This document provides details for a federal contract opportunity to repair two barracks buildings at the United States Military Academy at West Point. The contract involves repairing Building 740 at Lee Barracks and Building 738 at Sherman Barracks, including interior and exterior renovations, replacement of mechanical, electrical and plumbing systems, abatement of hazardous materials, and repair of supporting facilities.
The project for Building 740 at Lee Barracks includes replacing substandard design elements, upgrading life and safety systems, and improving energy efficiency. It will renovate approximately 73,698 square feet to house 138 cadets. Renovations will update spaces for laundry, storage, day rooms, offices and barracks rooms to current standards. The project also includes adding a cadet health clinic. Repairs for Building 738 at Sherman Barracks under the optional scope will renovate approximately 110,834 square feet to house 321 cadets within 152 rooms. Both projects will comply with energy efficiency requirements and are designed for LEED Silver certification. The contract value is estimated between $100-200 million with a performance period of approximately 1034 days. The solicitation will be posted on August 6, 2021 on SAM.gov.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lee and Sherman Barracks Upgrades Project September 8, 2021 US Military Academy, West Point, NY Issued for Amendment
SECTION 08 11 16
ALUMINUM DOORS AND FRAMES
05/ 17, CHG 2: 11/ 18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)
AAMA 2605 (2020) Voluntary Specification, Performance Requirements and Test Procedures for Superior Performing Organic Coatings on Aluminum Extrusions and Panels
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 - IP (2013) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM B209 (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
ASTM B209M (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate (Metric)
ASTM B221 (2014) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
ASTM B221M (2013) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric)
ASTM E283 (2019) Standard Test Method for Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen
ASTM E331 (2000; R 2016) Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference
SECTION 08 11 16 Page 1
NATIONAL FENESTRATION RATING COUNCIL (NFRC)
NFRC 100 (2017) Procedure for Determining Fenestration Product U-Factors
NFRC 200 (2017) Procedure for Determining Fenestration Product Solar Heat Gain Coefficient and Visible Transmittance at Normal Incidence
1.2 PERFORMANCE REQUIREMENTS
1.2.1 Structural Calculations
1.2.2 Air Infiltration
When tested in accordance with ASTM E283, air infiltration per door leaf cannot exceed 0.6 cubic feet per minute per square foot of fixed area at a test pressure of 6.24 pounds per square foot .
1.2.3 Water Penetration
When tested in accordance with ASTM E331, there can be no water penetration at a pressure of 2.86 pounds per square foot of fixed area.
1.2.4 Thermal Transmittance, Solar Heat Gain, Visible Light Transmittance
Provide products bearing NFRC Project Label Certificates for Fenestration verifying compliance with requirements for each assembly indicated. An NFRC Bid Report, or approved equal, for field assembled exterior doors may be submitted in lieu of Project Label Certificates for Fenestration if such reports are created in accordance with NFRC CAMP procedures and are provided by the manufacturer. Such alternate reports may be submitted with shop drawings, however, NFRC validated Project Label Certificates for Fenestration are required as a Closeout Submittal. Contact NFRC for information on NFRC 100 and NFRC 200 Compliance and Monitoring Program (CAMP) rating requirements:
http://www.nfrc.org/industry/certification/compliance-and-monitoring-program-camp/
1.2.4.1 U-Factor
Provide exterior glazed assemblies, including aluminum entrances doors with greater than 50 percent glazed area, certified by the NFRC as having a whole window U-factor of 0.42 or less as determined in accordance with ASHRAE 90.1 - IP and as verified in accordance with NFRC 100.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
For Each Type of Door and Frame Assembly ; G,AE
SECTION 08 11 16 Page 2
SD-03 Product Data
For Each Type of Door and Frame Assembly ; G,AE
Recycled Content of Aluminum Material ; S
SD-04 Samples
Finish Samples ; G,AE
SD-06 Test Reports
Air Infiltration ; G, RO
Water Penetration ; G, RO
SD-07 Certificates
NFRC Project Label Certificates for Fenestration ; G, RO
Colors And Finishes ; G, RO
SD-08 Manufacturer's Instructions
Installation of Each Type of Door and Frame Assembly ; G, RO
SD-10 Operation and Maintenance Data
Adjustments, Cleaning, and Maintenance ; G, RO
SD-11 Closeout Submittals
NFRC Project Label Certificates for Fenestration ; G, RO
1.4 DELIVERY, STORAGE, AND HANDLING
Inspect materials delivered to the site for damage. Unload and store with minimum handling. Provide storage space in dry location with adequate ventilation, free from dust or water, and easily accessible for inspection and handling. Stack materials on non-absorptive strips or wood platforms. Do not cover doors and frames with tarps, polyethylene film, or similar coverings. Protect finished surfaces during shipping and handling using manufacturer's standard method. Do not apply coatings or lacquers to surfaces to which caulking and glazing compounds must adhere.
1.5 QUALITY CONTROL
1.5.1 Shop Drawing
Indicate elevations and sections for each type of door and frame assembly .
Show sizes and details of each assembly, frame construction,subframe attachment, thickness and gages of metal, details of door and frame construction, proposed method(s) of anchorage, glazing details, provisions for an location of hardware, mullion details, method and materials for flashing and weatherstripping, miscellaneous trim, installation details, and other related items necessary for a complete representation of all components. A qualified blast engineer must perform testing or calculations for door system design resistance to specified blast loads.
SECTION 08 11 16 Page 3
1.5.2 Finish Samples
Submit two color charts and two finish sample chips from manufacturer's standard color and finish options for each type of finish indicated.
1.5.3 Operation and Maintenance Data
Submit detailed instructions for installation, adjustments, cleaning, and maintenance of each type of assembly indicated.
PART 2 PRODUCTS
2.1 DOORS AND FRAMES
Provide swing-type aluminum doors and frames of size, design, and location indicated. Provide doors complete with frames, framing members, subframes, transoms, adjoining side lites, trim, and accessories.
Coordinate side lites, window walls, adjacent curtainwall with Section
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS.
2.2 MATERIALS
2.2.1 Anchors
Stainless steel.
2.2.2 Weatherstripping
Continuous wool pile, silicone treated, or type recommended by door manufacturer.
2.2.3 Aluminum Alloy for Doors and Frames
ASTM B221M, ASTM B221, Alloy 6063-T5 for extrusions. ASTM B209M, ASTM B209, alloy and temper best suited for aluminum sheets and strips. Provide aluminum materials that include a minimum of 30 percent recycled content.
Provide data indicating percentage of recycled content of aluminum material .
2.2.4 Fasteners
Hard aluminum or stainless steel.
2.2.5 Structural Steel
ASTM A36/A36M.
2.2.6 Aluminum Paint
Aluminum door manufacturer's standard aluminum paint.
2.3 FABRICATION
2.3.1 Aluminum Frames
Extruded aluminum shapes with contours approximately as indicated.
Provide removable glass stops and glazing beads for frames accommodating fixed glass. Use countersunk stainless steel Phillips screws for exposed fastenings, and space not more than 12 inches on center. Mill joints in frame members to a hairline fit, reinforce, and secure mechanically.
SECTION 08 11 16 Page 4
2.3.2 Aluminum Doors
Of type, size, and design indicated and minimum 1-3/4 inch thick. minimum wall thickness, 0.125 inch , except beads and trim, 0.050 inch . Door sizes shown are nominal; include standard clearances as follows: 0.093 inch at hinge and lock stiles, 0.125 inch between meeting stiles, 0.125 inch at top rails, 0.187 inch between bottom and threshold, and 0.687 inch between bottom and floor.
2.3.2.1 Full Glazed Stile and Rail Doors
Provide doors with narrow stiles and rails as indicated. Fabricate from extruded aluminum hollow seamless tubes or from a combination of open-shaped members interlocked or welded together. Fasten top and bottom rail together by means of welding or by 3/8 or 1/2 inch diameter cadmium-plated tensioned steel tie rods. Provide an adjustable mechanism of jack screws or other methods in the top rail to allow for minor clearance adjustments after installation.
2.3.3 Welding and Fastening
Where possible, locate welds on unexposed surfaces. Dress welds on exposed surfaces smoothly. Select welding rods, filler wire, and flux to produce a uniform texture and color in finished work. Remove flux and spatter from surfaces immediately after welding. Exposed screws or bolts will be permitted only in inconspicuous locations, and must have countersunk heads. Weld concealed reinforcements for hardware in place.
2.3.4 Weatherstripping
Provide on stiles and rails of exterior doors. Fit into slots which are integral with doors or frames. Weatherstripping must be replaceable without special tools, and adjustable at meeting rails of pairs of doors.
During installation, verify doors swing freely and close positively.
Refer to paragraph AIR INFILTRATION for air leakage requirements and testing.
2.3.5 Anchors
On the backs of subframes, provide anchors of the sizes and shapes indicated for securing subframes to adjacent construction. Anchor transom bars at ends and mullions at head and sill. Place anchors near top and bottom of each jamb and at intermediate points not more than 25 inch apart.
2.3.6 Provisions for Hardware
Coordinate with Section 08 71 00 DOOR HARDWARE. Deliver hardware templates and hardware (except field-applied hardware) to the door manufacturer for use in fabrication of aluminum doors and frames. Cut, reinforce, drill, and tap doors and frames at the factory to receive template hardware. Provide doors to receive surface-applied hardware, except push plates, kick plates, and mop plates, with reinforcing only;
drill and tap in the field. Provide hardware reinforcements of stainless steel or steel with hot-dipped galvanized finish, and secure with stainless steel screws.
SECTION 08 11 16 Page 5
2.3.7 Provisions for Glazing
Provide glazing beads with vinyl insert glazing gaskets. Design glazing beads to receive thickness indicated for each glazed assembly. Coordinate requirements with Section 08 81 00 GLAZING.
2.3.8 Finishes
Provide exposed aluminum surfaces with factory finish organic coating to match aluminum storefront system assembly finish the door is within.
2.3.8.1 Organic Coating
Clean and prime exposed aluminum surfaces. Exposed aluminum color to be selected to approximate the color of the wood door to be replaced. Color may be selected from manufacturer's standard range or may be custom as required to achieve the appropriate color and finish. Submit colors and finishes for approval by COR and Cultural Resources Officer for USMA.
Provide corrosion resistant over dried Kynar 500, 70 percent PVDF fluoropolymer, three-coat superior-performance organic finish in accordance with AAMA 2605 finish.
PART 3 EXECUTION
3.1 INSTALLATION
Plumb, square, level, and align frames and framing members to receive doors, transoms, adjoining side lites, and, adjoining window walls. Anchor frames to adjacent construction as indicated and in accordance with manufacturer's printed instructions and the approved shop drawings.
Install anchorage that complies with applicable structural requirements.
Anchor bottom of each frame to rough floor construction with 3/32 inch thick minimum stainless steel angle clips secured to back of each jamb and to floor construction; use stainless steel bolts and expansion rivets for fastening clip anchors. Hang doors to produce clearances specified in paragraph ALUMINUM DOORS. After erection and glazing, adjust doors and hardware to operate properly.
3.2 PROTECTION FROM DISSIMILAR MATERIALS
3.2.1 Dissimilar Metals
Where aluminum surfaces come in contact with metals other than stainless steel, zinc, or small areas of white bronze, protect from direct contact to dissimilar metals.
3.2.1.1 Protection
Provide one of the following systems to protect surfaces in contact with dissimilar metals:
a. Paint the dissimilar metal with one coat of heavy-bodied bituminous paint.
b. Apply elastomeric sealant between aluminum and dissimilar metals in accordance with Section 07 92 00 JOINT SEALANTS.
c. Paint dissimilar metals with one coat of primer and one coat of aluminum paint.
SECTION 08 11 16 Page 6
d. Use a non-absorptive tape or gasket in permanently dry locations.
3.2.2 Drainage from Dissimilar Metals
In locations where drainage from dissimilar metals has direct contact with aluminum, provide protective paint to prevent aluminum discoloration.
3.2.3 Masonry and Concrete
Provide aluminum surfaces in contact with mortar, concrete, or other masonry materials with one coat of heavy-bodied bituminous paint.
3.2.4 Wood or Other Absorptive Materials
Provide aluminum surfaces in contact with absorptive materials subject to frequent moisture, and aluminum surfaces in contact with treated wood, with two coats of aluminum paint or one coat of heavy-bodied bituminous paint. In lieu of painting aluminum, paint the wood or other absorptive surface with two coats of aluminum paint and seal joints with elastomeric sealant.
3.3 SEALING AROUND ASSEMBLIES
Seal all penetrations of the air barrier by sealing around door openings as necessary to achieve compliance with air leakage requirements indicated in the air barrier sections of the specifications. Flash all doors with corrosion resistant flashing to prevent water intrusion.
3.4 CLEANING
Upon completion of installation, clean door and frame surfaces in accordance with door manufacturer's written recommended procedure. Do not use abrasive, caustic, or acid cleaning agents.
3.5 PROTECTION
Protect doors and frames from damage and from contamination by other materials such as cement mortar. Prior to completion and acceptance of the work, restore damaged doors and frames to original condition, or replace with new ones.
-- End of Section --
SECTION 08 11 16 Page 7
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 08 11 16 Page 8
SECTION 07 81 00
SPRAY-APPLIED FIREPROOFING
02/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASSOCIATION OF THE WALL AND CEILING INDUSTRY (AWCI)
AWCI TM 12-A (1997; 3rd Ed) Standard Practice for the Testing and Inspection of Field Applied Sprayed Fire-Resistive Materials; An Annotated Guide
ASTM INTERNATIONAL (ASTM)
ASTM E1042 (2002; R 2014) Acoustically Absorptive Materials Applied by Trowel or Spray
ASTM E119 (2020) Standard Test Methods for Fire Tests of Building Construction and Materials
ASTM E605/E605M (1993; R 2015; E 2015) Standard Test Methods for Thickness and Density of Sprayed Fire-Resistive Material (SFRM) Applied to Structural Members
ASTM E736 (2000; R 2011) Cohesion/Adhesion of Sprayed Fire-Resistive Materials Applied to Structural Members
ASTM E759/E759M (1992; R 2015; E 2015) Standard Test Method for Effect of Deflection on Sprayed Fire-Resistive Material Applied to Structural Members
ASTM E760/E760M (1992; R 2015; E 2015) Standard Test Method for Effect of Impact on Bonding of Sprayed Fire-Resistive Material Applied to Structural Members
ASTM E761/E761M (1992; R 2015; E 2015) Standard Test Method for Compressive Strength of Sprayed Fire-Resistive Material Applied to Structural Members
ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials
SECTION 07 81 00 Page 1
ASTM E859/E859M (1993; R 2015; E 2015) Standard Test Method for Air Erosion of Sprayed Fire-Resistive Materials (SFRMs) Applied to Structural Members
ASTM E937/E937M (1993; R 2015; E 2015) Standard Test Method for Corrosion of Steel by Sprayed Fire-Resistive Material (SFRM) Applied to Structural Members
ASTM G21 (2015) Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi
ICC EVALUATION SERVICE, INC. (ICC-ES)
ICC-ES AC23 (2012; R 2016) Acceptance Criteria for Sprayed Fire-resistant Materials (SFRMs), Intumescent Fire-resistant Coatings and Mastic Fire-resistant Coatings Used to Protect Structural Steel Members
NSF INTERNATIONAL (NSF)
NSF/ANSI 336 (2018) Sustainability Assessment for Commercial Furnishings Fabric
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED BDC Ref Guide (2013) USGBC LEED Reference Guide for Building Design and Construction, v4
UNDERWRITERS LABORATORIES (UL)
UL 263 (2011; Reprint Mar 2018) Fire Tests of Building Construction and Materials
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SYSTEM DESCRIPTION
1.2.1 General Requirements
Protect all structural steel and steel roof decks with spray-applied fireproofing to a fire resistance hour-rating as indicated below, unless otherwise indicated.
1.2.2 Fire Resistance Rating
Fire resistance ratings shall be in accordance with the fire rated assemblies listed in UL Fire Resistance . Proposed materials not listed in UL Fire Resistance shall have fire resistance ratings at least equal to the UL Fire Resistance ratings as determined by an approved independent testing laboratory, based on tests specified in UL 263 or ASTM E119.
Submit reports and test records, attesting that the fireproofing material conforms to the specified requirements. Each test report shall conform to the report requirements specified by the test method. For the underside of the decking use metal lath installed prior to the fireproofing material or Rigid Board Fireproofing Material as outlined in the UL Fire Resistance
SECTION 07 81 00 Page 2
Directory Volume 1. Apply fireproofing to structural steel members, with the following hourly fire resistance rating and in accordance with the following UL design or approved equivalent. Use unrestrained fire resistance ratings, unless the architect/engineer has specified that the degree of thermal restraint of the construction meets or exceeds the degree of thermal restraint of the tested assembly. Performance tests shall be in accordance with ASTM E119.
Fire Rating Schedule
Element Hourly Rating UL Design Reference
Columns supporting roof 2 Hr. UL X771 & X772
Roof decks 2 Hr. UL P701
1.2.3 Evaluation Reports - ICC-ES Reports
Materials shall be evaluated in accordance with ICC-ES AC23 . ICC-ES Reports shall be included as part of the Submittals below. The reports will identify the product as code compliant and having met the physical performance requirements outlined in paragraphs "Dry Density and Cohesion/Adhesion" through "Air Erosion".
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Fireproofing Material ; G, RO, AE
SD-04 Samples
Spray-Applied Fireproofing ; G, RO, AE
SD-06 Test Reports
Fire Resistance Rating ; G, RO, AE Field Tests ; G, RO Evaluation Reports ; G, RO
SD-07 Certificates
Installer Qualifications ; G, RO Surface Preparation Report ; G, RO Manufacturer's Inspection Report ; G, RO
1.3.1 Sustainable Design Submittals
1. Building Product Disclosure and Optimization – Environmental Product
SECTION 07 81 00 Page 3
Declarations (EPD) – MR Credit 2, Option 1:
a. Submit product EPD or life-cycle assessment; refer to Division 01 33 29 and the LEED BDC Ref Guide v4 for full requirements. The Life-cycle assessment and EPDs must conform to one of the disclosure types listed in below, in descending order of preference:
1. Products with a publicly available life-cycle assessment conforming to ISO 14044 that have at least a cradle to gate scope.
2. Product-specific Type III EPD -- Internally Reviewed. Products with an internally critically reviewed LCA in accordance with ISO 14071.
3. Industry-wide Type III EPD -- Products with third-party certification (Type III), including external verification, in which the manufacturer is explicitly recognized as a participant by the program operator.
b. EPDs which conform to ISO 14025 and EN 15804 or ISO 21930 and have at least a cradle to gate scope.
1. Product-specific Type III EPD -- Products with third-party certification (Type III), including external verification and external critical review in which the manufacturer is explicitly recognized as the participant by the program operator.
c. USGBC-approved program – Products that comply with other USGBC approved EPD frameworks.
d. Provide LEED Submittal Cover Sheet in accordance with Section 01 33 29.
2. Building Product Disclosure and Optimization, Sourcing of Raw Materials: Option 2, Leadership Extraction Practices
a. Submit description of salvaged, refurbished or reused products.
b. Submit manufacturer’s data sheet or statement of pre-consumer and post-consumer recycled content. Indicate the percentage of the dollar value of the recycled content compared to the total dollar value of the product or assembly containing the product.
c. Permanently installed, non-recycled wood and wood-based materials should be certified in accordance with Forest Stewardship Council Guidelines. This includes wood permanently installed in the project wood products. Submit all FSC product certification information including required Chain-of-Custody certificates and invoices tracking FSC purchase. Refer to Division 01 33 29 and the LEED BDC Ref Guide v4 for full requirements.
d. Provide LEED Submittal Cover Sheet in accordance with Section 01 33 29.
3. Building Product Disclosure and Optimization, Material Ingredients:
Option 1, Material Ingredient Reporting.
a. Submit Material Ingredient Reports for manufacturers that use any of the following programs to demonstrate the chemical inventory of the product to at least 0.1% (1000 ppm), which meet one of the following disclosure criteria:
SECTION 07 81 00 Page 4
1. One of the following product attributes: Health Product Declaration; Cradle to Cradle certifications; Declare product labels; Living Product Challenge; ANSI/BIFMA e3 Furniture Sustainability Standard; Product Lens Certification; Facts –
NSF/ANSI 336 .
2. Manufacturer Inventory.
3. A publicly available inventory of all ingredients identified by name and Chemical Abstract Service Registration Number (CASRN) and/or European Community Number (EC Number).
4. Materials defined as trade secret or intellectual property may withhold the name and/or CASRN/EC Number but must disclose ingredient/chemical role, amount and hazard score/class using either:
5. Greenscreen List Translator (LT) score and/or Full GreenScreen Benchmark (BM)
6. The Globally Harmonized System of Classification and Labeling of Chemicals rev.6 (2015) (GHS)
7. Refer to https://www.usgbc.org/node/2616399?return=/credits/new-construction/v4/material-%26amp%3B-resources for current list of USGBC-approved compliance programs.
b. Refer to Division 01 33 29 and the LEED BDC Ref Guide v4 for full requirements.
c. Provide LEED Materials Content Form in accordance with Section 01 33 29.
4. Low-Emitting Materials - Interior paints and coatings applied on site:
a. Meet the VOC emissions evaluation and the VOC content evaluation. The paints and coatings product category include all interior paints and coatings applied on site. Refer to Division 01 33 29 and the LEED BDC Ref Guide v4.1 for full VOC content and emissions requirements.
1. For CDPH version compliance information, refer to LEED interpretation #ID 10495 “LEM for v4 projects”:
https://www.usgbc.org/leedaddenda/10495
b. Provide LEED Submittal Cover Sheet in accordance with Section 01 33 29.
5. Low-Emitting Materials - Insulation:
a. Meet the VOC emissions evaluation for all insulation products. The insulation material category includes all thermal and acoustic boards, batts, rolls, blankets, sound attenuation fire blankets, foamed-in place, loose-fill, blown, and sprayed insulation. Insulation for HVAC ducts and plumbing piping are excluded. Refer to Division 01 33 29 and the LEED BDC Ref Guide v4.1 for full VOC content and emissions requirements.
b. Provide LEED Submittal Cover Sheet in accordance with Section 01 33 29.
SECTION 07 81 00 Page 5
1.4 QUALITY ASSURANCE
1.4.1 Installer Qualifications
Engage an experienced installer that is certified, licensed, or otherwise qualified by the spray-on fireproofing manufacturer as having the necessary experience, staff, and training to install the manufacturer's products in accordance with specified requirements. Submit manufacturer's certification that each listed installer is qualified and trained to install the specified fireproofing. Show evidence that each fireproofing installer has had a minimum of 3 years experience in installing the specified type of fireproofing. Each installer of fireproofing material shall be trained, have a minimum of 3 years experience and a minimum of three installations using fireproofing of the type specified. A manufacturer's willingness to sell its products to the Contractor or installer does not infer qualification of the buyer.
1.4.2 Pre-Installation Meeting
Hold a meeting with the installer, field testing agency, the manufacturer, subcontractors (whose employees come into contact with the fireproofing), and the Contracting Officer prior to the installation of any fireproofing material to review the substrates for acceptability, method of application, applied thickness, patching, repair, inspection and testing procedures.
1.5 DELIVERY, STORAGE, AND HANDLING
Deliver packaged material in the original unopened containers, marked to show the brand name, the manufacturer, and the UL markings. Keep fireproofing material dry until ready to be used, and store off the ground, under cover and away from damp surfaces. Damaged or opened containers will be rejected. Apply material with shelf-life prior to expiration of the shelf-life.
1.6 PROJECT/SITE CONDITIONS
1.6.1 Temperature
Maintain substrate and ambient air temperatures above 40 degrees F during application and for 24 hours before and after application. Maintain relative humidity within the limits recommended by the fireproofing manufacturer.
1.6.2 Ventilation
Provide adequate ventilation to properly dry the fireproofing after application. In enclosed areas, provide a minimum of 4 air exchanges per hour by forced air circulation.
PART 2 PRODUCTS
2.1 SPRAY-APPLIED FIREPROOFING
Provide spray-applied fireproofing material, including sealer, conforming to ASTM E1042, Class (a), Category A, either Type I or Type II, except that the dust removed shall not exceed 0.0025 gram per square foot of fireproofing material applied as specified in the project. Only products
SECTION 07 81 00 Page 6 that have been evaluated at UL and bear and "investigated for exterior use" approval are allowed in waterfront areas where the fireproofing may be directly exposed to a natural body of water. Material shall be asbestos free, and shall resist fungus for a period of 28 days when tested in accordance with ASTM G21. Material shall have a flame spread of 25 or less and a smoke developed rating of 50 or less when tested in accordance with ASTM E84. Submit one sample panel, 18 inches square, for each specified type of fireproofing. Also, a designated sample area of not less than 100 square feet shall be prepared. Sample area shall be representative of typical installation of fireproofing including metal decks, beams, columns and attachments. Equipment, materials and procedures used in the sample area shall be the same as, or representative of, that to be used in the work. The sample area shall be approved prior to proceeding with fireproofing work in any other area. The approved sample area shall be used as a reference standard for applied fireproofing material. Sample area shall remain in place and open to observation until all spray-applied fireproofing is completed and accepted, at which time it may become part of the work.
2.1.1 Dry Density and Cohesion/Adhesion
Fireproofing shall have a minimum ASTM E605/E605M dry density and ASTM E736 cohesion/adhesion properties as follows:
2.1.1.1 Concealed Structural Components
Fireproofing for structural components concealed above the ceiling, or within a wall, chase, or furred space, shall have a minimum applied dry density of 15 pounds per cubic foot and a cohesion/adhesion strength of 200 psf .
2.1.1.2 Exposed Structural Components
Fireproofing for exposed structural components, except where otherwise specified or indicated, shall have a minimum applied dry density of 22 pounds per cubic foot and a cohesion/adhesion strength of 434 psf .
2.1.2 Deflection
Spray-applied fireproofing shall not crack, spall, or delaminate when backing to which it is applied is subject to downward deflection 1/120 of 10 foot clear span, when tested in accordance with ASTM E759/E759M .
2.1.3 Bond-Impact
Spray-applied fireproofing material shall not crack, spall or delaminate when tested in accordance with ASTM E760/E760M .
2.1.4 Compressive Strength
The minimum compressive strength shall be 1000 psf when tested in accordance with ASTM E761/E761M .
2.1.5 Corrosion
Spray-applied fireproofing material shall not contribute to corrosion of test panels when tested as specified in ASTM E937/E937M .
SECTION 07 81 00 Page 7
2.1.6 Air Erosion
Dust removal shall not exceed 0.025 gram per square foot when tested in accordance with ASTM E859/E859M .
2.2 SEALER
Sealer shall be the type approved by the manufacturer of the fireproofing material, shall be fungus resistant, shall have a flame spread of 25 or less and a smoke developed rating of 50 or less when tested in accordance with ASTM E84, and shall be white color.
2.3 WATER
Water used for material mixing and surface preparation shall be potable.
2.4 SPRAY-APPLIED INTUMESCENT EPOXY COATING SYSTEM
All new structural steel tube columns installed on the Lee Barracks floors sub-basement, and basement, are to receive intumescent epoxy coating. All foam plastic closed cell insulation exposed to the interior of the building without thermal barrier tested per NFPA 275 must also be coated with spray applied Intumescent epoxy Coating System.
Provide a two-component epoxy based intumescent fire protective coating that meets the following requirements.
a. On curing it forms a flexible and tough epoxy barrier which transforms into a ceramic-like, insulating char to provide thermal protection of the substrate in the event of a fire.
b. The coating system includes the manufacturer's required surface preparation, primer, and fire protective layer, and topcoat.
c. The coating system protects the substrate from corrosion and retain its fire protection properties under aggressive chemical environments.
d. Resistant to solvents, acids, alkalis, salts and abrasion while retaining its fire protective properties.
Provide a system that exhibits the following properties:
2.4.1 Percent Solids by Weight
100 percent
2.4.2 In Service Temperature Restrictions
Up to 150 degrees F
2.4.3 Application Method
Air spray or specialized plural component airless equipment approved by the manufacture. Troweling can be used for small areas or touch-up work.
2.4.4 Drying Time
Approximately 24 hours to achieve a Shore D hardness of 25.
SECTION 07 81 00 Page 8
2.4.5 Shelf Life
Minimum shelf life under proper storage condition is 1 Year from date of manufacture.
2.4.6 Pot Life
Approximately 40 minutes at 77 degrees F and 50 percent relative humidity.
Pot life is not a factor when using specialized plural component airless spray equipment.
2.4.7 Flash Point
Greater than 212 degrees F Pensky-Martens for each component.
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Thoroughly clean surfaces to be fireproofed of dirt, grease, oil, paint, primers, loose rust, rolling lubricant, mill scale or other contaminants that will interfere with the proper bonding of the sprayed fireproofing to the substrate. Test painted/primed steel substrates in accordance with ASTM E736, with specified sprayed fireproofing material, to provide the required fire-resistance rating; painted or primed steel surfaces may require a fireproofing bond test to determine if the paint formulation will impair proper adhesion. Certify the acceptability of surfaces to receive sprayed-applied fireproofing by inspection and submit a Surface Preparation Report accordingly. The statement shall list the structural members and the areas that have been inspected and certified. Overhead areas to be fireproofed shall be cleared of all obstructions interfering with the uniform application of the spray-applied fireproofing. Hardware such as support sleeves, inserts, clips, hanger attachment devices and the like shall be installed prior to the application of the fireproofing.
Condition of the surfaces shall be acceptable to the manufacturer prior to application of spray-applied fireproofing. Applications listed for use on primed surfaces shall be in accordance with the manufacturer's recommendations and standards, and detailed in submittal item SD-03 Product Data.
3.2 PROTECTION
Cover surfaces not to receive spray-applied fireproofing to prevent contamination by splatter, rebound and overspray. Cover exterior openings in areas to receive spray-applied fireproofing prior to and during application of fireproofing with tarpaulins or other approved material.
Clean surfaces not to receive fireproofing of fireproofing and sealer.
3.3 FIREPROOFING MATERIAL
Mix fireproofing material in accordance with the manufacturer's recommendations. Submit data identifying performance characteristics of fireproofing material. Data includes recommended application requirements and indicate thickness of fireproofing to be applied to achieve each required fire rating.
SECTION 07 81 00 Page 9
3.4 APPLICATION
3.4.1 Sequence
Prior to application of fireproofing on each floor, the manufacturer shall inspect and approve application equipment, water supply and pressure, and the application procedures. If fireproofing is required to be applied to underside of steel roof deck and steel floor assemblies, it shall be done only after respective roof or floor construction is complete. No roof or floor traffic shall be allowed during application. Fireproofing material shall be applied prior to the installation of ductwork, piping and conduits which would interfere with uniform application of the fireproofing.
3.4.2 Application Technique
Maintain water pressure and volume to manufacturer's recommendations throughout the fireproofing application. Apply fireproofing material to the thickness and density established for the specified fire resistance rating, in accordance with the procedure recommended by the manufacturer, and to a uniform density and texture. Do not tamp fireproofing material to achieve the desired density.
3.4.3 Sealer Application
If sealer is required by the product used, apply it after field testing has been conducted and after corrective measures and repairs, if required, have been completed.
3.4.4 Applied Thickness
The minimum average thickness shall be no less than 0.375 inches .
Thicknesses shall not be less than required to achieve designated fire resistance ratings. If the specified thickness is greater than or equal to 1 inch , any individual measurement shall not be less than the specified thickness minus 0.25 inches . If the specified thickness is less than 1 inch , any individual measurement shall not be less than the specified thickness minus 25 percent.
3.4.5 Application of Spray-Applied Intumescent Epoxy Coating System
Prepare surfaces and apply the spray-applied Intumescent epoxy coating system in accordance with the manufacturer's written recommendations.
3.5 MANUFACTURER'S SERVICES
3.5.1 General
The manufacturer, or its representative, shall be onsite prior to, periodically during, and at completion of the application, to provide the specified inspections and certifications; and to ensure that preparations are adequate and that the material is applied according to manufacturer's recommendations and the contract requirements.
3.5.2 Manufacturer's Inspection
The manufacturer shall inspect the fireproofing work after the work is completed on each floor or area, including testing, repair and clean-up, and shall certify that the work complies with the manufacturer's criteria
SECTION 07 81 00 Page 10 and recommendations. Before the sprayed material is covered, and after all of the fireproofing work is completed, including repair, testing, and clean-up; and after mechanical, electrical and other work in contact with fireproofing material has been completed, the manufacturer shall re-inspect the work and certify that the entire project complies with the manufacturer's criteria and recommendations. Obtain and submit the Manufacturer's Inspection Report and certifications of approval stating that the spray-applied fireproofing in the entire project complies with the manufacturer's criteria and recommendations.
3.6 FIELD TESTS
The applied fireproofing shall be tested by an approved independent testing laboratory to be selected by the A/E and paid for by the Contractor. Submit test reports documenting results of tests on the applied material in the project. Report shall include defects identified, repair procedures, and results of the retests when required. Perform the tests in approved locations: for density in accordance with ASTM E736, cohesion/adhesion in accordance with ASTM E736, and for thickness in accordance with ASTM E605/E605M . Determine densities in accordance with ASTM E605/E605M or Appendix A, "Alternate Method for Density Determination" of AWCI TM 12-A . Take density determinations at the flat portion of deck, beam bottom flange, beam web, column, and an equivalent area from the top of the lower beam flange. Areas showing a density less than specified will be rejected. A test sample shall be located every 10,000 square feet of floor area or two for each floor, whichever produces the greatest number of test areas. Any area showing less than minimum requirements shall be corrected. Proposed corrective measures, in writing, shall be approved before starting the corrective action.
Corrected work shall be retested.
3.6.1 Structural Components
Test each structural component type at floor and roof decks, beams, columns, joists, and trusses. Minimum average thickness shall be as required by UL Fire Resistance . Density and cohesion/adhesion shall be as specified.
3.6.2 Repair
Additional fireproofing material may be added to provide proper thickness. Correct rejected areas of fireproofing to meet specified requirements by adding fireproofing material to provide the proper thickness, or by removing defects and respraying with new fireproofing material. Use same type of fireproofing material for repairs as originally applied or use patching materials recommended by the manufacturer. Retest and reinspect repaired areas. Apply fireproofing material to voids or damaged areas by hand-trowel, or by respraying.
3.6.3 Visual Inspections
Inspections shall be made by the certified independent laboratory prior to closure of concealed areas. These inspections may be phased, but shall not occur less than 5 working days prior to the enclosure of the fireproofing. Sprayed areas shall receive a final inspection.
Fireproofed surfaces shall be inspected after mechanical, electrical, and other work in contact with fireproofing material has been completed and before sprayed material is covered. Any locations missing fireproofing shall be patched in accordance with the manufacturer's requirements.
SECTION 07 81 00 Page 11
3.6.4 Patching
Patch and repair damaged fireproofing. The patching material shall be the same as that specified for that area.
3.7 CLEANUP
Thoroughly clean surfaces not indicated to receive fireproofing of sprayed material within a 24 hour period after application.
-- End of Section --
SECTION 07 81 00 Page 12
SECTION 33 63 13
EXTERIOR UNDERGROUND STEAM DISTRIBUTION SYSTEM
04/06
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 300 (2003; R 2017) Standard Specification for Inorganic Zinc-Rich Primer
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.9 (2018) Factory-Made Wrought Buttwelding Fittings
ASME B16.11 (2016) Forged Fittings, Socket-Welding and Threaded
ASME B31.1 (2020) Power Piping
ASME B40.100 (2013) Pressure Gauges and Gauge Attachments
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A106/A106M (2019a) Standard Specification for Seamless Carbon Steel Pipe for High-Temperature Service
ASTM A134/A134M (2019) Standard Specification for Pipe, Steel, Electric-Fusion (Arc)-Welded (Sizes NPS 16 and Over)
ASTM A135/A135M (2020) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A139/A139M (2016) Standard Specification for Electric-Fusion (ARC)-Welded Steel Pipe (NPS 4 and over)
ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting
SECTION 33 63 13 Page 1
Chromium-Nickel Steel Plate, Sheet, and Strip
ASTM A234/A234M (2019) Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service
ASTM C518 (2017) Standard Test Method for Steady-State Thermal Transmission Properties by Means of the Heat Flow Meter Apparatus
ASTM C533 (2017) Standard Specification for Calcium Silicate Block and Pipe Thermal Insulation
ASTM C591 (2020) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
ASTM D2310 (2006; R 2012) Machine-Made "Fiberglass" (Glass-Fiber-Reinforced Thermosetting-Resin) Pipe
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D2996 (2017) Standard Specification for Filament-Wound "Fiberglass" (Glass-Fiber-Reinforced Thermosetting-Resin) Pipe
INTERNATIONAL SOCIETY OF AUTOMATION (ISA)
ISA MC96.1 (1982) Temperature Measurement Thermocouples
NACE INTERNATIONAL (NACE)
NACE SP0169 (2015) Control of External Corrosion on Underground or Submerged Metallic Piping Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA ICS 4 (2015) Application Guideline for Terminal Blocks
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS L-S-125 (Rev B; Notice 1) Screening, Insect, Nonmetallic
1.2 DEFINITIONS
The following definitions are applicable:
SECTION 33 63 13 Page 2
1.2.1 Pre-engineered System
A complete underground heat distribution and condensate return system including all required components such as carrier pipes, steam pipe, condensate return pipe, and fittings, anchors, pipe supports, insulation, protective casing, and cathodic protection, for the system supplied. The pre-engineered system does not include valve manholes and the piping and equipment inside the valve manholes. The pre-engineered system shall include all piping and components to a point at least six inches inside the building and valve manhole. The UHDS shall not use any part of the building or valve manhole structure as an anchor point. Ensure there is adequate space allocated for welding of the piping.
1.2.2 Direct-Buried
A system which is buried without the need for a field-fabricated protective enclosure such as a concrete trench or tunnel.
1.2.3 UHDS Types
1.2.3.1 Drainable-Dryable-Testable (DDT) Direct-Buried System
A factory-fabricated system including an air and water-tight outer protective casing, air space and an insulated carrier pipe. Drains and vents are provided at the end plates of the system (in manholes or buildings). The drains are normally plugged but the plugs can be removed to drain water which may leak into the air space if there is a failure in the casing or the carrier pipe. The vents allow water vapor to escape and provide a tell-tale sign of leakage.
1.2.4 UHDS Manufacturer Certification
The UHDS manufacturer is the company responsible for the design and manufacture of the pre-engineered system. The UHDS manufacturer directs the installation of their system and has a representative on the job site.Certification includes that the UHDS manufacturer regularly and currently manufactures direct-buried systems, and that the designs of the system and equipment to be provided for this project conform to specification requirements. This certification shall be an original signed by a principal officer of the UHDS manufacturer and shall be submitted at minimum of 2 weeks prior to start of work.
1.2.5 UHDS Manufacturer's Representative
The UHDS manufacturer's representative shall be a person who regularly performs the duties specified herein, is certified in writing by the UHDS manufacturer to be technically qualified and experienced in the installation of the system, and shall be authorized by the manufacturer to make and sign the daily reports specified herein. The UHDS manufacturer's representative shall be under the direct employ and supervision of the UHDS manufacturer.
1.2.6 Corrosion Engineer
Corrosion engineer refers to a person who by knowledge of the physical sciences and the principles of engineering and mathematics, acquired by professional education and related practical experience, is qualified to engage in the practice of corrosion control. Such person may be a licensed professional corrosion engineer or certified as being qualified
SECTION 33 63 13 Page 3 by the National Association of Corrosion Engineers (NACE), if such licensing or certification includes 3 years experience in corrosion control on underground metallic surfaces of the type under this contract.
NACE certification shall be technologist, corrosion specialist, or cathodic protection specialist. The corrosion engineer shall make at least 3 visits to the project site. The first of these visits shall include obtaining soil resistivity data, acknowledging the type of pipeline coatings to be used and reporting to the Contractor the type of cathodic protection required. Once the submittals are approved and the materials delivered, the corrosion engineer shall revisit the site to ensure the Contractor understands installation practices and laying out the components. The third visit shall involve testing the installed cathodic protection systems and training applicable personnel on proper maintenance techniques. The corrosion engineer shall supervise, inspect, and test the installation and performance of the cathodic protection system.
1.2.7 Pipe-Stress and System Expansion Calculations
Pipe-stress and system-expansion calculations for each expansion compensation elbow using a finite element computer generated three-dimensional analysis, not later than 7 days after notice to proceed.
Calculations (including heat loss calculations) shall demonstrate that pipe stresses from temperature changes are within the allowable requirements in ASME B31.1 and the anchors and the guides will withstand the resultant forces. Submitted detailed design layout drawings including the location of all anchors and guides. Layout shall also include all analysis node points. As a minimum, the computer analysis results include node stresses, forces, moments and displacements. Calculations shall be approved, certified, stamped and signed by a registered Professional Engineer in the employ of the UHDS manufacturer.
1.2.8 Cathodic Protection System Calculations
Design life calculations for cathodic protection system in accordance with NACE SP0169, not later than 7 days after notice to proceed. Calculations shall be stamped and signed by a NACE qualified corrosion engineer.
1.2.9 Manufacturer's Data Sheets
Manufacturer's data sheets on all components of the UHDS and the instrumentation required for thermal performance testing.
Manufacturer's data sheets for all coatings and for carrier pipe insulation, indicate thicknesses not later than 7 days after notice to proceed.
1.2.10 Work Plan
A proposed schedule of activities indicating when various items of work and tests are to be carried out and when the representative of the UHDS manufacturer shall be present at job site. The UHDS manufacturer shall submit a list of what characteristics shall be considered damaged or defective materials that must be replaced.
1.2.11 Quality Assurance Plan
Manufacturer's quality assurance plan for fabrication, delivery, storage, SECTION 33 63 13 Page 4 installation and testing of system.
1.2.12 Thermal Performance Testing
A proposed test procedure and proposed samples of test data sheets for each required test, 30 days prior to the proposed test date. The procedure shall contain a complete description of the proposed test with calibration curves or test results furnished by an independent testing laboratory of each instrument, meter, gauge, and thermometer to be used in the tests. The test shall not commence until the procedure has been approved.
1.2.12 Certificate of Compliance
Upon completion of the work, and before final acceptance, a notarized statement signed by a principal officer of both the UHDS manufacturer and the contractor, certifying that the system has been installed satisfactorily and in accordance with the contract drawings, specifications, UHDS manufacturer's detailed design layout drawings and with the UHDS manufacturer's recommendations.
1.2.13 Testing Firm Qualification
A Certificate of the Testing Firm Qualification from the independent testing firm or firms, certifying that: weld examination methods and procedures, and the interpretation of radiographic films will be performed in accordance with ASME B31.1 ; the firm intends to utilize the proper film exposure, techniques, and…