training completion.

1.11 DESIGN REVIEW AND DOCUMENTATION

1.11.1 Basis of Design and Design Intent

Review the basis of design received from the Contracting Officer and the design intent.

1.11.2 Design Review

Review design documents to verify that each commissioned system meets the design intent relative to functionality, energy performance, water performance, maintainability, sustainability, system cost, and local

SECTION 01 45 00.00 20 Page 8 environmental impacts. Fully document review in written report.

1.12 THREE PHASES OF CONTROL

Adequately cover both on-site and off-site work with the Three Phases of

Control and include the following for each DFOW.

1.12.1 Preparatory Phase

Notify the Contracting Officer at least two work days in advance of each preparatory phase meeting. The meeting will be conducted by the QC Manager and attended by the Project Superintendent and the foreman responsible for the DFOW. When the DFOW will be accomplished by a subcontractor, that subcontractor's foreman shall attend the preparatory phase meeting.

Document the results of the preparatory phase actions in the daily

Contractor Quality Control Report and in the Preparatory Phase Checklist.

Perform the following prior to beginning work on each DFOW:

a. Review each paragraph of the applicable specification sections.

b. Review the Contract drawings.

c. Verify that field measurements are as indicated on construction and/or shop drawings before confirming product orders, in order to minimize waste due to excessive materials.

d. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required.

e. Review the testing plan and ensure that provisions have been made to provide the required QC testing.

f. Examine the work area to ensure that the required preliminary work has been completed.

g. Coordinate the schedule of product delivery to designated areas.

h. Arrange for the return of shipping/packaging materials, such as wood pallets, where economically feasible.

i. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data.

j. Discuss specific controls used and construction methods, construction tolerances, workmanship standards, and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.

k. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Material

Safety Data Sheets (MSDS) are submitted.

1.12.2 Initial Phase

Notify the Contracting Officer at least two work days in advance of each initial phase. When construction crews are ready to start work on a DFOW, conduct the initial phase with the Project Superintendent, and the foreman

SECTION 01 45 00.00 20 Page 9 responsible for that DFOW. Observe the initial segment of the DFOW to ensure that the work complies with Contract requirements. Document the results of the initial phase in the daily CQC Report and in the Initial

Phase Checklist. Repeat the initial phase for each new crew to work on-site, or when acceptable levels of specified quality are not being met.

Perform the following for each DFOW:

a. Establish the quality of workmanship required.

b. Resolve conflicts.

c. Ensure that testing is performed by the approved laboratory.

d. Check work procedures for compliance with the APP and the appropriate

AHA to ensure that applicable safety requirements are met.

e. Review the QC Plan and ensure all preparatory work items have been completed and documented.

1.12.3 Follow-Up Phase

Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily CQC

Report:

a. Ensure the work is in compliance with Contract requirements.

b. Maintain the quality of workmanship required.

c. Ensure that testing is performed by the approved laboratory.

d. Ensure that rework items are being corrected.

e. Assure manufacturers representatives have performed necessary inspections if required and perform safety inspections.

f. Review the QC Plan and ensure all work items, testing, and documentation has been completed.

1.12.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same DFOW if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a DFOW is resumed after substantial period of inactivity, or if other problems develop.

1.12.5 Notification of Three Phases of Control for Off-Site Work

Notify the Contracting Officer at least two weeks prior to the start of the preparatory and initial phases.

1.13 SUBMITTAL REVIEW AND APPROVAL

Procedures for submission, review and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES.

SECTION 01 45 00.00 20 Page 10

1.14 QC CERTIFICATIONS

1.14.1 CQC Report Certification

Contain the following statement within the CQC Report: "On behalf of the

Contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge, except as noted in this report."

1.14.2 Invoice Certification

Furnish a certificate to the Contracting Officer with each payment request, signed by the QC Manager or Alternate QC Manager where applicable attesting that the Plans are current, coordinated and attesting that the work for which payment is requested, including stored material, is in compliance with Contract requirements.

1.14.3 Completion Certification

Upon completion of work under this Contract, the QC Manager shall furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the Contract."

Provide a copy of this final QC Certification for completion to the OMSI preparer for inclusion into the OMSI documentation.

1.15 COMPLETION INSPECTIONS

1.15.1 Punch-Out Inspection

Near the completion of all work or any increment thereof, established by a completion time stated in the Contract Clause entitled "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager must conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved drawings, specifications and Contract. Include in the punch list any remaining items on the "Rework Items List", which were not corrected prior to the Punch-Out Inspection. Include within the punch list the estimated date by which the deficiencies will be corrected. Provide a copy of the punch list to the Contracting Officer. The QC Manager, or staff, must make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government "Pre-Final Inspection".

1.15.2 Pre-Final Inspection

The Government and QCM will perform this inspection to verify that the work area(s) is complete. A Government "Pre-Final Punch List" will be documented by the CQM as a result of this inspection. The QC Manager will ensure that all items on this list are corrected prior to notifying the

Government that a "Final" inspection with the Client can be scheduled. Any items noted on the "Pre-Final" inspection must be corrected in a timely manner and be accomplished before the contract completion date for the work,or any particular increment thereof, if the project is divided into increments by separate completion dates.

1.15.3 Final Acceptance Inspection

Notify the Contracting Officer at least 14 calendar days prior to the date

SECTION 01 45 00.00 20 Page 11 a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final acceptance inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, and others deemed necessary.

Attendees for the Government will include the Contracting Officer, other

FEAD/ROICC personnel, and personnel representing the Client. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the

Contract Clause entitled "Inspection of Construction."

1.16 DOCUMENTATION

Maintain current and complete records of on-site and off-site QC program operations and activities.

1.16.1 Construction Documentation

Reports are required for each day that work is performed and must be attached to the Contractor Quality Control Report prepared for the same day. Maintain current and complete records of on-site and off-site QC program operations and activities. The forms identified under the paragraph "INFORMATION FOR THE CONTRACTING OFFICER" will be used. Reports are required for each day work is performed. Account for each calendar day throughout the life of the Contract.Every space on the forms must be filled in. Use N/A if nothing can be reported in one of the spaces.The

Project Superintendent and the QC Manager must prepare and sign the

Contractor Production and CQC Reports, respectively. The reporting of work must be identified by terminology consistent with the construction schedule. In the "remarks" sections of the reports, enter pertinent information including directions received, problems encountered during construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site, quality control problem areas, deviations from the QC Plan, construction deficiencies encountered, meetings held. The

"Remarks" section shall also include detailed information specifying the cumulative total of: quantity dredged, quantity processed (the processing facility must be identified and the quantity must be broken out if more than one processing facility is utilized), and quantity placed at the dredged material's final placement location (the placement site must be identified and the quantity must be broken out if more than one placement site is utilized).

For each entry in the report(s), identify the Schedule Activity No. that is associated with the entered remark.

1.16.2 Quality Control Validation

Establish and maintain the following in a series of three ring binders.

Binders shall be divided and tabbed as shown below. These binders must be readily available to the Contracting Officer during all business hours.

a. All completed Preparatory and Initial Phase Checklists, arranged by specification section.

b. All milestone inspections, arranged by Activity Number.

SECTION 01 45 00.00 20 Page 12

c. An up-to-date copy of the Testing Plan and Log with supporting field test reports, arranged by specification section.

d. Copies of all contract modifications, arranged in numerical order.

Also include documentation that modified work was accomplished.

e. An up-to-date copy of the Rework Items List.

f. Maintain up-to-date copies of all punch lists issued by the QC staff to the Contractor and Sub-Contractors and all punch lists issued by the

Government.

g. Commissioning documentation including QC checklists, schedules, tests, and reports.

1.16.3 Testing Plan and Log

As tests are performed, the QC Manager will record on the "Testing Plan and

Log" the date the test was performed and the date the test results were forwarded to the Contracting Officer. Attach a copy of the updated

"Testing Plan and Log" to the last daily CQC Report of each month, per the paragraph "INFORMATION FOR THE CONTRACTING OFFICER". Provide a copy of the final "Testing Plan and Log" to the OMSI preparer for inclusion into the

OMSI documentation.

1.16.4 Rework Items List

The QC Manager must maintain a list of work that does not comply with the

Contract, identifying what items need to be reworked, the date the item was originally discovered, the date the item will be corrected by, and the date the item was corrected. There is no requirement to report a rework item that is corrected the same day it is discovered. Attach a copy of the

"Rework Items List" to the last daily CQC Report of each month. The

Contractor is responsible for including those items identified by the

Contracting Officer.

1.17 NOTIFICATION ON NON-COMPLIANCE

The Contracting Officer will notify the Contractor of any detected non-compliance with the Contract. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification.

If the Contractor fails or refuses to comply promptly, the Contracting

Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time for excess costs or damages by the Contractor.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 PREPARATION

Designate receiving/storage areas for incoming material to be delivered according to installation schedule and to be placed convenient to work area in order to minimize waste due to excessive materials handling and

SECTION 01 45 00.00 20 Page 13 misapplication. Store and handle materials in a manner as to prevent loss from weather and other damage. Keep materials, products, and accessories covered and off the ground, and store in a dry, secure area. Prevent contact with material that may cause corrosion, discoloration, or staining. Protect all materials and installations from damage by the activities of other trades.

-- End of Section --