This document provides details for a federal contract opportunity with the U.S. Army Corps of Engineers to repair two barracks buildings at West Point. The project involves renovating Building 740 at Lee Barracks and has an estimated cost between $100-200 million. It will repair interior spaces, replace mechanical, electrical and plumbing systems, and address exterior envelope and site work. As an option, the project may also renovate Building 738 at Sherman Barracks for an additional 321 cadet rooms. The solicitation will be posted on August 6 on SAM.gov and proposals will be due around 30 days later. Contractors must register in SAM prior to award. The period of performance is approximately 1034 calendar days from notice to proceed. The NAICS code is 236220.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lee and Sherman Barracks Upgrades Project August 27, 2021 US Military Academy, West Point, NY Issued for Amendment
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 00 00 06/15 SEALS PAGE
00 00 01 01/18 COVER SHEET
00 00 02 01/18 CHECK LIST FOR BIDDERS
00 10 00 12/17 SF 1442 AND BIDDING SCHEDULE
00 21 16 09/16 INSTRUCTIONS, CONDITIONS, AND NOTICE
TO BIDDERS
00 22 20 09/17 PROPOSAL SUBMISSION REQUIREMENTS AND
INSTRUCTIONS
00 24 00 06/17 EVALUATION FACTORS FOR AWARD
00 45 00 09/16 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 09/16 CONTRACT CLAUSES
00 90 00 06/17 WAGE RATES
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 08/15 SUMMARY OF WORK
01 14 00 11/11 WORK RESTRICTIONS
01 22 00.00 10 08/15 PRICE AND PAYMENT PROCEDURES
01 30 00 08/15 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 02/15 PROJECT SCHEDULE
01 33 00 08/18 SUBMITTAL PROCEDURES
01 33 29 02/17 SUSTAINABILITY REPORTING
01 35 26 11/15 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 91 07/21 HISTORIC TREATMENT PROCEDURES
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 11/16 QUALITY CONTROL
01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 20.00 18 NY Dist. July 2018 TESTING FOR MECHANICAL AND ELECTRICAL
SYSTEMS
01 45 35 02/20 SPECIAL INSPECTIONS
01 50 00 05/18 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 53 00 06/21 TEMPORARY CONSTRUCTION
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19 PROJECT IDENTIFICATION
01 74 19 02/19 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
01 78 24.00 10 05/18 FACILITY DATA REQUIREMENTS
01 91 00.15 10 05/19 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10 DEMOLITION AND DECONSTRUCTION
02 42 91 11/18 REMOVAL AND SALVAGE OF HISTORIC
CONSTRUCTION MATERIALS
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 11/18 ASBESTOS REMEDIATION
02 84 16 05/20 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
02 84 33 05/20 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
PROJECT TABLE OF CONTENTS Page 1
02 85 00 11/18 MOLD REMEDIATION
DI VI SI ON 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE
03 30 00 02/19 CAST-IN-PLACE CONCRETE
DI VI SI ON 04 - MASONRY
04 03 00 11/17 CONSERVATION TREATMENT FOR PERIOD
MASONRY
04 20 00 11/15 UNIT MASONRY
DI VI SI ON 05 - METALS
05 12 00 08/18 STRUCTURAL STEEL
05 30 00 05/15 STEEL DECKS
05 40 00 05/15 COLD-FORMED METAL FRAMING
05 50 13 05/17 MISCELLANEOUS METAL FABRICATIONS
05 51 00 02/17 METAL STAIRS
05 52 00 02/18 METAL RAILINGS
05 72 00 05/18 DECORATIVE METAL RESTORATION
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 08/16 ROUGH CARPENTRY
06 20 00 08/16 FINISH CARPENTRY
06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 11 13 08/11 BITUMINOUS DAMPPROOFING
07 13 53 02/16 ELASTOMERIC SHEET WATERPROOFING
07 14 00 02/12 FLUID-APPLIED WATERPROOFING
07 17 00 02/16 BENTONITE WATERPROOFING
07 21 13 02/16 BOARD AND BLOCK INSULATION
07 21 16 11/11 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16 ROOF AND TRAFFIC DECK INSULATION
07 27 26 05/17 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 05/17 SPRAY FOAM AIR BARRIERS
07 42 13 05/11 METAL WALL PANELS
07 52 00 05/12 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 05/17 FLASHING AND SHEET METAL
07 62 13 08/09 COPPER SHEET METAL FLASHING AND TRIM
07 81 00 02/11 SPRAY-APPLIED FIREPROOFING
07 84 00 05/10 FIRESTOPPING
07 92 00 08/16 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 14 00 08/16 WOOD DOORS
08 33 23 08/20 OVERHEAD COILING DOORS
08 41 13 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 51 13 05/19 ALUMINUM WINDOWS
PROJECT TABLE OF CONTENTS Page 2
08 71 00 02/16 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 22 36 01/08 LATH
09 23 00 08/16 GYPSUM PLASTERING
09 29 00 08/16 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17 STATIC-CONTROL FLOORING
09 65 00 08/10 RESILIENT FLOORING
09 66 16.01 08/16 TERRAZZO BASE AND STAIR TREADS
09 66 23 08/16 RESINOUS MATRIX TERRAZZO FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 68 00 11/17 CARPETING
09 90 00 05/11 PAINTS AND COATINGS
09 96 00 11/14 HIGH-PERFORMANCE COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 11 00 08/20 VISUAL DISPLAY UNITS
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 21 23.16 04/06 CUBICLE TRACK AND HARDWARE
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 METAL LOCKERS
10 51 26 05/11 PLASTIC LOCKERS
10 56 13 04/06 STEEL SHELVING
DI VI SI ON 11 - EQUI PMENT
11 72 13 04/06 MEDICAL EQUIPMENT, MISCELLANEOUS
11 81 19 02/09, CHG 1: 02/15 VACUUM CLEANING SYSTEMS
DI VI SI ON 12 - FURNI SHI NGS
12 21 00 08/17 WINDOW BLINDS
12 22 00 08/16 CURTAINS AND DRAPES
12 36 00 08/18 COUNTERTOPS
12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES
12 93 00 08/17 SITE FURNISHINGS
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 21 48 04/06 PREFABRICATED AUDIOMETRIC ROOMS
13 34 23.13 06/19 PORTABLE BUILDINGS
13 49 10 11/20 X-RAY SHIELDING
DI VI SI ON 14 - CONVEYI NG EQUI PMENT
14 24 23 05/16 HYDRAULIC PASSENGER ELEVATORS
DI VI SI ON 21 - FI RE SUPPRESSI ON
PROJECT TABLE OF CONTENTS Page 3
AdamsL3 Cross-Out
21 12 00 05/11 STANDPIPE SYSTEMS
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08 FIRE PUMPS
DI VI SI ON 22 - PLUMBI NG
22 00 00 11/15 PLUMBING, GENERAL PURPOSE
22 00 70 05/20 PLUMBING FOR HEALTHCARE FACILITIES
22 05 48.00 20 04/06 MECHANICAL SOUND, VIBRATION, AND
SEISMIC CONTROL
22 07 19.00 40 08/16 PLUMBING PIPING INSULATION
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 01 30.41 02/15 HVAC SYSTEM CLEANING
23 03 00.00 20 08/10 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 02/14 COMMON PIPING FOR HVAC
23 05 48.00 40 08/15 VIBRATION AND SEISMIC CONTROLS FOR
HVAC PIPING AND EQUIPMENT
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.01 02/19 LONWORKS DIRECT DIGITAL CONTROL FOR
HVAC AND OTHER BUILDING CONTROL SYSTEMS
23 11 20 05/20 FACILITY GAS PIPING
23 21 23 08/17 HYDRONIC PUMPS
23 23 00 10/07 REFRIGERANT PIPING
23 25 00 11/08 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20 HVAC AIR DISTRIBUTION
23 57 10.00 10 11/19 FORCED HOT WATER HEATING SYSTEMS USING
WATER AND STEAM HEAT EXCHANGERS
23 64 10 11/16 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 81 00 05/18 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.21 11/17 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS FIRE AND LIFE SAFETY
25 05 11.23 11/17 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS UTILITY MONITORING
CONTROL SYSTEM (UMCS)
25 08 10 04/06 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DI VI SI ON 26 - ELECTRI CAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 08 00 08/08 APPARATUS INSPECTION AND TESTING
26 09 13 11/08 POWER MONITORING SYSTEM
PROJECT TABLE OF CONTENTS Page 4
26 20 00 08/19 INTERIOR DISTRIBUTION SYSTEM
26 24 13 05/15 SWITCHBOARDS
26 28 01.00 10 10/07 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20 INTERIOR LIGHTING
26 56 00 05/20 EXTERIOR LIGHTING
26 56 10 01/17 HISTORIC EXTERIOR LIGHTING RESTORATION
DI VI SI ON 27 - COMMUNI CATI ONS
27 05 28.36 40 05/17 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 52 24 08/17 NURSE CALL SYSTEM
27 53 19.13 05/20 FIRST RESPONDER DISTRIBUTED ANTENNAE
SYSTEMS (DAS)
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 08 10 05/16 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 00 00 08/08 EARTHWORK
31 05 19 08/08 GEOTEXTILE
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 08/17 AGGREGATE BASE COURSES
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16 PAVEMENT MARKINGS
32 31 13 11/16 CHAIN LINK FENCES AND GATES
32 92 19 08/17 SEEDING
32 93 00 08/17 EXTERIOR PLANTS
DI VI SI ON 33 - UTI LI TI ES
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 02/10 STORM DRAINAGE UTILITIES
33 51 15 08/19 NATURAL-GAS / LIQUEFIED PETROLEUM GAS
DISTRIBUTION PIPELINES
33 63 13 04/06 EXTERIOR UNDERGROUND STEAM
DISTRIBUTION SYSTEM
33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
PROJECT TABLE OF CONTENTS Page 5
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 6
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 137 PAGES
West Point Lee and Sherman Barracks
01 14 00 SD-01 Preconstruction Submittals
1.4.4.1Personnel List
01 30 00 SD-01 Preconstruction Submittals
1.4 G ROView Location Map
1.5 G ROProgress and Completion
Pictures
1.5.5.2Preconstruction Video Recording
1.5.4.2Preconstruction Digital
Photographs
1.10 G ROWork To Be Performed By The
Contractor
1.21 G ROEng Form 93
1.21 G ROEng Form 93
1.21 G ROEng Form 93
SD-04 Samples
1.3 G ROColor Boards
SD-05 Design Data
1.5.5.3Periodic Construction Video
Recordings
1.5.4.3Periodic Construction Digital
Photographs
1.5.5.4Final Completion Construction
Video Recordings
SD-07 Certificates
1.21 G ROEng Form 93
1.21 G ROEng Form 93
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 137 PAGES
01 30 00 1.21 G ROEng Form 93
SD-11 Closeout Submittals
1.5.4.4Final Completion Construction
Digital Photographs
01 32 01.00 10 SD-01 Preconstruction Submittals
1.3 G ROProject Scheduler Qualifications
3.7.1 G ROPreliminary Project Schedule
3.7.2 G ROInitial Project Schedule
3.9.2 G ROPeriodic Schedule Update
3.8.2 G RONarrative Report
01 33 00 SD-01 Preconstruction Submittals
1.8 G ROSubmittal Register
01 33 29 SD-01 Preconstruction Submittals
1.5.3.1 S ROPreliminary High Performance
and Sustainable Building Checklist
1.4.1 S ROSustainability Action Plan
1.5.3.1 S ROPreliminary Sustainability
eNotebook
SD-11 Closeout Submittals
1.5.3.1 S ROFinal High Performance and
Sustainable Building Checklist
1.5.3.1 S ROFinal Sustainability eNotebook
1.5.3.1 S ROAmended Final Sustainability
eNotebook
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 137 PAGES
01 33 29 1.5.3.1 S ROAmended Final High
Performance and Sustainable
Building Checklist
3.2 S ROThird Party Certification
Certificate, Assessment, or
Validation
01 35 26 SD-01 Preconstruction Submittals
1.7 G ROAccident Prevention Plan (APP)
SD-06 Test Reports
1.4Monthly Exposure Reports
1.12Notifications and Reports
1.12.2 G ROAccident Reports
1.12.3LHE Inspection Reports
SD-07 Certificates
1.6.1.5Crane Operators/Riggers
1.7.2.2 G ROStandard Lift Plan
1.7.2.3 G ROCritical Lift Plan
1.8Activity Hazard Analysis (AHA)
1.9.1Confined Space Entry Permit
1.9.1Hot Work Permit
1.12.4Certificate of Compliance
1.14License Certificates
1.14.1 G RORadiography Operation Planning
Work Sheet
1.14.1 G ROPortable Gauge Operations
Planning Worksheet
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 137 PAGES
01 35 91 SD-01 Preconstruction Submittals
2.1 G ROConstruction Schedule for
Historic Treatment
2.2 G ROPhotographic Documentation
2.1 G ROHistoric Treatment Program
3.3 G ROHistoric Treatment Program
2.3 G ROAlternative Methods and
Materials
3.2.1 G ROFire-Prevention Plan
SD-05 Design Data
2.2 G AEProgress Photos
01 45 00.00 10 SD-01 Preconstruction Submittals
3.2 G ROContractor Quality Control (CQC)
Plan
SD-06 Test Reports
3.9.2Verification Statement
SD-07 Certificates
3.10 G ROQCR Report
01 45 20.00 18 SD-01 Preconstruction Submittals
1.3 G ROTest Plan List
01 45 35 SD-01 Preconstruction Submittals
3.1.2Written NDT Practices
SD-06 Test Reports
3.1.2Daily Reports
3.1.1Biweekly Reports
SD-07 Certificates
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 137 PAGES
01 45 35 2.1AISC Certified Steel Fabricator
1.5 G ROSpecial Inspector
3.1.2Qualification Records
SD-11 Closeout Submittals
3.1.2 G ROComprehensive Final Report
01 50 00 SD-01 Preconstruction Submittals
1.4 G ROConstruction Site Plan
3.5.1 G ROTraffic Control Plan
2.2.1 G ROHaul Road Plan
1.7.1.4 G ROContractor Computer
Cybersecurity Compliance
Statements
1.7.6 G ROContractor Temporary Network
Cybersecurity Compliance
Statements
3.6.1 G ROExisting Conditions Report
SD-02 Shop Drawings
3.7.2.2Steel Truss Drawing
3.7.2.2Building Elevations (Typical)
3.7.2.2Module Multiple Plans
3.7.2.2Key Plan Business Use Plans
3.7.2.2Power Riser Diagrams
3.7.2.2Steel Frame Plans
3.7.2.2Cross Section
3.7.2.2Floor Framing Plan
3.7.2.2Roof Framing Plan Shell Units
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 137 PAGES
01 50 00 3.7.2.2Ceiling Layout
3.7.2.2Roof Ventilation Plan And Details
3.7.2.2Plumbing Schematics
3.7.2.2Typical Foundation Plan
3.7.2.2Millwork Shop Drawings
3.7.2.2Site Electrical
3.7.2.2Site Domestic Water And
Sanitary Service Connections And
Routing
3.7.2.2Heat Tracing System For
Exposed Sanitary And Domestic
Water Service
SD-05 Design Data
3.7.2.2Perimeter Frame Calculations
3.7.2.2Floor Joist Calculation
3.7.2.2Exterior Stud Calculation
3.7.2.2Solid Rafter Calculation
3.7.2.2Mechanical Calculations
3.7.2.2Code Notes
3.7.2.2Uplift Siding Mansard Calculation
3.7.2.2Window and Door Design
Pressure (DP) Ratings
SD-07 Certificates
1.5.1Backflow Tester
1.5Backflow Preventers
3.7.2.2 G ROAsbestos Free Materials
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 137 PAGES
01 50 00 3.7.2.2Lead-Free Products
3.7.2.2Architectural Barriers Act
SD-10 Operation and Maintenance
Data
3.7.2.2 G ROHeat Distribution System
01 53 00 SD-01 Preconstruction Submittals
2.2.1 G ROConstruction Vehicle And
Delivery Route Plan
1.4 G ROConstruction Site Plan
SD-02 Shop Drawings
3.2 G ROSteel Truss Drawing
3.2 G ROBuilding Elevations (Typical)
3.2 G ROModule Multiple Plans
3.2 G ROKey Plan Business Use Plans
3.2 G ROPower Riser Diagrams
3.2 G ROSteel Frame Plans
3.2 G ROCross Section
3.2 G ROFloor Framing Plan
3.2 G RORoof Framing Plan Shell Units
3.2 G ROCeiling Layout
3.2 G RORoof Ventilation Plan And Details
3.2 G ROPlumbing Schematics
3.2 G ROTypical Foundation Plan
3.2 G ROMillwork Shop Drawings
3.2 G ROSite Electrical
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 137 PAGES
01 53 00 3.2 G ROSite Domestic Water And
Sanitary Service Connections And
Routing
3.2 G ROHeat Tracing System For
Exposed Sanitary And Domestic
Water Service
SD-03 Product Data
2.1.2 G ROFacility Identification Signs
SD-05 Design Data
3.2 G ROPerimeter Frame Calculations
3.2 G ROFloor Joist Calculation
3.2 G ROExterior Stud Calculation
3.2 G ROSolid Rafter Calculation
3.2 G ROMechanical Calculations
3.2 G ROCode Notes
3.2 G ROUplift Siding Mansard Calculation
3.2 G ROWindow And Door Dp Ratings
SD-07 Certificates
3.2 G ROAsbestos Free Materials
3.2 G ROLead-Free Products
3.2 G ROArchitectural Barriers Act
1.5 G ROBackflow Preventers Certificate
1.5.1Backflow Tester Certificate
SD-10 Operation and Maintenance
Data
3.2 G ROHeat Distribution System
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 137 PAGES
01 57 19 SD-01 Preconstruction Submittals
1.5.1Preconstruction Survey
1.10 G ROSolid Waste Management Permit
1.5.2 G RORegulatory Notifications
1.6 G ROEnvironmental Protection Plan
3.2.1.1 G ROStormwater Pollution Prevention
Plan
3.2.1.2 G ROStormwater Notice of Intent
1.6.9.1 G RODirt and Dust Control Plan
1.5.5 G ROEmployee Training Records
1.5.4 G ROEnvironmental Manager
Qualifications
SD-06 Test Reports
3.2.1.3Inspection Reports
1.10.1 G ROMonthly Solid Waste Disposal
Report
SD-07 Certificates
1.5.5 G ROEmployee Training Records
1.5.5.1Certificate of Competency
1.5.5Erosion and Sediment Control
Inspector
SD-11 Closeout Submittals
3.2.1.4 G ROStormwater Pollution Prevention
Plan Compliance Notebook
3.2.1.5 G ROStormwater Notice of Termination
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 137 PAGES
01 57 19 3.7.1 G ROWaste Determination
Documentation
3.7.3.6 G RODisposal Documentation for
Hazardous and Regulated Waste
1.5.5 G ROAssembled Employee Training
Records
1.10 G ROSolid Waste Management Permit
3.7.2.1 G ROProject Solid Waste Disposal
Documentation Report
3.7.3.1 G ROHazardous Waste/Debris
Management
1.5.2 G RORegulatory Notifications
3.7.2.1 G ROSales Documentation
01 58 00 SD-02 Shop Drawings
1.4.1 G ROSign Legend Orders
01 74 19 SD-01 Preconstruction Submittals
1.7 G ROConstruction Waste Management
Plan
SD-06 Test Reports
1.9.2Quarterly Reports
1.9.3Annual Report
SD-11 Closeout Submittals
1.10 SFinal Construction Waste
Diversion Report
01 78 00 SD-03 Product Data
1.9.1Warranty Management Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 137 PAGES
01 78 00 1.9.5Warranty Tags
1.7Spare Parts Data
SD-08 Manufacturer’s Instructions
1.9.1Instructions
SD-10 Operation and Maintenance
Data
3.7 G ROOperation and Maintenance
Manuals
SD-11 Closeout Submittals
3.1 G ROAs-Built Drawings
3.3 G RORecord Drawings
2.2 G RORecord Model
1.9.1As-Built Record of Equipment and Materials
3.6As-Built Record of Equipment and Materials
3.4 G ROFinal Approved Shop Drawings
3.5 G ROConstruction Contract
Specifications
2.3 G ROCertification of EPA Designated
Items
2.4 G ROCertification Of USDA Designated
Items
3.9.1 G ROInterim DD FORM 1354
3.9.2 G ROChecklist for DD FORM 1354
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 137 PAGES
01 78 00 3.9.2 G ROHigh Performance and
Sustainable Building (HPSB)
Checklist
01 78 23 SD-10 Operation and Maintenance
Data
1.4 G ROO&M Database
3.1.1 G ROTraining Plan
3.1.3 G ROTraining Outline
3.1.2 G ROTraining Content
SD-11 Closeout Submittals
3.1.4 G ROTraining Video Recording
3.1.6 G ROValidation of Training Completion
01 78 24.00 10 SD-01 Preconstruction Submittals
1.5.1Facility Data Project Execution
Plan
SD-10 Operation and Maintenance
Data
3.1 G ROFacility Data Workbook, Construction Progress
3.1 G ROFacility Document Set, Construction Progress
SD-11 Closeout Submittals
3.2 G ROFacility Data Workbook, Construction Final
1.5.3 G ROFacility Document Set, Construction Final
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 137 PAGES
01 78 24.00 10 3.2 G ROFacility Document Set, Construction Final
01 91 00.15 10 SD-01 Preconstruction Submittals
1.7 G DOCommissioning Firm
1.7.1 G DOLead Commissioning Specialist
1.7.2 G DOTechnical Commissioning
Specialists
1.7 G DOCommissioning Firm's Contract
SD-06 Test Reports
3.1.4 G DODesign Review Report
3.1.3.1 G DOInterim Construction Phase
Commissioning Plan
3.1.3.2 G DOFinal Construction Phase
Commissioning Plan
3.1.3.1.2 G DOTemplate Building Envelope
Inspection Checklists
3.1.6.2 G DOBuilding Envelope Inspection
Checklists
3.1.6.3 G DOPre-Functional Checklists
1.9Issues Log
3.2 G DOCommissioning Report
3.3.1 G DOPost-Construction Trend Log
Report
SD-07 Certificates
1.10 G DOCertificate of Readiness
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 137 PAGES
01 91 00.15 10 SD-10 Operation and Maintenance
Data
3.1.7 G ROTraining Plan
3.1.7 G ROTraining Attendance Rosters
3.1.8 G DOSystems Manual
3.1.9 G DOMaintenance and Service Life
Plans
SD-11 Closeout Submittals
3.2 S DOFinal Commissioning Report
3.1.3.2 SFinal Construction Phase
Commissioning Plan
02 41 00 SD-01 Preconstruction Submittals
1.2.2 G RODemolition Plan
1.2.2 G RODeconstruction Plan
1.10Existing Conditions
1.10.2Scaled And Dimensioned
Drawings Of All Major Existing To
Remain Architectural And
Structural Elements
SD-07 Certificates
1.7 G RONotification
02 42 91 SD-01 Preconstruction Submittals
1.2 G ROWork Plan
02 81 00 SD-03 Product Data
2.1.1Packaging Notifications
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 137 PAGES
02 81 00 3.1 G ROHazardous Waste Management
Plan
3.2 G ROOnsite Hazardous Waste
Management
3.3Notices of Non-Compliance and
Notices of Violation
SD-06 Test Reports
3.7 G RORecordkeeping
3.7 G ROException Report
3.8Spill Response
SD-07 Certificates
1.4.1 G ROTransportation and Disposal
Coordinator
1.4.2 G ROTraining
1.4.3Certification
3.3.3 G ROShipping Documents and
Packagings Certification
3.3.4Security Plan
3.3.5Certificates of Disposal
3.6Waste Minimization
02 82 00 SD-03 Product Data
1.2.2 G ROAmended Water
1.3.9 G ROSafety Data Sheets (SDS) for All
Materials
3.1.2.1 G RORespirators
3.1.7 G ROLocal Exhaust Equipment
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 137 PAGES
02 82 00 3.1.7 G ROPressure Differential Automatic
Recording Instrument
3.1.8 G ROVacuums
SD-06 Test Reports
1.5.5 G ROAir Sampling Results
1.5.6 G ROPressure Differential Recordings
for Local Exhaust System
3.3.3.2 G ROAsbestos Disposal Quantity
Report
SD-07 Certificates
1.3.4 G ROEmployee Training
1.3.5 G RONotifications
1.3.7 G RORespiratory Protection Program
1.3.10 G ROAsbestos Hazard Abatement Plan
1.3.11 G ROTesting Laboratory
1.3.12 G ROLandfill Approval
1.3.12 G RODelivery Tickets
1.3.12 G ROWaste Shipment Records
1.3.13 G ROTransporter Certification
1.3.14 G ROMedical Certification
1.5.1 G ROPrivate Qualified Person
Documentation
1.5.2 G ROCompetent Person
1.5.3 G ROWorker's License
1.5.4 G ROContractor's License
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 137 PAGES
02 82 00 1.5.7 G ROFederal, State or Local Citations on Previous Projects
3.1 G ROEquipment Used to Contain
Airborne Asbestos Fibers
3.1.3.2 G ROWater Filtration Equipment
3.1.8 G ROVacuums
3.1.8 G ROVentilation Systems
SD-11 Closeout Submittals
1.3.5 G ROPermits and Licenses
1.3.5 G RONotifications
1.3.7.1 G RORespirator Program Records
1.7.1 G RORental Equipment
02 84 16 SD-07 Certificates
1.8.1 G ROQualifications of CIH
1.8.1 G ROTraining Certification
1.8.2 G ROPCB and Lamp Removal Work
Plan
1.8.3 G ROPCB and Lamp Disposal Plan
SD-11 Closeout Submittals
3.5.2 G ROTransporter Certification
3.2.4Certification of Decontamination
3.5.2.1Certificate of Disposal and/or recycling
3.5.3.2DD Form 1348-1
3.3.1Testing Results
02 84 33 SD-07 Certificates
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 137 PAGES
02 84 33 1.7.1Training certification
1.7.2 G ROQualifications of CIH
1.7.3 G ROPCB Removal Work Plan
1.7.4 G ROPCB Disposal Plan
1.7.5 G RONotification
3.8Transporter Certification
3.5.4Certification of Decontamination
3.5.5Post Cleanup Sampling
3.8.1Certificate of Disposal
02 85 00 SD-01 Preconstruction Submittals
1.2.26 G ROVentilation System Mold
Remediator Qualifications (VSMR)
1.4.1.1 G ROMold Assessment Report
1.4.1.2 G ROMold Remediation Plan
1.4.1.3 G RORespiratory Protection Program
1.4.1.4Worker Records
1.4.1.5 G ROCertified Industrial Hygienist
(CIH)/Licensed NYS Mold
Assessor Qualifications
1.4.1.6 G RONYS Mold Remediation
Supervisor Qualifications
1.4.1.6 G ROCorporate NYS Mold License
SD-03 Product Data
1.2.11 G RODisinfectants or Biocide
Sanitizing Solutions
1.2.14 G ROFungicidal Agents, (EPA)
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 137 PAGES
02 85 00 1.2.21 G ROPersonal Protective Equipment
(PPE)
1.2.24Pressure Differential Measuring
Instrument
2.2 G ROSafety Data Sheets (SDS) for All
Materials
3.1.4Dehumidifiers
3.1.5Air Filtration Units
SD-06 Test Reports
1.4.3 G ROLicensed NYS Mold Assessor
Daily Reports
1.4.4 G ROLicensed NYS Mold Assessor
Daily Reports
SD-11 Closeout Submittals
1.4.4 G ROSubmittals at Completion of
Remediation Work
03 01 00 SD-01 Preconstruction Submittals
1.5.3 G ROQualifications
1.5.5 G ROWork Plan
1.6.1 G ROWork Plan
1.5.2 G ROQuality Control Plan
SD-03 Product Data
2.5Conventional Concrete
2.6Polymers
2.7Miscellaneous Materials And
Equipment
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 137 PAGES
03 01 00 SD-05 Design Data
3.1.3 G AEFormwork And Shoring
1.5.1 G AERepair Procedures
2.8 G AEMixture Proportioning
SD-06 Test Reports
2.8Mixture Proportioning
3.1.5Quality Control
3.2.3Quality Control
3.3.3Quality Control
3.5.3Quality Control
2.4Reinforcement And
Reinforcement Supports
2.5Conventional Concrete
SD-07 Certificates
1.5.3Qualifications
2.4Reinforcement And
Reinforcement Supports
03 30 00 SD-01 Preconstruction Submittals
1.6.5 G ROQuality Control Plan
1.6.6 G ROQuality Control Personnel
Certifications
1.6.6Quality Control Organizational
Chart
1.6.8 G ROLaboratory Accreditation
3.3.8Maturity Method Data
SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 137 PAGES
03 30 00 2.1Formwork
1.6.2.1 G AEReinforcing Steel
SD-03 Product Data
2.4.5Joint Sealants
2.4.4Joint Filler
2.3.1Cementitious Materials
2.4.6Vapor Retarder
2.4.1Concrete Curing Materials
2.6Reinforcement
2.3.4Admixtures
2.6.2Mechanical Reinforcing Bar
Connectors
2.2.2Waterstops
2.2.3Biodegradable Form Release
Agent
1.6.3.3Finishing Plan
2.4.2Nonshrink Grout
2.4.3.3 G AEClear Waterbased Curing
Compound and Sealer Finish
(SC1)
SD-04 Samples
1.6.3.6 G AEField Test Panels for Finish (SC1)
SD-05 Design Data
1.6.1.1 G AEConcrete Mix Design
SD-06 Test Reports
1.6.1.1 G AEConcrete Mix Design
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 137 PAGES
03 30 00 1.6.4.1Fly Ash
1.6.4.1Pozzolan
1.6.4.2Slag Cement
1.6.4.3Aggregates
3.14.2.3 G AECompressive Strength Tests
3.14.2.5Unit Weight of Lightweight
Structural Concrete
3.14.2.4Air Content
3.14.2.1Slump Tests
2.3.2Water
1.6.4.4Slip Resistance Testing for
Finished Sealed Concrete (SC1)
SD-07 Certificates
2.6.1Reinforcing Bars
1.6.3.4VOC Content for Form Release
Agents, Curing Compounds, and
Concrete Penetrating Sealers
1.6.3.5Safety Data Sheets
1.6.6.2Field Testing Technician and
Testing Agency
SD-08 Manufacturer’s Instructions
2.4.5Joint Sealants
2.4.3.3 G AEClear Waterbased Curing
Compound and Sealer Finish
(SC1)
2.4.1Curing Compound
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 137 PAGES
04 03 00 SD-01 Preconstruction Submittals
1.6.1 G ROQuality Control Plan
1.6.1 G ROProject Training Program
1.6.2 G ROQualifications
3.1 G ROHistoric Masonry Repair
Assessment
SD-02 Shop Drawings
1.6.5Photographic Documentation
3.8.1 G ROStructural Upgrades
SD-03 Product Data
1.6.2 G ROQualifications
1.6.6 G ROCleaning and Restoration
Methods
2.1 G ROCleaning Materials
1.3.2 G ROBiocides
2.2.2.2 G ROReplacement Mortar
2.4 G ROMortar Mix
SD-04 Samples
1.6.7.1 G ROMock-ups
SD-05 Design Data
3.8.1 G ROStructural Upgrades
SD-06 Test Reports
2.2.2.1 G ROTesting and Matching
SD-07 Certificates
2.2 G RORepair Materials
04 20 00 SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 137 PAGES
04 20 00 3.3.3.1 G ROCut CMU
3.4.1.1 G RO Detail Drawings
SD-03 Product Data
1.5.1 G ROHot Weather Procedures
1.5.2 G ROCold Weather Procedures
2.2.3.2.5 G RO Hollow Load Bearing Units
2.2.3.2.5 G RO Hollow Non-Load Bearing Units
2.2.3.2.5 G RO Glazed Fire Rated Load Bearing
Units
2.2.3.2.5 G RO Glazed Hollow Non-Load Bearing
Units
2.2.3.2.5 G RO Ground and Polished Hollow
Non-Load Bearing Units
2.4.1.1 G ROCementitious Materials
2.2.3.2.1 G ROCement
2.2.3.2 G ROConcrete Masonry Units (CMU)
3.3.1.4 G ROControl Joint
2.6.3 G ROJoint Reinforcement
1.3.1.1 G ROColored Mortar
2.2.3.2.2 G RO Recycled Content
2.2.2 G ROClay or Shale Brick
SD-04 Samples
1.3.1 G ROMock-Up
2.2.3.2 G ROConcrete Masonry Units (CMU)
2.2.3.2.5 G RO Glazed Hollow Non-Load Bearing
Units
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 137 PAGES
04 20 00 2.2.3.2.5 G RO Ground and Polished Hollow
Non-Load Bearing Units
2.2.5 G RODimension Stone Units
2.6.2 G ROAnchors, Ties, and Bar
Positioners
2.6.3 G ROJoint Reinforcement
2.6.7 G ROInsulation
SD-05 Design Data
2.1.2 G RO Masonry Compressive Strength
2.2.3.3 G ROFire-Rated Concrete Masonry
Units
3.2.4 G RO Bracing Calculations
SD-06 Test Reports
2.2.3.3 G ROFire-Rated Concrete Masonry
Units
3.6.1.1 G ROField Testing of Mortar
3.6.1.2 G ROField Testing of Grout
SD-07 Certificates
2.2.3.2 G ROConcrete Masonry Units (CMU)
2.4.1.4 G ROAdmixtures for Masonry Mortar
2.4.2.2 G ROAdmixtures for Grout
2.6.2 G ROAnchors, Ties, and Bar
Positioners
2.6.3Joint Reinforcement
SD-10 Operation and Maintenance
Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 137 PAGES
04 20 00 3.8 G ROTake-Back Program
SD-11 Closeout Submittals
2.2.3.2.2 S RORecycled Content
05 12 00 SD-01 Preconstruction Submittals
1.5.1.1 G AEErection and Erection Bracing
Drawings
SD-02 Shop Drawings
1.5.2 G AEFabrication Drawings
SD-03 Product Data
2.6.2Shop Primer
2.4.1Welding Electrodes and Rods
2.3.1.3Direct Tension Indicator Washers
2.4.2Non-Shrink Grout
2.3.2Tension Control Bolts
2.2.1 SRecycled Content for Structural
Steel
2.2.2 SRecycled Content for Structural
Steel Tubing
2.2.3 SRecycled Content for Steel Pipe
SD-06 Test Reports
2.6.2Class B Coating
2.3Bolts, Nuts, and Washers
3.7.1.2Weld Inspection Reports
3.7.2.1Direct Tension Indicator Washer
Inspection Reports
3.7.3.1Bolt Testing Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 137 PAGES
05 12 00 SD-07 Certificates
2.2Steel
2.3Bolts, Nuts, and Washers
2.5Galvanizing
1.3AISC Structural Steel Fabricator
Quality Certification
1.3AISC Structural Steel Erector
Quality Certification
1.5.3.1Welding Procedures and
Qualifications
2.4.1Welding Electrodes and Rods
3.7.1.1Certified Welding Inspector
3.7.1.2NDT Technician
3.4Welding Procedure Specifications
(WPS)
05 30 00 SD-02 Shop Drawings
1.3.5 G AEFabrication Drawings
SD-03 Product Data
2.2Accessories
2.1Deck Units
2.2.7Mechanical Fasteners
2.1.2Touch-Up Paint
1.3.3Welding Equipment
1.3.3Welding Rods and Accessories
2.1 SRecycled Content of Steel
Products
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 137 PAGES
05 30 00 SD-05 Design Data
2.1 G RODeck Units
SD-07 Certificates
1.3.2Powder-Actuated Tool Operator
1.3.3Welder Qualifications
1.3.3Welding Procedures
1.3.4.1Fire Safety
1.3.1Manufacturer's Certificate
05 40 00 SD-02 Shop Drawings
1.6.1 G ROFraming Components
SD-03 Product Data
2.1Studs
2.1 S RORecycled Content of Steel
Products
2.1 S RORecycled Content of Steel
Products
SD-05 Design Data
1.6.2 G RO Metal Framing Calculations
SD-07 Certificates
1.4Cold-Formed Metal Framing
05 50 13 SD-02 Shop Drawings
2.10 G AEStructural Steel Gate Frames
2.5 G ROCover Plates and Frames
2.6 G ROExpansion Joint Covers
2.4 G AEAccess Doors and Panels
2.7 G ROFloor Gratings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 137 PAGES
05 50 13 2.7 G AERoof/Trash Enclosure Walkways
2.8 G ROBollards/Pipe Guards
2.9 G ROAngles and Plates
SD-03 Product Data
2.4 G AEAccess Doors and Panels
2.5 G ROCover Plates and Frames
2.6 G ROExpansion Joint Covers
2.10 G ROStructural Steel Gate Frames
2.1 S RORecycled Content
SD-04 Samples
2.6Expansion Joint Covers
2.1 G ROCertificates of Compliance
2.2 G ROCertified Mill
05 51 00 SD-02 Shop Drawings
1.3.2 G AEMember and Connection
Calculation
2.1 G ROSteel Hardware
2.1 G ROSteel Shapes, Plates, Bars, and
Strips
2.2.1 G AEMetal Stair System
SD-03 Product Data
2.4.1 G AEStructural-Steel Plates, Shapes, and Bars
2.4.2 G AEStructural-Steel Tubing
2.4.5 G AEHot-Rolled Carbon Steel Sheets
and Strips
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 137 PAGES
05 51 00 2.4.4 G AECold-Finished Steel Bars
2.4.3 G AEHot-Rolled Carbon Steel Bars
2.4.6 G AECold-Rolled Carbon Steel Sheets
2.4.8 G AECold-Drawn Steel Tubing
2.3.3 G AEConcrete Inserts
2.3.4 G AEMasonry Anchorage Devices
2.2.4 G AEProtective Coating
2.2.2 G AESteel Pan Stairs
2.3.1 G AESteel Stairs
SD-07 Certificates
1.3.1 G ROWelding Procedures
1.3.1 G ROWelder Qualification
SD-08 Manufacturer’s Instructions
2.4.1 G ROStructural-Steel Plates, Shapes, and Bars
2.4.2 G ROStructural-Steel Tubing
2.2.4 G ROProtective Coating
2.3.4 G AEMasonry Anchorage Devices
05 52 00 SD-02 Shop Drawings
1.2.1 G AEFabrication Drawings
3.2 G ROIron and Steel Hardware
3.2 G ROSteel Shapes, Plates, Bars and
Strips
SD-03 Product Data
2.2.1 G ROStructural-Steel Plates, Shapes, and Bars
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 137 PAGES
05 52 00 3.2 G ROStructural-Steel Plates, Shapes, and Bars
2.2.2 G ROStructural-Steel Tubing
2.2.5 G ROConcrete Inserts
2.2.6 G ROMasonry Anchorage Devices
2.1.2 G ROProtective Coating
2.2.8 G AESteel Railings and Handrails
1.2.1 G ROAnchorage and Fastening
Systems
SD-07 Certificates
1.4.1 G ROWelding Procedures
1.4.2 G ROWelder Qualification
SD-08 Manufacturer’s Instructions
3.2Installation Instructions
05 72 00 SD-01 Preconstruction Submittals
1.1 G ROExisting Conditions
SD-02 Shop Drawings
1.5.3 G RODocumentation
SD-03 Product Data
2.1 G ROCleaning Materials
2.3 G ROFinish Materials
1.5.1 G ROQualifications
SD-04 Samples
1.5.4 G ROMock-ups
06 10 00 SD-02 Shop Drawings
2.1.2 G RONailing Strips
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 137 PAGES
06 10 00 SD-03 Product Data
2.2 G ROPlywood and oriented strand
board (OSB)
1.8 G ROFire-retardant treatment
2.3.1 G ROGypsum wall sheathing
2.3.3 G ROAdhesives
2.2.2.1 G RONAUF Composite Wood and
Laminating Adhesives
SD-06 Test Reports
1.4.4Preservative-treated
SD-07 Certificates
1.10.1Certificates of Grade
2.2.1.1 SCertified Sustainably Harvested
Plywood
SD-11 Closeout Submittals
1.9.1 G RO Local/Regional Materials
2.3.3Adhesives
2.2.2.1NAUF Composite Wood and
Laminating Adhesives
1.10.1 G ROCertified Wood
1.9.1 G RO LEED(tm) Documentation
06 20 00 SD-02 Shop Drawings
1.3 G AEDetail Drawings Indicating All
Wood Assemblies
SD-03 Product Data
2.1 G ROWood Products
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 137 PAGES
06 20 00 2.2.1 G ROCountertops
2.2.1 G ROVanity Tops
1.4 G ROTreated Wood Products
2.5 G ROHardware and Accessories
SD-04 Samples
2.1.7 G AEWood Chair Rail, Crown Molding
and Trim
SD-07 Certificates
1.7.1.1 G ROCertificates of Grade
2.6.1.2 SIndoor Air Quality for Non-aerosol
Adhesives
2.6.1.2 SIndoor Air Quality for Aerosol
Adhesives
06 41 16.00 10 SD-02 Shop Drawings
1.5.2 G AEShop Drawings
2.14 G AEShop Drawings
3.1 G AEInstallation
SD-03 Product Data
2.1 G ROWood Materials
2.12 G ROWood Finishes
2.14.7.3 G ROFinish Schedule
1.5.3 G ROCertification
SD-04 Samples
2.3 G AEPlastic Laminates
2.9 G AECabinet Hardware
1.5.2.1 G AETextured MDF Panel - XW12
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 137 PAGES
06 41 16.00 10 2.5 G AETextured MDF Panel - XW12
1.5.2.2 G AEGraphics on Laminate Panels -
XW13
2.6 G AEGraphics on Laminate Panels -
XW13
1.5.2 G AEMock-ups
SD-07 Certificates
1.5Quality…