01 32 01.00 10 Project Schedule.pdf

PDF 167 KB Posted

Attached to
Maintenance Dredging, Hudson River, NY Federal Navigation Project, Port of Albany Turning Basin Dredge Area
Solicitation number
W912DS21B0007
Issued by

About this file

This document outlines requirements for a project schedule on the maintenance dredging of the Hudson River Port of Albany Turning Basin. Key details include the scope of dredging the Port of Albany Turning Basin on the Hudson River, with submittal requirements for a preliminary project schedule within 5 days of notice to proceed and an initial project schedule within 5 additional days. The schedule is to demonstrate a logical sequence of activities to complete the dredging through the entire contract performance period using critical path methodology. Periodic schedule updates are required on at least a monthly basis to track progress and determine earned value for payment. The document specifies various coding and formatting requirements for the project schedule and provides definitions and constraints for activities, milestones, calendars and floats.

View the file

Other files

File Type Posted
Bid Abstract_05-27-2021.pdf PDF
Amendment 0005_Houghtaling Island Topo.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment_0002_Site Visit Sign In Sheet.pdf PDF
Amendment_0002.pdf PDF
Amendment 0001_Pre-bid site vist_directions and instructions.pdf PDF
Amendment 0001.pdf PDF
00 01 15 list of drawings.pdf PDF
00 90 01 AA list of documents.pdf PDF
00 90 01 E- Report of Operations Pipeline Dipper or Bucket Dredges.pdf PDF
AFO - 6 - Index_Notes.pdf PDF
00 90 01 C 33CFR Oil Hazardous Form.pdf PDF
00 90 01 J-Location of Ice Houses.pdf PDF
00 90 01 F-Transportation and Placement Log Mechanical Dredges.pdf PDF
01 50 00 Temp Construction Facilites Controls.pdf PDF
01 58 00 Project ID.pdf PDF
01 57 20.00 10 Environmental protection.pdf PDF
00 90 02 AA WQC PARKS .pdf PDF
01 30 00 Admin Requirments.pdf PDF
W912DS21B0007.pdf PDF
00 90 01 K-Control Points.pdf PDF
01 78 00 clouseout Submittal.pdf PDF
00 90 01 I-Sediment_Physical and Chemistry Data Reports.pdf PDF
35 20 23 dredging.pdf PDF
AFO - 3 - Houghtaling Island Topo and Site.pdf PDF
01 33 00 Submittal Procedures.pdf PDF
01 45 00.00 20 quality control.pdf PDF
00 90 01 L-SUBMITTAL REGISTER_EXAMPLE ONLY.pdf PDF
00 90 01 H-Standard specifications for silt fence.pdf PDF
01 20 00 Tech Spec3.pdf PDF
01 42 00 Sources of Reference.pdf PDF
AFO - 5 - ATB HYDRO.pdf PDF
01 22 00.00 10 measurement and payment.pdf PDF
AFO - 4 - Houghtaling Offshore Hydro.pdf PDF
00 90 02 PARKS Permit Attachement.pdf PDF
00 90 01 A-CQC Report Example.pdf PDF
00 90 01 D-Guidelines for Preparing Accident Prevention Plan.pdf PDF
01 35 26 Gov Safety Requirment.pdf PDF
35 20 29 dredge material transport.pdf PDF
AFO - 2 -location.pdf PDF
01 20 00.00 20 price and payment procedures.pdf PDF
AFO - 1 - Index.pdf PDF
00 90 01 G-Daily Site Safety and Health Inspection Log.pdf PDF
00 90 01 B-Project Sign and Safety Sign.pdf PDF
00 90 02 WQC Attachement.pdf PDF
01 11 00 summary of work2.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Port of Albany Turning Basin, Hudson River, NY Federal Navigation Project 2021

SECTION 01 32 01.00 10 Page 1

PART 1 GENERAL

1.1 SUBMITTALS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

Government approval is required for submittals with a "G" designation, submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-Construction Submittals G, Progress Schedule; G

1.2 QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling projects similar in nature to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Working on the project shall also contribute in developing and maintaining an accurate Project

Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.1.1 SCHEDULING AND DETERMINATION OF PROGRESS

In accordance with the contract provisions, the Contractor shall, within five (5) days after receipt of Notice to Proceed by him or as otherwise determined by the Contracting Officer and/or his Representative, submit for approval a practicable Progress Schedule. The progress schedule shall be

SECTION 01 32 01.00 10 Page 2 in the form of a chart graphically indicating the sequence proposed to accomplish each work feature of operation (Eng. Form 2454 or an acceptable equivalent -e.g., computer-generated from a commercially available project management software package). The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of the receipt of the Notice to Proceed and indicating calendar days to completion. Each activity in construction shall be represented by an arrow. The head to tail arrangement of arrows shall flow from left to right. Each arrow representing an activity shall be annotated to show the activity description and duration. Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. When changes are authorized that result in contract time extensions, the Contractor shall submit a modified chart for approval by the Contracting Officer and/or his Representative. The terms of Section 00 72 00, Contract Clause entitled: SCHEDULES FOR

CONSTRUCTION CONTRACTS, with reference to overtime, extra shifts, etc., may be invoked when the Contractor fails to start or complete work features or portions of same by the time indicated by the milestone dates on the approved progress chart, or when it is apparent to the Contracting

Officer from the Contractor's actual progress that these dates will not be met. Neither on the chart nor on the periodic charts which the Contractor is required to prepare and submit, as described in paragraph, SCHEDULES

FOR CONSTRUCTION CONTRACTS of the Contract Clauses, shall the actual progress to be entered include or reflect any materials which may be on the site, but are not yet installed or incorporated in the work. For payment purposes only, an allowance will be made by the Contracting

Officer and/or his Representative of up to 100 percent of the invoiced cost of materials or equipment delivered to the site but not incorporated into the construction, pursuant to Section 00 72 00, Contract Clause entitled: "PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." The making of such an allowance will be contingent upon a determination by the

Contracting Officer and/or his Representative that the Contractor's compliance with the quality control requirements of the contract is more than satisfactory.

When the contractor submits his progress schedule, he will include in the submission a progress curve reflecting the intended schedule for completing the work. The progress curve (S-Curve) will be plotted to reflect

Cumulative Progress (Percent) based on placement along the Y-axis and Time along the X-axis. The progress curve will be furnished at the same time the progress schedule is submitted for approval and updated monthly by the

Contractor.

3.1.2 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

3.1.3 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the

SECTION 01 32 01.00 10 Page 3 approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the

Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

3.1.4 Default Terms

Failure of the Contractor to comply with the requirements of the

Contracting Officer shall be grounds for a determination, by the

Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 BASIS FOR PAYMENT AND COST LOADING

Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project

Schedule shall be capable of meeting all requirements of this specification. Comply with PRIMAVERA P6 - USACE MANDATORY REQUIREMENTS.

Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.

3.3.1 Critical Path Method

Use the Critical Path Method (CPM) of network calculation to generate the

Project Schedule. Prepare the Project Schedule using the Precedence

Diagram Method (PDM).

3.3.2 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The

Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

SECTION 01 32 01.00 10 Page 4

3.3.2.1 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations

(OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.

3.3.2.2 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.3.2.3 Contract Changes/Requests for Equitable Adjustment Coding (MODF)

Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the

Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.

Assign Activity codes for these activities with a Contract Changes/REA

Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.

3.3.2.4 Contract Line Item (CLIN) Coding (BIDI)

Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN

Item Code. CLIN Item code all activities, even when an activity is not cost loaded.

3.3.2.5 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to . Code fast track phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.

3.3.2.6 Category of Work Coding (CATW)

Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, SECTION 01 32 01.00 10 Page 5 but is not limited to: approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive

Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.

3.3.2.7 Definable Features of Work Coding (FOW1, FOW2, FOW3)

Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable

Feature of Work is defined in Specification Section 01 45 00.00 10 QUALITY

CONTROL. An activity shall not have more than one Definable Feature of

Work Code. Not all activities are required to be Definable Feature of Work

Coded.

3.3.3 Scheduled Project Completion and Activity Calendars

The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the

Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a

Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather

Sensitive Installation to those activities that are weather sensitive.

Original durations must account for anticipated normal adverse weather.

The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.

3.3.3.1 Project Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project" (or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.

3.3.3.2 Schedule Constraints and Open Ended Logic

Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities:

Start Project (or NTP) with no predecessor logic and End Project with no successor logic.

SECTION 01 32 01.00 10 Page 6

3.3.3.3 Early Project Completion

In the event the Preliminary or Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's

"early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.

3.3.4 Interim Completion Dates

Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.

3.3.4.1 Start Phase

Include as the first activity for a project phase an activity called "Start

Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the

NTP was acknowledged, and a zero day duration.

3.3.4.2 End Phase

Include as the last activity for a project phase an activity called "End

Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the specified completion date for that phase and a zero day duration.

3.3.4.3 Phase "X" Hammock

Include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" hammock activity shall be logically tied to the earliest and latest activities in the phase.

3.3.5 Default Progress Data Disallowed

Do not automatically update Actual Start and Finish dates with default mechanisms that may be included in the scheduling software. Activity

Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process shall match those dates provided from Contractor Quality Control

Reports. Failure of the Contractor to document the AS and AF dates on the

Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's updated schedule and the inability of the

Contracting Officer to evaluate Contractor progress for payment purposes.

Updating of the percent complete and the remaining duration of any activity shall be independent functions. Disable program features which calculate one of these parameters from the other.

3.3.6 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case

SECTION 01 32 01.00 10 Page 7 basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer.

3.3.7 Negative Lags and Start to Finish Relationships

Lag durations contained in the project schedule shall not have a negative value. Do not use Start to Finish (SF) relationships.

3.3.8 Calculation Mode

Schedule calculations shall retain the logic between predecessors and successors even when the successor activity starts and the predecessor activity has not finished. Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") will not be allowed.

3.3.9 Milestones

The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for each fast track design package released for construction; design complete;

foundation/substructure construction complete; superstructure construction complete; building dry-in or enclosure complete to allow the initiation of finish activities; permanent power complete; and building systems commissioning complete.

3.4 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data CD, reports, and network diagrams required for each submission are contained in paragraph

SUBMISSION REQUIREMENTS.

3.4.1 Preliminary Project Schedule Submission

Submit the Preliminary Project Schedule, defining the Contractor's planned operations for the first 90 calendar days for approval within 5 calendar days after the NTP is acknowledged. The approved Preliminary Project

Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. Detail it for the first 90 calendar days. It may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as previously specified. The Preliminary

Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required Plan and Program preparations, submissions and approvals identified in the contract (for example, Quality

Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, the planned submissions of all early design packages, permitting activities, design review conference activities and other non-construction activities intended to occur within the first 90 calendar days. Schedule any construction activities planned for the first 90 calendar days after NTP. Constrain planned construction activities by

Government acceptance of the associated design package(s) and all other specified Program and Plan approvals. Activity code any activities that

SECTION 01 32 01.00 10 Page 8 are summary in nature after the first 90 calendar days with Responsibility

Code (RESP) and Feature of Work code (FOW1, FOW2, FOW3).

3.4.2 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within 5 calendar days after NTP. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Initial Schedule shall be at a reasonable level of detail as determined by the Contracting Officer.

3.4.3 Periodic Schedule Updates

Based on the result of the meeting, specified in PERIODIC SCHEDULE UPDATE

MEETINGS, submit periodic schedule updates. These submissions will enable the Contracting Officer to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgment of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the

Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.

3.5 SUBMISSION REQUIREMENTS

Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:

3.5.1 Schedule Reports

The format, filtering, organizing and sorting for each schedule report shall be as directed by the Contracting Officer. Typically reports shall contain: Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and

Percent Complete. The following lists typical reports that will be requested. One or all of these reports may be requested for each schedule submission.

3.5.1.1 Activity Report

A list of all activities sorted according to activity number.

3.5.1.2 Logic Report

A list of detailed predecessor and successor activities for every activity in ascending order by activity number.

3.5.1.3 Total Float Report

A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

3.5.1.4 Earnings Report by CLIN

A compilation of the Contractor's Total Earnings on the project from the

NTP to the data date. This report shall reflect the earnings of specific

SECTION 01 32 01.00 10 Page 9 activities based on the agreements made in the schedule update meeting defined herein. Provided that the Contractor has furnished a complete schedule update, this report shall serve as the basis of determining progress payments. Group activities by CLIN item number and sort by activity number. This report shall: sum all activities coded to a particular CLIN and provide a CLIN item percent earned value; and complete and sum CLIN items to provide a total project percent complete. The printed report shall contain, for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Total Quantity, Quantity to

Date, Percent Complete (based on cost), and Earnings to Date.

3.6 PERIODIC SCHEDULE UPDATE MEETINGS

Conduct periodic schedule update meetings for the purposes of reviewing the

Contractor's proposed out of sequence corrections, determining causes for delay, correcting logic, maintaining schedule accuracy and determining earned value. Meetings shall occur at least monthly within five days of the proposed schedule data date and after the Contractor has updated the schedule with Government concurrence respecting actual start dates, actual finish dates, remaining durations and percent complete for each activity it intends to status. Provide a computer with the scheduling software loaded and a projector during the meeting which allows all meeting participants to view the proposed schedule update during the meeting. The meeting and resultant approvable schedule update shall be a condition precedent to a formal submission of the update as described in SUBMISSION REQUIREMENTS and to the submission of an invoice for payment. The meeting will be a working interactive exchange which will allow the Government and the Contractor the opportunity to review the updated schedule on a real time and interactive basis. The Contractor's authorized scheduling representative will organize, sort, filter and schedule the update as requested by the

Government. The meeting will last no longer than 8 hours. A rough draft of the proposed activity logic corrections and narrative report shall be provided to the Government 48 hours in advance of the meeting. The

Contractor's Project Manager and Authorized Scheduler shall attend the meeting with the Authorized Representative of the Contracting Officer.

3.6.1 Update Submission Following Progress Meeting

Submit a complete update of the project schedule containing all approved progress, revisions, and adjustments, pursuant to paragraph SUBMISSION

REQUIREMENTS not later than 4 working days after the periodic schedule update meeting, reflecting only those changes made during the previous update meeting.

3.6.2 Status of Activities

Update information, including Actual Start Dates (AS), Actual Finish Dates

(AF), Remaining Durations (RD), and Percent Complete shall be subject to the approval of the Government prior to the meeting. As a minimum, address the following items on an activity by activity basis during each progress meeting.

3.6.2.1 Start and Finish Dates

Accurately show the status of the AS and/or AF dates for each activity currently in-progress or completed since the last update. The Government may allow an AF date to be assigned with the percent complete less than 100 percent to account for the value of work remaining but not restraining

SECTION 01 32 01.00 10 Page 10 successor activities. Only assign AS dates when actual progress occurs on an activity.

3.6.2.2 Remaining Duration

Update the estimated RD for all incomplete activities independent of

Percent Complete. Remaining Durations may exceed the activity OD or may exceed the activity's prior update RD if the Government considers the current OD or RD to be understated based on current progress, insufficient work crews actually manning the job, unrealistic OD or deficiencies that must be corrected that restrain successor activities.

3.6.2.3 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete.

To allow for proper schedule management, cost load the correction of punch list from Government pre-final inspection activity(ies) not less than 1 percent of the total contract value, which activity(ies) may be declared

100 percent complete upon completion and correction of all punch list work identified during Government pre-final inspection(s).

3.6.2.4 Logic Changes

Specifically identify and discuss all logic changes pertaining to NTP on change orders, change orders to be incorporated into the schedule, Contractor proposed changes in work sequence, corrections to schedule logic for out-of-sequence progress, and other changes that have been made pursuant to contract provisions. The Government will only approve logic revisions for the purpose of keeping the schedule valid in terms of its usefulness in calculating a realistic completion date, correcting erroneous logic ties, and accurately sequencing the work.

3.6.2.5 Other Changes

Other changes required due to delays in completion of any activity or group of activities include: 1) delays beyond the Contractor's control, such as strikes and unusual weather. 2) delays encountered due to submittals, Government Activities, deliveries or work stoppages which make re-planning the work necessary. 3) Changes required to correct a schedule that does not represent the actual or planned prosecution and progress of the work.

3.7 REQUESTS FOR TIME EXTENSIONS

a. Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered.

The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

3.7.1 Time Extension for Unusually Severe Weather

a. If a time extension is requested due to adverse weather conditions, the contractor must chronologically list each day that was lost due to adverse

SECTION 01 32 01.00 10 Page 11 weather conditions with his daily reports. The Contracting Officer or his

Representative will examine whether the contractor is entitled to a time extension. The adverse weather days must prevent work for 50% or more of the contractor’s work day and delay work critical to the timely completion of the project. The Contracting Officer or his Representative will convert any delays meeting the above requirements to calendar days and issue a modification in accordance with Contract Clause “CHANGES.”

b. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default (Fixed-Price Construction)".

The listing below defines the monthly anticipated adverse weather for the contract period and is based upon NOAA or similar data for the geographic location of the project.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON 5 WORK

DAY WEEK STATION LOCATION: VARIOUS BASES, NY

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(31) (28) (31) (7) (8) (5) (6) (6) (4) (5) (6) (15)

c. The above schedule of anticipated adverse weather will constitute the base line for monthly (or portion thereof) weather time evaluations. Upon acknowledgment of the notice to proceed and continuing throughout the contract on a monthly basis, actual adverse weather days will be recorded on a calendar day basis (include weekends and holidays) and compared to the monthly anticipated adverse weather in subparagraph a. above. For purposes of the sub- paragraph b., the term actual adverse weather days shall include days impacted by actual adverse weather for 50% or more of the

Contractor's work day.

d. The number of actual adverse weather days shall be calculated chronologically from the first to the last day in each month. Once the number of actual adverse weather days anticipated in subparagraph a. above have been incurred, the Contracting Officer will examine any subsequently occurring adverse weather days to determine whether a contractor is entitled to a time extension. These subsequently occurring adverse weather days must prevent work for 50 percent or more of the Contractor's work day and delay work critical to the timely completion of the project. The

Contracting Officer will convert any delays meeting the above requirement to calendar days and issue a modification in accordance with the general provision entitled "Termination for Default - Damages for Delay - Time

Extensions".

e. The Contractor's schedule must reflect the above anticipated adverse weather delays on all weather dependent activities.

3.7.2 Justification of Delay

The project schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request. The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the

Contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, SECTION 01 32 01.00 10 Page 12 or any interim milestone date.

3.7.3 Submission Requirements

In the event the Contractor believes it is entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the Contracting

Officer: justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs

(updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. In response to each Request

For Proposal issued by the Government, submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.

Submit a justification for each request for a change in the contract completion date of less than 2 weeks based upon the most recent schedule update at the time of the NTP or constructive direction issued for the change. Such a request shall be in accordance with the requirements of other appropriate Contract Clauses and shall include, as a minimum:

a. A list of affected activities, with their associated project schedule activity number.

b. A brief explanation of the causes of the change.

c. An analysis of the overall impact of the changes proposed.

d. A sub-network of the affected area.

Identify activities impacted in each justification for change by a unique activity code contained in the required data file.

3.7.4 Additional Submission Requirements

The Contracting Officer may request an interim update with revised activities for any requested time extension of over 2 weeks. Provide this disk within 4 days of the Contracting Officer's request.

3.8 DIRECTED CHANGES

If the NTP is issued for changes prior to settlement of price and/or time, submit proposed schedule revisions to the Contracting Officer within 2 weeks of the NTP being issued. The Contracting Officer will approve proposed revisions to the schedule prior to inclusion of those changes within the project schedule. If the Contractor fails to submit the proposed revisions, the Contracting Officer may furnish the Contractor with suggested revisions to the project schedule. Include these revisions in the project schedule until revisions are submitted, and final changes and impacts have been negotiated. If the Contractor has any objections to the revisions furnished by the Contracting Officer, advise the Contracting

Officer within 2 weeks of receipt of the revisions. Regardless of the objections, continue to update the schedule with the Contracting Officer's revisions until a mutual agreement in the revisions is reached. If the

Contractor fails to submit alternative revisions within 2 weeks of receipt of the Contracting Officer's proposed revisions, the Contractor will be deemed to have concurred with the Contracting Officer's proposed revisions. The proposed revisions will then be the basis for an equitable

SECTION 01 32 01.00 10 Page 13 adjustment for performance of the work.

3.9 WEEKLY PROGRESS MEETINGS

a. Meet weekly with the Government (or as otherwise mutually agreed to) between the meetings described in paragraph PERIODIC SCHEDULE UPDATE

MEETINGS for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. The then current and approved schedule update shall be used for the purposes of this meeting and for the production and review of reports. The Contractor's Project

Manager and the Authorized Representative of the Contracting Officer shall attend. The weekly progress meeting will address the status of

Requests For Information (RFI's), and Requests For Proposal (RFP's) and

Submittals.

b. Provide a bar chart produced by the scheduling software, organized by

Total Float and Sorted by Early Start Date, and a two week "look-ahead" schedule by filtering all schedule activities to show only current ongoing activities and activities schedule to start during the upcoming two weeks, organized by Work Area Code (AREA) and sorted by Early Start

Date.

c. The Government and the Contractor shall jointly review the reports. If it appears that activities on the longest path(s) which are currently driving the calculated completion date (driving activities), are not progressing satisfactorily and therefore could jeopardize timely project completion, corrective action must be taken immediately.

Corrective action includes but is not limited to: increasing the number of work crews; increasing the number of work shifts; increasing the number of hours worked per shift; and determining if Government responsibility coded activities require Government corrective action.

3.10 OWNERSHIP OF FLOAT

Float available in the schedule, at any time, shall not be considered for the exclusive use of either the Government or the Contractor.

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

(Not Applicable)

-- End of Section --