Amendment 0004 - 12018718_12018724_Spec013000_Response.pdf
PDF 12 KB Posted
- Attached to
- Construction of Chilled Water Plant and Site Utility Upgrades at VA Medical Center in West Haven, CT
- Solicitation number
- W912WJ26RA008
About this file
This is an excerpt from a Department of Veterans Affairs solicitation for the West Haven VA Medical Center Phase A2-Chilled Water Plant Replacement project (Solicitation #W912WJ26RA008/VA #VAWH-689-040).
The document establishes project governance and partnering requirements for the contractor. A formal partnering session must be conducted with an experienced, third-party independent facilitator who is not an employee of the contractor. The partnering session outcome must include an escalation matrix identifying key Government and Contractor decision makers by name with anticipated decision durations. Follow-on partnering sessions must be hosted at three- to six-month intervals or more frequently as needed, lasting generally a half day or less, with attendance limited to personnel required to resolve current issues. The same facilitator must lead follow-on sessions unless the Contracting Officer permits an alternative. All costs associated with follow-on partnering sessions are the contractor's responsibility, including securing and providing an appropriate meeting venue. An integrated governance structure manages the project through a "One Team" concept with objectives of achieving effective and accountable project leadership, open and effective communication within the team and with stakeholders, and fostering trust, honesty, and shared values. The Senior Advisory Group meets quarterly after the formal partnering session and includes representatives from USACE (North Atlantic Division Senior Executive, Mid-Atlantic District Chief, Regional Chief of E&C, and Headquarters Project Management Office) and DVA (CFM Executive Liaison and Eastern Regional Director).
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Veterans Affairs Solicitation #W912WJ26RA008/VA #VAWH-689-040 West Haven VA Medical Center Phase A2-Chilled Water Plant Replacement
d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant
- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.
e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.
f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.
Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.
1.8 GOVERNANCE STRUCTURE
An integrated governance structure is used to manage the project, shown below. There are members of each organization strategically and tactically placed within the Governance structure to facilitate communication and issue resolution at the appropriate level; including the ability to obtain support from each appropriate management structure to solve issues that are inherently the responsibility of separate agencies. The Contractor will participate as members of the Governance structure at the Senior Advisory Group level and below. Timely delivery cannot be accomplished by any one organization alone and requires an integrated team concept promoted via the "One Team" Governance concept.
The Objectives are:
(1) Effective and accountable project leadership;
(2) Open and effective communication within the team and with stakeholders; and the result is
(3) The team fosters trust, honesty, and shared values
1.8.1 Senior Advisory Group (SAG)
Meetings held quarterly after the formal partnering session. Members include:
a. USACE NAD Senior Executive, SES
b. USACE NAD MID Chief
c. USACE NAD Regional Chief of E&C
d. HQUSACE PMO
e. DVA CFM Executive Liaison
f. DVA CFM Eastern Regional Director
SECTION 01 30 00 Page 5
MBSaquilayan Text Box including securing and providing
MBSaquilayan Text Box an appropriate meeting venue
MBSaquilayan Callout in person
MBSaquilayan Line