Specifications - Volume II.pdf
PDF 7 MB Posted
- Attached to
- Construction of Chilled Water Plant and Site Utility Upgrades at VA Medical Center in West Haven, CT
- Solicitation number
- W912WJ26RA008
About this file
This is a Specifications Volume II document for the West Haven VA Medical Center Chilled Water Plant Replacement and Site Utility Improvements Phase A2 project, issued by the Department of Veterans Affairs (Solicitation #W912WJ26RA008/VA #VAWH-689-040) with a ready-to-advertise date of July 31, 2026. The specifications cover multiple construction disciplines including civil, structural, exterior and interior architecture, mechanical and plumbing, electrical, telecommunications, and fire protection systems. The document provides comprehensive technical requirements across 33 divisions organized by construction trade, referencing industry standards such as NFPA, ASME, ASTM, and NSF International.
Key technical requirements include: wet-pipe sprinkler systems designed per NFPA 13 with hydraulically calculated automatic systems and 1500 gpm capacity fire pumps; plumbing systems with domestic water distribution, sanitary and storm drainage, compressed air systems, and medical gas systems; HVAC systems including boiler plant piping, hydronic systems, water chillers, cooling towers, and air handling units; electrical systems with medium-voltage and low-voltage distribution, lighting controls, and uninterruptible power supply; and telecommunications and fire detection systems. All equipment and materials must be UL or FM listed, new unless otherwise specified, and sourced from manufacturers with permanent authorized service organizations within 100 miles capable of emergency response within four hours. The specifications mandate comprehensive commissioning, testing, training of VA personnel, as-built documentation in multiple formats (printed, PDF, and AutoCAD), and operations and maintenance manuals for all systems. Submittals require government approval and must be prepared by qualified technicians holding NICET Level III or IV certification or Professional Engineer stamps in applicable disciplines.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
West Haven VA Medical Center
Chilled Water Plant Replacement and Site Utility Improvements – Phase A2
Surgical and Clinical Tower
July 31, 2026
Ready to Advertise
Specifications
VOLUME 2
CIVIL STRUCTURAL
EXTERIOR
ARCHITECTURE
INTERIOR
ARCHITECTURE
MECHANICAL &
PLUMBING
ELECTRICAL
TELECOMMUNICATIONS FIRE PROTECTION
DATE:
7/31/2026
7/31/2026
JE
FF
REY KEILMAN
No. ARI.0015787
Department of Veterans Affairs Solicitation #W912WJ26RA008/VA #VAWH-689-040 West Haven VA Medical Center Phase A2-Chilled Water Plant Replacement
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 32 00 08/02 GEOTECHNICAL DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 11/21 GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00 04/94 MEASUREMENT AND PAYMENT
01 30 00 11/20, CHG 1: 08/21 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23, CHG 1: 08/24 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 21 02/20 CONSTRUCTION PHASE BIM, CIM, AND CAD
REQUIREMENTS
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 05/24 CONSTRUCTION INDOOR AIR QUALITY
MANAGEMENT
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 43 30 01/25 MOCKUPS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 29 TESTING LABORATORY SERVICES
01 45 35 11/20 SPECIAL INSPECTIONS
01 45 41 EXTERIOR ENCLOSURE PERFORMANCE
REQUIREMENTS, MOCKUPS, AND TESTING
01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 3: 11/21 PROJECT IDENTIFICATION
01 58 16 TEMPORARY INTERIOR SIGNAGE
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 81 13 10/17 SUSTAINABLE CONSTRUCTION REQUIREMENTS
01 81 13.02 4/23 SUSTAINABILITY CERTIFICATION
REQUIREMENTS - LEED v4 BD+C
01 86 25 CYBERSECURITY FOR FACILITY RELATED
CONTROL SYSTEMS
01 91 00.01 05/19, CHG 2: 08/20 DVA/USACE PROJECTS GENERAL
COMMISSIONING REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 82 11 1/21 TRADITIONAL ASBESTOS ABATEMENT
02 82 13.13 1/21 GLOVEBAG ASBESTOS ABATEMENT
02 83 33.13 1/21 LEAD-BASED PAINT REMOVAL AND DISPOSAL
DIVISION 03 - CONCRETE
03 30 00 1/21 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
DOCUMENT PROJECT Page 1
04 01 00 1/21 MAINTENANCE OF MASONRY
04 05 13 2/17 MASONRY MORTARING
04 20 00 8/17 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 11/18 STRUCTURAL STEEL FRAMING
05 31 00 1/21 STEEL DECKING
05 36 00 1/21 COMPOSITE METAL DECKING
05 40 00 1/21 COLD-FORMED METAL FRAMING
05 50 00 8/18 METAL FABRICATIONS
05 51 00 1/21 METAL STAIRS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 10/17 ROUGH CARPENTRY
06 16 63 1/21 CEMENTITIOUS SHEATHING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 1/21 PREPARATION FOR RE-ROOFING
07 08 00.01 8/19 DVA/USACE PROJECTS FACILITY EXTERIOR
CLOSURE COMMISSIONING
07 13 52 1/21 MODIFIED BITUMINOUS SHEET WATERPROOFING
07 18 13 1/21 PEDESTRIAN TRAFFIC COATINGS
07 21 13 1/21 THERMAL INSULATION
07 21 23 1/21 LOOSE-FILL INSULATION
07 22 00 1/21 ROOF AND DECK INSULATION
07 27 27 1/21 FLUID-APPLIED MEMBRANE AIR BARRIERS,
VAPOR RETARDING
07 42 13 08/25 METAL WALL PANELS
07 42 63 08/25 FABRICATED WALL PANEL ASSEMBLIES
07 54 23 1/21 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
07 60 00 1/21 FLASHING AND SHEET METAL
07 71 00 1/21 ROOF SPECIALTIES
07 72 00 1/21 ROOF ACCESSORIES
07 81 00 7/23 APPLIED FIREPROOFING
07 84 00 1/21 FIRESTOPPING
07 92 00 4/22 JOINT SEALANTS
07 95 13 1/21 EXPANSION JOINT COVER ASSEMBLIES
DIVISION 08 - OPENINGS
08 11 13 1/21 HOLLOW METAL DOORS AND FRAMES
08 31 13 06/25 ACCESS DOORS AND FRAMES
08 33 00 1/21 COILING DOORS
08 41 13 1/21 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 44 13 4/20 GLAZED ALUMINUM CURTAIN WALLS
08 71 00 3/24 DOOR HARDWARE
08 80 00 1/21 GLAZING
08 90 00 1/21 LOUVERS AND VENTS
DIVISION 09 - FINISHES
09 05 16 1/21 SUBSURFACE PREPARATION FOR FLOOR
FINISHES
09 22 16 6/18 NON-STRUCTURAL METAL FRAMING
09 29 00 4/20 GYPSUM BOARD
DOCUMENT PROJECT Page 2
09 30 13 1/21 CERAMIC/PORCELAIN TILING
09 51 00 12/18 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 65 13 1/21 RESILIENT BASE AND ACCESSORIES
09 65 19 5/18 RESILIENT TILE FLOORING
09 67 23.20 12/21 RESINOUS (EPOXY BASE) WITH VINYL CHIP
BROADCAST (RES-2)
09 91 00 PAINTING
DIVISION 10 - SPECIALTIES
10 14 00 1/21 SIGNAGE
10 22 13 1/21 WIRE MESH PARTITIONS
10 26 00 1/21 WALL AND DOOR PROTECTION
10 28 00 1/21 TOILET, BATH, AND LAUNDRY ACCESSORIES
10 44 13 8/18 FIRE EXTINGUISHER CABINETS
DIVISION 12 - FURNISHINGS
12 24 00 8/17 WINDOW SHADES
12 36 00 11/23 WINDOW STOOLS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 00 4/24 TRACTION ELEVATOR - NEW
DIVISION 21 - FIRE SUPPRESSION
21 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
FIRE SUPPRESSION SYSTEMS
21 13 13 6/15 WET-PIPE SPRINKLER SYSTEMS
21 30 13 5/15 ELECTRIC-DRIVEN, FIRE PUMPS
DIVISION 22 - PLUMBING
22 05 11 1/23 COMMON WORK RESULTS FOR PLUMBING
22 05 12 9/20 GENERAL MOTOR REQUIREMENTS FOR
PLUMBING EQUIPMENT
22 05 19 9/20 METERS AND GAUGES FOR PLUMBING PIPING
22 05 23 11/22 GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 05 33 9/20 HEAT TRACING FOR PLUMBING PIPING
22 07 11 9/15 PLUMBING INSULATION
22 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
PLUMBING SYSTEMS
22 11 00 5/21 FACILITY WATER DISTRIBUTION
22 11 23 9/15 DOMESTIC WATER PUMPS
22 12 16 9/15 FACILITY ELEVATED, POTABLE-WATER
STORAGE TANKS
22 13 00 9/20 FACILITY SANITARY AND VENT PIPING
22 14 00 9/15 FACILITY STORM DRAINAGE
22 14 29 9/15 SUMP PUMPS
22 14 36 9/15 PACKAGED, SUBMERSIBLE, DRAINAGE PUMP
UNITS
22 15 00 9/20 GENERAL SERVICE COMPRESSED-AIR SYSTEMS
22 33 00 9/20 HEAT PUMP DOMESTIC WATER HEATER
22 40 00 5/24 PLUMBING FIXTURES
22 62 00 5/23 VACUUM SYSTEMS FOR LABORATORY AND
HEALTHCARE FACILITIES
22 63 00 5/23 GAS SYSTEMS FOR LABORATORY AND
DOCUMENT PROJECT Page 3
HEALTHCARE FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 11 3/23 COMMON WORK RESULTS FOR HVAC
23 05 12 3/23 GENERAL MOTOR REQUIREMENTS FOR HVAC
AND STEAM GENERATION EQUIPMENT
23 05 41 3/23 NOISE AND VIBRATION CONTROL FOR HVAC
PIPING AND EQUIPMENT
23 05 93.01 11/21 DVA/USACE PROJECTS TESTING, ADJUSTING,
AND BALANCING FOR HVAC
23 07 11 2/20 HVAC AND BOILER PLANT INSULATION
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL SYSTEMS
23 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
HVAC SYSTEMS
23 09 23 3/23 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC
23 10 00 4/20 FACILITY FUEL OIL SYSTEMS
23 21 11 3/24 BOILER PLANT PIPING SYSTEMS
23 21 13 06/25 HYDRONIC PIPING
23 21 23 3/23 HYDRONIC PUMPS
23 22 13 3/24 STEAM AND CONDENSATE HEATING PIPING
23 22 23 4/20 STEAM CONDENSATE PUMPS
23 25 00 3/23 HVAC WATER TREATMENT
23 31 00 3/23 HVAC DUCTS AND CASINGS
23 34 00 3/23 HVAC FANS
23 37 00 3/23 AIR OUTLETS AND INLETS
23 40 00 3/23 HVAC AIR CLEANING DEVICES
23 50 11 3/22 BOILER PLANT MECHANICAL EQUIPMENT
23 64 00 3/24 PACKAGED WATER CHILLERS
23 65 00 3/23 COOLING TOWERS
23 73 00 3/23 INDOOR CENTRAL-STATION AIR-HANDLING
UNITS
23 81 00 3/24 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 43 3/23 AIR-SOURCE UNITARY HEAT PUMPS
23 82 00 3/23 CONVECTION HEATING AND COOLING UNITS
23 82 16 3/24 AIR COILS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - BUILDING AUTOMATION
SYSTEMS (L-M-M)
25 05 11.02 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - UTILITY MONITORING
AND CONTROL SYSTEMS (L-L-L)
25 05 11.03 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - ELECTRONIC SECURITY
SYSTEMS (M-M-M)
25 05 11.04 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - FIRE AND LIFE SAFETY
SYSTEMS (L-L-L)
25 10 10 2/10 ADVANCED UTILITY METERING SYSTEM
DIVISION 26 - ELECTRICAL
26 05 11 11/22 REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS
26 05 13 06/25 MEDIUM-VOLTAGE CABLES
26 05 19 11/22 LOW-VOLTAGE ELECTRICAL POWER
DOCUMENT PROJECT Page 4
CONDUCTORS AND CABLES
26 05 26 11/22 GROUNDING AND BONDING FOR ELECTRICAL
SYSTEMS
26 05 33 11/22 RACEWAY AND BOXES FOR ELECTRICAL
SYSTEMS
26 05 41 06/25 UNDERGROUND ELECTRICAL CONSTRUCTION
26 05 73 11/22 OVERCURRENT PROTECTIVE DEVICE
COORDINATION STUDY
26 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
ELECTRICAL SYSTEMS
26 09 23 11/22 LIGHTING CONTROLS
26 11 16 11/22 SECONDARY UNIT SUBSTATIONS
26 12 19 11/22 PAD-MOUNTED, MEDIUM-VOLTAGE
TRANSFORMERS
26 13 01 05/24 PAD-MOUNTED DEAD-FRONT AIR INSULATED
SWITCHGEAR
26 13 13 06/25 MEDIUM-VOLTAGE CIRCUIT BREAKER
SWITCHGEAR
26 22 00 11/22 LOW-VOLTAGE TRANSFORMERS
26 23 00 11/22 LOW-VOLTAGE SWITCHGEAR
26 24 13 11/22 DISTRIBUTION SWITCHBOARDS
26 24 16 11/22 PANELBOARDS
26 27 26 11/22 WIRING DEVICES
26 29 11 11/22 MOTOR CONTROLLERS
26 29 21 11/22 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 33 53 11/22 STATIC UNINTERRUPTIBLE POWER SUPPLY
26 36 23 11/22 AUTOMATIC TRANSFER SWITCHES
26 41 00 11/22 FACILITY LIGHTNING PROTECTION
26 43 13 11/22 SURGE PROTECTIVE DEVICES
26 51 00 3/24 INTERIOR LIGHTING
26 56 00 11/22 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 11 9/19 REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS
27 05 26 11/21 GROUNDING AND BONDING FOR
COMMUNICATIONS SYSTEMS
27 05 33 10/18 CONDUITS AND BACKBOXES FOR
COMMUNICATIONS SYSTEMS
27 05 36 10/18 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 05 53 7/21 IDENTIFICATION FOR COMMUNICATIONS
SYSTEMS
27 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
COMMUNICATIONS SYSTEMS
27 10 00 6/15 STRUCTURED CABLING
27 11 00 6/15 TELECOMMUNICATIONS ROOM FITTINGS
27 11 16 COMMUNICATIONS CABINETS, RACKS,
FRAMES, AND ENCLOSURES
27 11 19 COMMUNICATIONS TERMINATION BLOCKS AND
PATCH PANELS
27 13 13 COMMUNICATIONS COPPER BACKBONE CABLING
27 13 13.13 COMMUNICATIONS COPPER CABLE SPLICING
AND TERMINATIONS
27 13 23 COMMUNICATIONS OPTICAL FIBER BACKBONE
CABLING
27 13 23.13 COMMUNICATIONS OPTICAL FIBER SPLICING
AND TERMINATIONS
27 15 00 1/16 COMMUNICATIONS STRUCTURED CABLING
DOCUMENT PROJECT Page 5
27 15 13 COMMUNICATIONS COPPER HORIZONTAL
CABLING
27 16 19 COMMUNICATIONS PATCH CORDS, STATION
CORDS, AND CROSS CONNECT WIRE
27 51 16 10/18 PUBLIC ADDRESS
27 78 00 5/24 CLOSEOUT SUBMITTALS FOR COMMUNICATIONS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 05 00 4/18 COMMON WORK RESULTS FOR ELECTRONIC
SAFETY AND SECURITY
28 05 13 10/18 CONDUCTORS AND CABLES FOR ELECTRONIC
SAFETY AND SECURITY
28 05 26 9/11 GROUNDING AND BONDING FOR ELECTRONIC
SAFETY AND SECURITY
28 05 28.33 9/11 CONDUITS AND BACKBOXES FOR ELECTRONIC
SAFETY AND SECURITY
28 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
ELECTRONIC SAFETY AND SECURITY SYSTEMS
28 13 00 10/11 PHYSICAL ACCESS CONTROL SYSTEM
28 23 00 9/11 VIDEO SURVEILLANCE
28 31 00 10/11 FIRE DETECTION AND ALARM
DIVISION 31 - EARTHWORK
31 20 00 08/23 EARTHWORK
31 23 19 10/12 DEWATERING
31 23 23.33 10/12 FLOWABLE FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 23 8/16 CEMENT AND CONCRETE FOR EXTERIOR
IMPROVEMENTS
32 12 16 9/15 ASPHALT PAVING
32 13 15.20 11/22 CONCRETE PAVEMENT FOR FUEL STORAGE
CONTAINMENT DIKES
32 17 23 8/16 PAVEMENT MARKINGS
32 31 13 11/21 CHAIN LINK FENCES AND GATES
32 31 40 11/21 HIGH-SECURITY FENCES AND GATES
DIVISION 33 - UTILITIES
33 08 00.01 8/19 DVA/USACE PROJECTS COMMISSIONING OF
SITE UTILITY SYSTEMS
33 10 00 3/17 WATER UTILITIES
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 46 13 05/18 FOUNDATION DRAINAGE
33 56 19 11/22 FUEL IMPERMEABLE LINER SYSTEM
33 63 00 2/24 STEAM ENERGY DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
DOCUMENT PROJECT Page 6
SECTION TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
SECTION 21 08 00.01
DVA/USACE PROJECTS COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
8/19
PART 1 GENERAL
1.1 DESCRIPTION
1.2 RELATED WORK
1.3 SUMMARY
1.4 DEFINITIONS
1.5 COMMISSIONED SYSTEMS
1.6 SUBMITTALS
1.7 SUBMITTAL INSTRUCTIONS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 CONSTRUCTION INSPECTIONS
3.2 PRE-FUNCTIONAL CHECKLISTS
3.3 CONTRACTORS TESTS
3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
3.5 TRAINING OF VA PERSONNEL
-- End of Section Table of Contents --
SECTION 21 08 00.01 Page 1
SECTION 21 08 00.01
8/19
DVA/USACE PROJECTS COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
PART 1 GENERAL
1.1 DESCRIPTION
a. The requirements of this Section apply to all sections of Division 21.
b. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00.01 DVA/USACE PROJECTS GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00.01 DVA/USACE PROJECTS GENERAL COMMISSIONING REQUIRMENTS. A Commissioning Agent (CxA) appointed by the Government and Commissioning Manager (CxM) as indicated in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS will manage the commissioning process.
1.2 RELATED WORK
a. UFGS GENERAL REQUIREMENTS sections
b. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS
c. UFGS Section 01 33 00 SUBMITTAL PROCEDURES
1.3 SUMMARY
a. This Section includes requirements for commissioning the Fire Suppression systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS.
b. Refer to Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
1.4 DEFINITIONS
Refer to Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.5 COMMISSIONED SYSTEMS
a. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS and of Division 21, is required in cooperation with the VA and the Commissioning Agent.
b. The Fire Suppression systems commissioning will include the systems listed in Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING
REQUIREMENTS:
SECTION 21 08 00.01 Page 2
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are forinformation only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-06 Test Reports
Pre-Functional Checklists ; G, DO
Contractors Tests ; G, DO
Systems Functional Performance Testing ; G, DO
SD-08 Manufacturer's Instructions
Training Agendas And Trainer Resumes ; G, DO
Training Plans ; G, DO
1.7 SUBMITTAL INSTRUCTIONS
a. The commissioning process requires review of selected Submittals. The CxA will provide a list of submittals that will be reviewed by the CxA and CxM. This list will be reviewed and approved by the DVA/USACE prior to forwarding to the Contractor. Refer to UFGS Section 01 33 00 SUBMITTAL PROCEDURES for further details.
b. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 CONSTRUCTION INSPECTIONS
Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The Contractor shall coordinate with the CxA and CxM in accordance with Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIRMENTS and the Commissioning plan to schedule inspections as required to support the Commissioning Process.
3.2 PRE-FUNCTIONAL CHECKLISTS
The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The CxM will prepare Pre-Functional Checklists to be used to document equipment installation.
The Contractor shall complete the checklists. Completed checklists shall be submitted to the DVA/USACE, and CxA for review. The CxM and CxA may spot check a sample of completed checklists. If the CxM and CxA determine that the information provided on the checklist is not accurate, the CxM
SECTION 21 08 00.01 Page 3 will return the marked-up checklist to the Contractor for correction and resubmission. If the CxM and CxA determine that a significant number of completed checklists for similar equipment are not accurate, the CxM in coordination with CxA will select a broader sample of checklists for review. If the CxM and CxA determine that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00.01 DVA/USACE PROJECTS GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.
3.3 CONTRACTORS TESTS
Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with UFGS GENERAL REQUIREMENTS sections. All testing shall be incorporated into the project schedule.
Contractor shall provide no less than 7 calendar days’ notice of testing.
The CxM will witness selected Contractor tests at the sole discretion of the CxM and CxA. The CxA and other Government representative(s) may choose to participate in some or all the testing procedures as observers.
Contractor tests shall be completed prior to scheduling Systems Functional Performance Testing.
3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The CxM will prepare final and detailed Systems Functional Performance Test procedures for review and approval by the Contracting Officer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The CxM will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00.01 DVA/USACE Projects GENERAL COMMISSIONING REQUIREMENTS, for additional details.
3.5 TRAINING OF VA PERSONNEL
Training of the VA operation and maintenance personnel is required in cooperation with the Contracting Officer, VA Resident Engineer, and CxM.
Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00.01 DVA/USACE PROJECTS GENERAL COMMISSIONING REQUIRMENTS. The instruction shall be scheduled in coordination with the Contracting Officer and VA Resident Engineer after submission and approval of formal training plans . Refer to Section 01 91 00.01 DVA/USACE PROJECTS GENERAL COMMISSIONING REQUIREMENTS and Division 21 Sections for additional Contractor training requirements.
-- End of Section --
SECTION 21 08 00.01 Page 4
SECTION TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
6/15
PART 1 GENERAL
1.1 DESCRIPTION
1.2 RELATED WORK
1.3 DESIGN CRITERIA
1.4 SUBMITTALS
1.5 SUBMITTAL INSTRUCTIONS
1.6 QUALITY ASSURANCE
1.7 REFERENCES
PART 2 PRODUCTS
2.1 PIPING & FITTINGS
2.2 VALVES
2.3 FIRE DEPARTMENT SIAMESE CONNECTION
2.4 SPRINKLERS
2.5 SPRINKLER CABINET
2.6 SPRINKLER SYSTEM SIGNAGE
2.7 SWITCHES
2.8 GAUGES
2.9 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
2.10 WALL, FLOOR AND CEILING PLATES
2.11 VALVE TAGS
PART 3 EXECUTION
3.1 INSTALLATION
3.2 INSPECTION AND TEST
3.3 INSTRUCTIONS
SECTION 21 13 13 Page 1
SECTION 21 13 13
6/15
WET-PIPE SPRINKLER SYSTEMS
PART 1 GENERAL
1.1 DESCRIPTION
a. Design, installation and testing shall be in accordance with NFPA 13 .
b. The design and installation of a hydraulically calculated automatic wet-pipe system complete and ready for operation, , including the penthouse, attic space, elevator machine rooms, elevator pits, .
c. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.
1.2 RELATED WORK
a. Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
b. Section 33 10 00 , WATER UTILITIES.
c. Section 07 84 00 , FIRESTOPPING.
d. Section 09 91 00 , PAINTING.
e. Section 22 05 23 , GENERAL-DUTY VALVES FOR PLUMBING PIPING.
f. Section 28 31 00 , FIRE DETECTION AND ALARM.
g. Section 21 30 13 , ELECTRIC-DRIVEN FIRE PUMPS.
1.3 DESIGN CRITERIA
a. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13 .
(1) Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method. Do not restrict design area reductions permitted for using quick response sprinklers throughout by the required use of standard response sprinklers in the areas identified in this section.
(2) Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13 . The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. Request clarification from the Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
(a) Light Hazard Occupancies: Patient care, treatment, and
SECTION 21 13 13 Page 2 customary access areas.
(b) Ordinary Hazard Group 1 Occupancies: Laboratories, Mechanical Equipment Rooms, Transformer Rooms, Electrical Switchgear Rooms, Electric Closets, and Repair Shops.
(c) Ordinary Hazard Group 2 Occupancies: Storage rooms, trash rooms, clean and soiled linen rooms, pharmacy and associated storage, laundry, kitchens, kitchen storage areas, retail stores, retail store storage rooms, storage areas, building management storage, boiler plants, energy centers, warehouse spaces, file storage areas for the entire area of the space up to (1500 square feet) and Supply Processing and Distribution (SPD).
(3) Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
(4) Water Supply: Base water supply on hydraulic analysis of new water tanks and fire pump.
(5) Zoning:
(a) For each sprinkler zone provide a control valve, flow switch, and a test and drain assembly with pressure gauge. For buildings greater than two stories, provide a check valve at each control valve.
(b) Sprinkler zones shall conform to the smoke barrier zones shown on the drawings.
(6) Provide seismic protection in accordance with NFPA 13 .
Contractor shall submit load calculations for sizing of sway bracing for systems that are required to be protected against damage from earthquakes.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Qualifications ;
SD-02 Shop Drawings
Drawings ;
SD-03 Product Data
Manufacturer’s Data Sheets ;
SD-05 Design Data
Calculation Sheets ;
SECTION 21 13 13 Page 3
Valve Charts ;
SD-11 Closeout Submittals
Final Document Submittals ;
1.5 SUBMITTAL INSTRUCTIONS
a. Submit as one package in accordance with Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.5(A) 1 through 1.5(A) 5 electronically in pdf format on a compact disc or as directed by the Contracting Officer. Submittals shall include, but not be limited to, the following:
(1) Qualifications :
(a) Provide a copy of the installing contractors fire sprinkler and state contractor’s license.
(b) Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering.
(c) Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
(2) Drawings : Submit detailed 1:100 1/8 inch scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA 13 . Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size.
Include a plan showing the piping to the water supply test location.
(3) Manufacturer’s Data Sheets : Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
(4) Calculation Sheets :
(a) Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and Calculations chapter of NFPA 13 .
SECTION 21 13 13 Page 4
(b) Submit calculations of loads for sizing of sway bracing in accordance with NFPA 13 .
(5) Valve Charts : Provide a valve chart that identifies the location of each control valve. Coordinate nomenclature and identification of control valves with Contracting Officer. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and Location.
(6) Final Document Submittals : Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:
(a) A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the Contracting Officer.
1. One full size (or size as directed by the Contracting Officer) printed copy.
2. One complete set in electronic pdf format.
3. One complete set in AutoCAD format or a format as directed by the Contracting Officer.
(b) Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA 13 .
Certificates shall be provided to document all parts of the installation.
(c) Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
(d) One paper copy of the Material and Testing Certificates and the Operations and Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the Contracting Officer.
(e) Provide one additional copy of the Operations and Maintenance Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the Contracting Officer.
SECTION 21 13 13 Page 5
1.6 QUALITY ASSURANCE
a. Installer Reliability: The installer shall possess a valid State of Connecticut contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
b. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.7 REFERENCES
a. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2025; TIA 24-1; TIA 24-2; TIA 24-3)
Standard for the Installation of Sprinkler Systems
NFPA 25 (2020; TIA 21-1) Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems
NFPA 101 (2024) Life Safety Code
NFPA 170 (2024; ERTA 1 2023) Standard for Fire Safety and Emergency Symbols
UL SOLUTIONS (UL)
UL Fire Prot Dir UL Product IQ (updated online) at https://productiq.ulprospector.com/en
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide https://www.approvalguide.com/
PART 2 PRODUCTS
2.1 PIPING & FITTINGS
a. Piping and fittings for private underground water mains shall be in accordance with NFPA 13 .
(1) Pipe and fittings from inside face of building (12 in.) above finished floor to a distance of approximately (5 ft.) outside building: Ductile Iron, flanged fittings and 316 stainless steel bolting.
b. Piping and fittings for sprinkler systems shall be in accordance with
NFPA 13 .
SECTION 21 13 13 Page 6
(1) Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
(2) Piping sizes 2 inches and smaller shall be black steel Schedule 40 with threaded end connections.
(3) Piping sizes (2 ½ inches) and larger shall be black steel Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
(4) Use nonferrous piping in MRI Scanning Rooms.
(5) Plastic piping shall not be permitted except for drain piping.
(6) Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside diameter or 1-inch and a maximum length of 6-feet.
2.2 VALVES
a. General:
(1) Valves shall be in accordance with NFPA 13 .
(2) Do not use quarter turn ball valves for 2 inch or larger drain valves.
b. Control Valve: The control valves shall be a listed indicating type.
Control valves shall be UL Fire Prot Dir or FM APP GUIDE for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI.
c. Check Valve: Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
d. Automatic Ball Drips: Cast brass 3/4 inch in-line automatic ball drip with both ends threaded with iron pipe threads.
e.
f.
2.3 FIRE DEPARTMENT SIAMESE CONNECTION
Brass, exterior fire department connection with brass escutcheon plate, and a minimum of two (2-1/2 inch) connections threaded to match those on the local fire protection service, with polished brass caps and chains.
Provide escutcheon with integral raised letters
2.4 SPRINKLERS
a. All sprinklers shall be FM approved quick response except “institutional” type sprinklers shall be permitted to be UL Listed quick response. Provide FM approved quick response sprinklers in all areas, except that standard response sprinklers shall be provided in freezers, refrigerators, elevator hoistways, elevator machine rooms, and generator rooms.
SECTION 21 13 13 Page 7
b. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
c. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the sprinkler head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
2.5 SPRINKLER CABINET
a. Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13 . Locate adjacent to the riser.
b. Provide a list of sprinklers installed in the property in the cabinet. The list shall include the following:
(1) Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
(2) General description of where each sprinkler is used.
(3) Quantity of each type present in the cabinet.
(4) Issue or revision date of list.
2.6 SPRINKLER SYSTEM SIGNAGE
Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
2.7 SWITCHES
a. OS&Y Valve Supervisory Switches shall be in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 1/2 inch conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
b. Water flow Alarm Switches: Mechanical, non-coded, non-accumulative retard and adjustable from 0 to 60 seconds minimum. Set flow switches at an initial setting between 20 and 30 seconds.
c.
d. Valve Supervisory Switches for Ball and Butterfly Valves: May be integral with the valve.
2.8 GAUGES
Provide gauges as required by NFPA 13 . Provide gauges where the normal pressure of the system is at the midrange of the gauge.
SECTION 21 13 13 Page 8
2.9 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13 .
2.10 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates.
2.11 VALVE TAGS
Engraved black filled numbers and letters not less than 1/2 inch high for number designation, and not less than 1/4 inch for service designation on 19 gage, (1-1/2 inches) round brass disc, attached with brass "S" hook, brass chain, or nylon twist tie.
PART 3 EXECUTION
3.1 INSTALLATION
a. Installation shall be accomplished by the licensed contractor.
Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
b. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Concealed piping in spaces that have finished ceilings. Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of (seven feet six inches).
Piping shall not obstruct the minimum means of egress clearances required by NFPA 101 . Pipe hangers, supports, and restraint of system piping, and seismic bracing shall be installed accordance with NFPA 13 .
Sprinkler piping shall not be used to support nonsystem components
c. Welding: Conform to the requirements and recommendations of NFPA 13 .
d. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13 . Pipe drains to discharge at safe points outside of the building or to sight cones attached to drains of adequate size to readily carry the full flow from each drain under maximum pressure. Do not provide a direct drain connection to sewer system or discharge into sinks. Install drips and drains where necessary and required by NFPA 13 . The drain piping shall not be restricted or reducedand shall be of the same diameter as the drain collector.
e. Supervisory Switches: Provide supervisory switches for sprinkler control valves.
f. Waterflow Alarm Switches: Install waterflow alarm switches and valves in stairwells or othereasily accessible locations.
g. Inspector's Test Connection: Install and supply in accordance with
SECTION 21 13 13 Page 9
NFPA 13 , locate in a secured area, and discharge to the exterior of the building.
h. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
i. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
j. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 2 inches nominally larger than the penetrating pipe for pipe sizes 1 inch to (3 ½ inches) and 4 inches nominally larger for penetrating pipe sizes 4 inches and larger.
k. Sleeves: Provide for pipes passing through masonry or concrete.
Provide space between the pipe and the sleeve in accordance with NFPA 13 . Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00 , FIRESTOPPING.
Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with Section 07 84 00 , FIRESTOPPING.
l. Where dry pendent sprinklers are used for freezers or similar spaces and they are connected to the wet pipe system, provide an EPDM boot around the dry pendent sprinkler on the heated side and securely seal to the pipe and freezer to prevent condensation from entering the freezer.
m. Provide pressure gauges at each water flow alarm switch location and at each main drain connection.
n. For each fire department connection, provide the symbolic sign given in NFPA 170 and locate (8 to 10 feet) above each connection location. Size the sign to (18 by 18 inches with the symbol being at least (14 by 14 inches).
o. Firestopping shall be provided for all penetrations of fire resistance rated construction. Firestopping shall comply with Section 07 84 00 , FIRESTOPPING.
p. MRI Suite: Provide no more than one penetration of the MRI shield enclosure.
q. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers. Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required. Painting shall comply with Section 09 91 00 , PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
r. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25 . Sprinkler system signage shall include, but not limited to, the following:
SECTION 21 13 13 Page 10
(1) Identification Signs:
(a) Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
(b) Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with C ontracting Officer. Where existing nomenclature does not exist, the Tag Identification shall include no less than the following:
(FP-B-F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone (if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire Protection, Building 500, First Floor East, Number 001.)
(2) Instruction/Information Signs:
(a) Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
(b) Provide signage indicating the number and location of low point drains.
(3) Hydraulic Placards:
(a) Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each alarm check valve.
s. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
t. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve occupied spaces. Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
a. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed.
Hydrostatically test system, including the fire department connections, as specified in NFPA 13 , in the presence of the Contracting Officers Representative (Contracting Officer) or his designated representative. Test and flush underground water line prior to performing these hydrostatic tests.
b. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13 , and when all necessary corrections have been accomplished, advise Contracting Officer to schedule a final inspection and test. Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all
SECTION 21 13 13 Page 11 instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the Contracting Officer.
SECTION 21 13 13 Page 12
SECTION TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
SECTION 21 30 13
ELECTRIC-DRIVEN, FIRE PUMPS
5/15
PART 1 GENERAL
1.1 DESCRIPTION
1.2 RELATED WORK
1.3 DESIGN CRITERIA
1.4 SUBMITTALS
1.5 SUBMITTAL INSTRUCTIONS
1.6 QUALITY ASSURANCE
1.7 REFERENCES
PART 2 PRODUCTS
2.1 GENERAL
2.2 PIPING & FITTINGS
2.3 VALVES
2.4 FIRE PUMP
2.5 FIRE PUMP CONTROLLER
2.6 AUTOMATIC TRANSFER SWITCH
2.7 PRESSURE SENSING LINE
2.8 JOCKEY PUMP
2.9 JOCKEY PUMP CONTROLLER
2.10 TEST HEADER
2.11 FLOW METER
2.12 IDENTIFICATION SIGNS
2.13 SWITCHES
2.14 GAUGES
2.15 PIPE HANGERS, SUPPORTS, AND RESTRAINT OF SYSTEM PIPING
2.16 WALL, FLOOR AND CEILING PLATES
2.17 PUMP BASE PLATE AND PAD
2.18 VALVE TAGS
PART 3 EXECUTION
3.1 INSTALLATION
3.2 INSPECTION AND TEST
3.3 INSTRUCTIONS
SECTION 21 30 13 Page 1
SECTION 21 30 13
5/15
ELECTRIC-DRIVEN, FIRE PUMPS
PART 1 GENERAL
1.1 DESCRIPTION
Installation of a new fire pump system with bypass and with an automatic transfer switch in accordance with NFPA 20 and NFPA 70 .
1.2 RELATED WORK
a. Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
b. Section 07 84 00 , FIRESTOPPING.
c. Section 09 90 00 , PAINTING.
d. Section 26 05 19 , LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.
e. Section 28 31 00 , FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
a. The design, materials, equipment, installation, inspection, and testing of the fire pump shall be in accordance with the required provisions of NFPA 20 and NFPA 70 .
b. Seismic Protection: Seismically brace all fire pump piping systems in accordance with NFPA 13 and NFPA 20 .
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Qualifications ;
SD-02 Shop Drawings
Drawings ;
SD-03 Product Data
Manufacturers Data Sheets ;
SD-05 Design Data
Calculation Sheets ;
Valve Charts ;
SECTION 21 30 13 Page 2
SD-07 Certificates
Factory Authorization Of Fire Pump Test Representative ;
SD-11 Closeout Submittals
Final Document Submittals ;
1.5 SUBMITTAL INSTRUCTIONS
a. Submit as one package in accordance with Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.5 (A) 1 through 1.5 (A) 5 electronically in pdf format on a compact disc or as directed by the Contracting Officer’s Representative (Contracting Officer). Submittals shall include, but not be limited to, the following:
(1) Qualifications :
(a) Provide a copy of the installing contractors fire sprinkler and state contractors license.
(b) Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering.
(c) Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic fire pump systems for the past 10 years.
(2) Drawings : Submit detailed 1/8 inch (1:100) scale (minimum) working drawings conforming to NFPA 20 . Provide drawings showing pump room configuration. Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. Provide wiring diagrams for connections to power, signal, and control wiring. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in area.
(3) Manufacturers Data Sheets : Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet. Data sheets shall be provided for, but not limited to, the
SECTION 21 30 13 Page 3 following:
(a) Pipe and fittings
(b) Valves
(c) Pressure Gauges
(d) Pipe Hangers and Supports
(e) Switches
(f) Fire Pump
(g) Jockey Pump
(h) Jockey Pump Controller
(i) Test Header
(j) Fire Pump Controller and Automatic Transfer Switch
(k) Certified Pump Curve
(l) Electric Motor
(m) Flow Meter
(4) Calculation Sheets : Submit seismic load calculations for sizing of sway bracing.
(5) Valve Charts : Provide a valve chart that identifies the location of each control valve. Coordinate nomenclature and identification of control valves with Contracting Officer. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID No., Valve Size, Service (control valve, test header valve, etc.), and Location.
(6) Factory Authorization of fire pump test representative : Two weeks prior to final inspection and testing, provide a copy of the necessary factory authorizations of the representative to be present at the acceptance testing. Authorizations shall include manufacturer’s representative for the fire pump, the fire pump controller and transfer switch in accordance with NFPA 20 requirements.
(7) Final Document Submittals : Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23 , SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
Submittals shall include, but not be limited to, the following:
(a) A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the Contracting Officer.
1. One full size (or size as directed by the Contracting Officer printed copy).
SECTION 21 30 13 Page 4
2. One complete set in electronic pdf format.
3. One complete set in AutoCAD format or a format as directed by the Contracting Officer.
(b) Centrifugal Fire Pump Acceptance Test Form and Certificates:
Upon completion of the fire pump system, including testing and flushing, provide a copy of a completed Centrifugal Fire Pump Acceptance Test Form and all…