About this file

This document provides specifications for maintenance dredging of the Port of Albany Turning Basin in the Hudson River in New York. The work includes dredging approximately 36,460 cubic yards of material to a depth of 32 feet below mean low water plus one foot of overdepth allowance, transporting, dewatering, and placing the dredged material at a government-furnished upland site on Houghtaling Island. The contractor must mobilize within five days of notice to proceed and complete all work, including dredging and interim site stabilization, by December 31, 2021, with all work finished within 365 calendar days. In-water dredging is restricted to the period between September 1 and November 30, 2021. The estimated cost for all work is between $1 million and $5 million. The solicitation was issued by the U.S. Army Corps of Engineers, New York District.

View the file

Other files

File Type Posted
Bid Abstract_05-27-2021.pdf PDF
Amendment 0005_Houghtaling Island Topo.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment_0002_Site Visit Sign In Sheet.pdf PDF
Amendment_0002.pdf PDF
Amendment 0001_Pre-bid site vist_directions and instructions.pdf PDF
Amendment 0001.pdf PDF
00 01 15 list of drawings.pdf PDF
00 90 01 AA list of documents.pdf PDF
00 90 01 E- Report of Operations Pipeline Dipper or Bucket Dredges.pdf PDF
AFO - 6 - Index_Notes.pdf PDF
00 90 01 C 33CFR Oil Hazardous Form.pdf PDF
00 90 01 J-Location of Ice Houses.pdf PDF
00 90 01 F-Transportation and Placement Log Mechanical Dredges.pdf PDF
01 50 00 Temp Construction Facilites Controls.pdf PDF
01 58 00 Project ID.pdf PDF
01 57 20.00 10 Environmental protection.pdf PDF
00 90 02 AA WQC PARKS .pdf PDF
01 30 00 Admin Requirments.pdf PDF
W912DS21B0007.pdf PDF
00 90 01 K-Control Points.pdf PDF
01 78 00 clouseout Submittal.pdf PDF
00 90 01 I-Sediment_Physical and Chemistry Data Reports.pdf PDF
35 20 23 dredging.pdf PDF
AFO - 3 - Houghtaling Island Topo and Site.pdf PDF
01 33 00 Submittal Procedures.pdf PDF
01 45 00.00 20 quality control.pdf PDF
01 32 01.00 10 Project Schedule.pdf PDF
00 90 01 L-SUBMITTAL REGISTER_EXAMPLE ONLY.pdf PDF
00 90 01 H-Standard specifications for silt fence.pdf PDF
01 20 00 Tech Spec3.pdf PDF
01 42 00 Sources of Reference.pdf PDF
AFO - 5 - ATB HYDRO.pdf PDF
01 22 00.00 10 measurement and payment.pdf PDF
AFO - 4 - Houghtaling Offshore Hydro.pdf PDF
00 90 02 PARKS Permit Attachement.pdf PDF
00 90 01 A-CQC Report Example.pdf PDF
00 90 01 D-Guidelines for Preparing Accident Prevention Plan.pdf PDF
01 35 26 Gov Safety Requirment.pdf PDF
35 20 29 dredge material transport.pdf PDF
AFO - 2 -location.pdf PDF
01 20 00.00 20 price and payment procedures.pdf PDF
AFO - 1 - Index.pdf PDF
00 90 01 G-Daily Site Safety and Health Inspection Log.pdf PDF
00 90 01 B-Project Sign and Safety Sign.pdf PDF
00 90 02 WQC Attachement.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

03/21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use, not later than 365 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3)

b. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer or Contracting Officer Representative

(COR) and subject, in every detail, to his supervision, direction, and instructions.

1.2 WORK COVERED BY THE CONTRACT DOCUMENTS

1.2.1 Project Description

The work to be performed under this project consists of providing all materials, plant, labor, equipment and services (except those furnished by the Government) to perform maintenance dredging of the Port of Albany

Turning Basin, Hudson River, New York, Federal Navigation Project, with placement of the material at the Government furnished upland dredged material placement site on Houghtaling Island. The Contractor will prosecute said work diligently, substantially complete the work to include dredging and interim stabilization of the disposal area, no later than

December 31, 2021; subject to the conditions in section 01 30 00 ADMINISTRATIVE REQUIREMENTS, paragraph 1.8.a “Weather.” The Contractor will complete the entire work within 365 calendar days after receipt of notice to proceed. The time stated for completion shall include the final clean-up.

In addition, Water Quality Certification restrictions prohibit performing any in-water dredging work earlier than September 1, 2021; or later than November 30, 2021 for the Albany Turning Basin dredging area. Extensions for in-water work past November 30, 2021 must be requested a minimum of 30 days prior to November 30,2021, and will be granted pending NYS DEC approval.

The Maintenance for this project consists of dredging approximately 36,460 CY of material based on a survey done between August and October 2020.

For more detail, see "ESTIMATED QUANTITIES" in Section 00 30 00

"ADMINISTRATIVE REQUIREMENTS" of these Specifications. The dredge material at the Albany Turning Basin has been determined to be approximately 17.5%

Sand, 59.5% Silt and 23.0% Clay. This work is subject to availability of

SECTION 01 11 00 Page 2 funds.

A summary of the Basic Work is shown on the table below:

BID SCHEDULE TOTAL

ESTIMATED

QUANTITY

CONTRACT TIME

FOR COMPLETION

(Calendar Days)

Mobilization and

Demobilization

1 JOB 365

Dredging Work: (32' COE MLW +

1' OD)

36,460 CY 365

Placement Site Work 1 JOB 365

Contract time for completion is based on a minimum average production rate of 405 cubic yards (CY) per day for dredging, transportation, processing and placement the Government furnished upland placement site. Should the total quantity of material exceed the estimated quantities within the

Solicitation Contract Form, additional time will be allowed at the rate of one (1) calendar day for each 405 cubic yards in excess of the established limit. However, this shall not relieve the Contractor from the requirement to complete all in-water dredging work within the period noted

2021. The time stated for completion above, and no later than November 30, shall include final clean up.

The contractor must bid on all items of the bid schedule. CLIN 0002

(Dredging Albany Turning Basin, Hudson River, NY, Federal Navigation

Channel) requires dredging to the plane of -32 feet COE MLW plus 1 foot allowable overdepth, with subsequent transportation, processing and placement of the dredged material the Government furnished upland dredged material placement site on Houghtaling Island, NY.

Sampling and testing was conducted by the Government in 2019, and the grain size test results are included in the specifications in Section 00 90 01 as

Attachment J. The complete sampling and testing results can be found as attachments to this solicitation on beta.SAM.Gov.

The current New York State Department of Environmental Conservation

(NYSDEC) Water Quality Certificate (WQC) for Hudson River, NY maintenance dredging is included in Section 00 90 02. The contractor must comply with all conditions of the NYSDEC WQC.

The work is anticipated to be performed within the approximate time period of August 2021 through July 2022.

1.3 PERFORMANCE OF WORK BY THE CONTRACTOR

The Contractor shall perform on the site, and with its own organization and equipment, work equivalent to at least forty (40) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performance of the work, the Contractor requests a reduction and the Contracting

Officer and/or his Representative determines that the reduction would be to

SECTION 01 11 00 Page 3 the advantage of the Government. (FAR 52.236-01)

1.4 DATUM AND BENCH MARKS

Soundings and Elevations shown in the contract drawings are in US Survey

Feet and refer to COE Mean Low Water (COE MLW). The Plane of COE MLW is

2.55 FEET BELOW NAVD88. The following Benchmark information should be referenced for defining local datum and required project depth.

LOCAL Benchmark: “HR-19”, USACE Disk

Coordinates Refer to US State Plane Coordinate System

NAD 1983. x: 1383029.185, y: 693355.76

New York East - Zone 3101

Elevation: 15.95' (NAVD88)

LOCAL Benchmark: “HR-18”, USACE Disk

Coordinates Refer to US State Plane Coordinate System

NAD 1983. x: 1375909.171, y: 690529.948

New York East – Zone 3101

Elevation: 6.83’ (NAVD88)

LOCAL Benchmark: “HR-20”, USACE Disk Coordinates Refer to US State Plane Coordinate System

NAD 1983. x: 1388400.889, y: 694780.110 New York East – Zone 3101

Elevation: 12.65’ (NAVD88)

LOCAL Benchmark: "HR-8", USACE Disk

Coordinates Refer to US State Plane Coordinate System

NAD 1983. x: 1314701.257, y: 686442.308

New York East - Zone 3101

Elevation: 45.36' (NAVD88)

All controls needs to be verified.

The contractor may contact the New York District Survey Section at (201)

333-0284 for assistance in establishing the location of the bench marks and the tide gages.

1.5 MISPLACED MATERIAL

Should the Contractor during the progress of the work, lose, dump, throw overboard, sink, or misplace any material, plant, machinery, or appliance, which in the opinion of the Contracting Officer and/or his Representative may be dangerous to or obstruct navigation, the Contractor shall recover and remove the same with the utmost dispatch. The Contractor shall give immediate notice, with description and location of such obstructions, to the Contracting Officer and/or his Representative or inspector, and when required shall mark or buoy such obstruction until the same are removed.

Should he refuse, neglect, or delay compliance with the above requirements, such obstructions may be removed by the Contracting Officer and/or his

Representative, and the cost of such removal may be deducted from any money due or to become due to the Contractor, or may be recovered under his bond. The liability of the Contractor for the removal of a vessel wrecked

SECTION 01 11 00 Page 4 or sunk without fault or negligence shall be limited to that provided in

Sections 15, 19, and 20 of the Rivers and Harbors Act of March 3, 1899 (33

USC. 410 et seq.) (DOD FARS SUPPL. 52.236-7006).

1.6 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

The entire work (Mob/Demob and Basic Work) is estimated to cost approximately $1,000,000.00 to $5,000,000.00.

1.7 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the

Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.8 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

File details come from the government source that posted it. Updated .