W9124920R0020 AMENDMENT 0003.pdf

PDF 358 KB Posted

Attached to
Fort Gordon MATOC IDIQ for Minor Construction, Repair and Alteration
Solicitation number
W9124920R0020
Issued by

About this file

This document is an amendment to a solicitation for an Indefinite-Delivery Indefinite-Quantity Multiple Award Task Order Contract for minor construction, repair, and alteration services at Fort Gordon, Georgia. The U.S. Army Materiel Command Mission and Installation Contracting Command at Fort Eustis issued Solicitation W9124920R0020 for construction and facility support. The amendment extends the response deadline from August 17th to August 21st at 3:00 PM Eastern Time. Site visits were scheduled for July 28th and 29th with a maximum of two people per company attending on one assigned date. The solicitation closes on the new date of August 21st at 3:00 PM.

View the file

Other files

File Type Posted
ATTACHMENT 38 - CONTRACTOR SUBMITTED QUESTIONS AND GOVERNMENT PROVIDED ANSWERS LAST ROUND OF QUESTIONS.pdf PDF
ATTACHMENT 39 - Consolidated Copy of Solicitation through Amendment 5.pdf PDF
W9124920R0020 AMENDMENT 0006.pdf PDF
Attachment 24- CH50091-2P Attachment 4 Experience Information.doc DOC document
Attachment 27b- CH50091-2P Attachment 5b Conceptual Construction Plans AD.pdf PDF
Attachment 20- CH50091-2P Renovate Expand Bldg-29608 SOW 20Aug20_.pdf PDF
Attachment 25 -CH50091-2P Attachment 5a Conceptual Design Analysis 20Aug....pdf PDF
Attachment 27g- CH50091-2P Attachment 5b Conceptual Construction Plans LS.pdf PDF
Attachment 26-CH50091-2P Attachment 5a Design Analysis 20Aug20.docx DOCX document
Attachment 27e- CH50091-2P Attachment 5b Conceptual Construction Plans I.pdf PDF
Attachment 11- Scope of Work_MATOC 17Aug20.pdf PDF
W9124920R0020 AMENDMENT 0005.pdf PDF
Attachment 27h- CH50091-2P Attachment 5b Conceptual Construction Plans M- (2).pdf PDF
Attachment 27c- CH50091-2P Attachment 5b Conceptual Construction Plans EP.pdf PDF
Attachment 27d- CH50091-2P Attachment 5b Conceptual Construction Plans FA.pdf PDF
Attachment 27i- CH50091-2P Attachment 5b Conceptual Construction Plans M-.pdf PDF
Attachment 36 - MATOC_Contractor Questions and Answers_FINAL.pdf PDF
Attachment 22-CH50091-2P Attachment 2 Proposal Format.docx DOCX document
Attachment 27f- CH50091-2P Attachment 5b Conceptual Construction Plans I-.pdf PDF
Attachment 37 - Site Visit sign in_Redacted.pdf PDF
Attachment 27a- CH50091-2P Attachment 5b Conceptual Construction Plans A.pdf PDF
Attachment 21- CH50091-2P Attachment 1 Task Order Price Schedule Rev1.docx DOCX document
Attachment 23- CH50091-2P Attachment 3 Experience Overview.doc DOC document
W9124920R0020 AMENDMENT 0004.pdf PDF
W9124920R0020 AMENDMENT 0002.pdf PDF
Attachment 17 - Past Performance Cover Letter and Assessment Questionnair-REV1.docx DOCX document
W9124920R0020 AMENDMENT 0001.pdf PDF
Attachment 5- Division 01 Specifications_MATOC 10Jun20.pdf PDF
Attachment 16- Example of Package 1.pdf PDF
Attachment 2-Davis-Bacon Act WD GA20200153 Building - Richmond County GA.pdf PDF
Attachment 4-01 33 00 attachment SF1413-13e.pdf PDF
Attachment 6- MATOC QA Plan with Appendices_10Jun20.pdf PDF
Attachment 8- FG Installation Planning Standards_PreFinal 061319.pdf PDF
Attachment 22-CH50091-2P Attachment 2 Proposal Format.docx DOCX document
Attachment 29- Draft RTOP Letter.pdf PDF
Attachment 25- CH50091-2P Attachment 5a Conceptual Design Analysis.pdf PDF
Attachment 1-Davis-Bacon Act WD GA20200275 Highway Georgia.pdf PDF
Attachment 3-01 08 00 Weighted Guidelines.xls XLS spreadsheet
Attachment 11- Scope of Work_MATOC 12Jun20.pdf PDF
Attachment 28- CH50091-2P Attachment 6 As-builts.pdf PDF
Attachment 12- Submital Register.pdf PDF
Attachment 10- Pre-Construction Safety Brief (Updated 2020).pdf PDF
Attachment 20- CH50091-2P Renovate Expand Bldg-29608 SOW Rev1.pdf PDF
Attachment 7- FG Storm Water Permitting Requirements.pdf PDF
Attachment 14- ufc_3_740_05_2010_c1 Construction Cost Est.pdf PDF
Attachment 27- CH50091-2P Attachment 5b Conceptual Construction Plans.pdf PDF
Attachment 19 - Consent Form for the Release of Past Performance.docx DOCX document
Attachment 18 - Specific Relevant Contract Reference Sheets.docx DOCX document
W9124920R0020 FORT GORDON MATOC.pdf PDF
Attachment 23- CH50091-2P Attachment 3 Experience Overview.doc DOC document
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose for this Amendment is to extend the Closing date to August 21, 2020.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Aug-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9124920R0020

X 9B. DATED (SEE ITEM 11)

15-Jul-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 4 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Aug-2020

CODE

MICC - FORT GORDON

271 HERITAGE PARK LANE

BLDG. 35200

FT GORDON GA 30905

W91249 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9124920R0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 17-Aug-2020 03:00 PM to 21-Aug-2020 03:00 PM.

(End of Summary of Changes)