WFLHD Construction Contract Administration_FY 23 V2.pdf
PDF 162 KB Posted
- Solicitation number
- 69056723B000021
About this file
This document is a Construction Contract Administration document that provides information about the Federal Highway Administration's (FHWA) procedures for definitizing equitable adjustments for change orders under construction contracts.
The document outlines the FHWA's past performance data for the prior 3 fiscal years regarding the time required to definitize equitable adjustments for change orders. The data shows the number of change order proposals definitized within various timeframes, including 0-30 days, 31-60 days, 61-90 days, 91-180 days, 181-365 days, and 366 or more days. There are no agency-specific additional policies and procedures that exist at this time.
The document is related to a federal contract opportunity for the OR FLAP GRANT 24(2), Granite Hill Road Reconstruction, Phase II project, which is being solicited by the Department of Transportation Federal Highway Administration. The Invitation for Bids (IFB), Plans, Physical Data, and the Construction Contract Administration Document per FAR 36.211 are provided as attachments to the solicitation.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2021 FY 2022 FY 2023
0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4
File details come from the government source that posted it. Updated .