This document package includes specifications for maintenance dredging of the Hudson River Federal Navigation Project in Albany, New York. The solicitation calls for dredging of the Port of Albany Turning Basin to be conducted in accordance with the attached Water Quality Certification and New York State Parks Permit. Bidders must comply with all permit conditions, which require the contractor to fill out the parks permit application and provide supporting documentation for approval prior to commencement of dredging activities. The solicitation was issued by the U.S. Army Corps of Engineers New York District for maintenance dredging of the designated area to maintain navigability of the Hudson River waterway.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021
SECTION 00 90 02
WATER QUALITY AND NYS PARKS
PERMIT
03/21
PART 1 GENERAL
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
The following attachments have been provided for reference to the bidder for use in performing the contract requirements.
3.1.1 WATER QUALITY CERTIFICATE
The current Water Quality Certificate (11 pages) for the maintenance dredging of the Hudson River, NY, Federal Navigation Project is attached.
The contractor must comply with all conditions of the Water Quality
Certification.
3.1.2 NYS PARKS PERMIT
Hougtaling Island may be accessed by land, via Schodack State Park access roads and trails. As of 2020, NYS PARKS requires that the Contractor, fill out and submit the NYS Parks Permit application, and provide all required documentation listed in said permit application. The current application (2 pages) is attached, and will need approval.
The contractor must comply with all conditions of the NYS Parks Permit.
-- End of Section --