QA_12-03-2024.pdf

PDF 61 KB Posted

Attached to
OR FLAP GRANT 24(2), Granite Hill Road Reconstruction, Phase II
Solicitation number
69056723B000021
Issued by

About this file

This is a Questions and Answers document for the OR FLAP GRANT 24(2) Granite Hill Road Reconstruction Phase II project, containing 11 contractor questions and government responses dated between November 26 and December 3, 2024.

Key clarifications include: bidders must access the planholders list through SAM.gov with appropriate registration and roles; no detour is required during road closures but traffic must be accommodated per solicitation documents; powerline conflicts will be addressed in Amendment A003; in-water work restrictions do not prevent all construction from starting until June 15th; and holiday work restrictions are governed by Subsection 156.07(k). Several technical questions about structural excavation, temporary bridge spans, aggregate sources, and traffic control requirements were addressed by referring bidders back to the solicitation documents.

View the file

Other files

File Type Posted
Bid Tabs_OR FLAP GRANT 24(2).pdf PDF
BidSum_OR FLAP GRANT 24(2).pdf PDF
QA_12-09-2024.pdf PDF
QA_12-04-2024.pdf PDF
Amendment A003.pdf PDF
QA_11-27-2024-2.pdf PDF
QA_11-27-2024.pdf PDF
Amendment A002.pdf PDF
QA_11-26-2024.pdf PDF
Amendment A001.pdf PDF
ora-grant24-2-Bull Run 03_proposed-horizontal-alignment.pdf PDF
ora-grant24-2_Bull Run 02_proposed-horizontal-alignment.pdf PDF
revised ora-grant24-2_plans.pdf PDF
ora-grant24-2_boundary creek_Earthwork.pdf PDF
AOP_Boundary_Creek_Hydraulics_Memo_Final.pdf PDF
ora-grant24-2_Bull Run 4_489-65 to 495-00_Earthwork.pdf PDF
ora-grant24-2_superelevation.pdf PDF
ora-grant24-2_Bull Run 01_proposed-vertical-alignment.pdf PDF
GR 04-21 Granite Hill Road Final Geotechnical Recommendations_FINAL.pdf PDF
Bull Run Creek_No-4_Bridge_HydraulicsTSL_Report_Final.pdf PDF
ora-grant24-2_Bull Run 03_Earthwork.pdf PDF
Bull Run Creek_No-2_AOP_Hydraulics_Memo_Final.pdf PDF
ora-grant24-2_Boundary creek_proposed-horizontal-alignment.pdf PDF
ora-grant24-2_Bull Run 1_Earthwork.pdf PDF
ora-grant24-2_Bull Run 02_proposed-vertical-alignment.pdf PDF
WFLHD Construction Contract Administration_FY 23 V2.pdf PDF
IFB_69056723B000021_OR FLAP GRANT 24(2).pdf PDF
Bull Run Creek_No-1_AOP_Hydraulics_Memo_Final.pdf PDF
Physical Data.zip ZIP file
ora-grant24-2_Bull Run 4_495-00 to 498-75_Earthwork.pdf PDF
ora-grant24-2_control-points.xlsx XLSX spreadsheet
ora-grant24-2_Bull Run 04_proposed-horizontal-alignment.pdf PDF
Bull Run Creek_No-3_Bridge_HydraulicsTSL_Report_Final.pdf PDF
ora-grant24-2_Bull Run 04_proposed-vertical-alignment.pdf PDF
ora-grant24-2_ESCP_Granite 2_2024.pdf PDF
ora-grant24-2_Bull Run 03_proposed-vertical-alignment.pdf PDF
ora-grant24-2_XS.dgn.pdf PDF
ora-grant24-2_Bull Run 2_Earthwork.pdf PDF
ora-grant24-2_boundary creek_proposed-vertical-alignment.pdf PDF
ora-grant24-2_Bull Run 01_proposed-horizontal-alignment.pdf PDF
GM14-23 Granite Hill Final Foundation Memorandum.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR FLAP GRANT 24(2)

Granite Hill Road Reconstruction, Phase

# General Technical Question Answer Date

1 X

Hi I was wondering if you could share the prospective bidder list for this project "OR FLAP

GRANT 24(2), Granite Hill Road Reconstruction, Phase II." I am interested in sub-contracting some work, and wanted to reach out to a few prospective bidders before the bid date.

The Government does not provide this since bidders may obtain the registered vendors list (aka planholders list) from sam.gov after linking their entity to their registration. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in

SAM.gov.

If you need additional assistance, you can reach the Federal Service Desk at

866-606-8220 or https://www.fsd.gov/gsafsd_sp?id=gsa_ind ex.

11/26/2024

2 X Can you please send me the bid holders list or a link to the bid holders list for this project that bids 12/10/2024

The Government does not provide this since bidders may obtain the registered vendors list (aka planholders list) from sam.gov after linking their entity to their registration. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in

SAM.gov.

If you need additional assistance, you can reach the Federal Service Desk at

866-606-8220 or https://www.fsd.gov/gsafsd_sp?id=gsa_ind ex.

11/26/2024

3 X Section 208 – Structural Excavation, does not have a Bid item in either Schedule A or B. please provide direction as to where this work is to be included.

See Section 209. 11/27/2024

4 X Section 156.04, allows for the closure of Granite Hill Road per the dates and times listed (a) thru

(f), will a detour be required?

No. Accommodate traffic according to solicitation documents. 11/27/2024

5 X Subsection 156.04 Accommodating Traffic During Work, states to immediately open the road to emergency vehicles, without a detour please clarify how to accommodate this.

Please submit bids according to the solicitation documents. 11/27/2024

6 X Will the powerlines (specifically at Boundary Creek and Bull Run #3 construction sites) be moved out of the way prior to our work?

This will be addressed under Amendment A003. 12/3/2024

7 X What are the span lengths for the temporary bridges at Bull Run #3 and #4? It’s difficult to tell where the Ordinary High Water (OHW)Pleas Mark is located to be able to guess span lengths.

Please submit bids according to the solicitation documents. 12/3/2024

8 X Are there any preferred aggregate sources like the one that was listed in Phase 1?

The solicitation does not list any preferred aggregate sources. Please submit bids according to the solicitation documents.

12/3/2024

9 X

It appears that the in-water restrictions (pg. 226 of the IFB Document) restrict us from starting any construction until June 15th at Bull Run 3 & 4 and July 1st at Boundary Creek and Bull Run 1

& 2. Is the correct assumption?

The in-water restrictions do not restrict a contractor from starting all construction until June15th. Please submit bids according to the solicitation documents.

12/3/2024

10 X

Page 226 of the IFB also states that we can close Granite Rd weekly during the dates listed. Do we need to have 24-hr per day flagging at the three box culverts during the weekends since there isn’t traffic diversions at those locations?

This is dependent on the ways and means of the Contractors. Please submit bids according to the solicitation documents.

12/3/2024

11 X

The Holiday Work restrictions (pg. 257 of the IFB Document) would suggest that we can’t work on those days on an already tight schedule. Are we allowed to work on Bull Run 3 and 4 if we don’t impact traffic since there will be traffic diversions around those two locations?

See Subsection 156.07(k). Please submit bids according to the solicitation documents.

12/3/2024

Check General or Technical

File details come from the government source that posted it. Updated .