AM#10 READY TO ADVERTISE CLR039a LRDR Construction Package #1 - Clear AFS, Alaska
SECTION 01 91 19.01 00
EXTERIOR ENCLOSURE COMMISSIONING
06/16
PART 1 GENERAL
1.1 SUMMARY
This Section includes building enclosure commissioning (Cx) process requirements for above- and below-grade systems and assemblies.
a. Horizontal and vertical waterproofing.
b. Opaque walls.
c. Roofs.
d. Openings.
e. Interfaces.
1.2 RELATED REQUIREMENTS
Section 01 91 00.01 15 COMMISSIONING for general requirements for Cx processes including definitions, Cx team membership, and responsibilities of Government, Contractor, Commissioning Specialists, and Contractor's Commissioning Representative.
Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS for Air Barrier Pressure Tests and Air Leakage Test Reports and Diagnostic Test Reports.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)
AAMA 501.1 (2005) Standard Test Method for Water Penetration of Windows, Curtain Walls and Doors Using Dynamic Pressure
AAMA 501.2 (2015) Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems
AAMA 501.5 (2007) Test Method for Thermal Cycling Of Exterior Walls
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 180 (2012) Standard Practice for Inspection and Maintenance of Commercial Building
SECTION 01 91 19.01 00 Page 1
READY TO ADVERTISE
HVAC Systems
ASHRAE 202 (2013) Commissioning Process for Buildings and Systems
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
ASTM INTERNATIONAL (ASTM)
ASTM C1153 (2010) Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging
ASTM C794 (2015a) Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants
ASTM D4541 (2009; E 2010) Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM D5957 (1998; R 2013) Standard Guide for Flood Testing Horizontal Waterproofing Installations
ASTM E1014 (2012) Standard Guide for Measurement of Outdoor A-Weighted Sound Levels
ASTM E1105 (2000; R 2008) Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference
ASTM E1186 (2003; R 2009) Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems
ASTM E1332 (2010a) Standard Classification for Rating Outdoor-Indoor Sound Attenuation
ASTM E1503 (2014) Standard Test Method for Conducting Outdoor Sound Measurements Using a Digital Statistical Sound Analysis System
ASTM E1827 (2011) Standard Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door
ASTM E2359 (2013) Standard Test Method for Field Pull Testing of an In-Place Exterior Insulation and Finish System Clad Wall Assembly
ASTM E283 (2004; R 2012) Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen
SECTION 01 91 19.01 00 Page 2
ASTM E330/E330M (2014) Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference
ASTM E331 (2000; R 2009) Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference
ASTM E488/E488M (2015) Standard Test Methods for Strength of Anchors in Concrete and Masonry Elements
ASTM E699 (2009) Standard Practice for Evaluation of Agencies Involved in Testing, Quality Assurance, and Evaluating of Building Components
ASTM E779 (2010) Standard Test Method for Determining Air Leakage Rate by Fan Pressurization
ASTM E783 (2002; R 2010) Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors
ASTM E966 (2010e1) Standard Guide for Field Measurements of Airborne Sound Insulation of Building Facades and Facade Elements
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition
1.4 DEFINITIONS
1.4.1 Building Enclosure
Materials, components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or between two or more environmentally distinct interior spaces in a building or structure. The building enclosure includes, but is not limited to, exterior walls, above and below grade, and roof assemblies.
1.4.2 Cx
Commissioning, as defined in Section 01 91 00.01 15 COMMISSIONING.
1.4.3 CxA
Commissioning Authority, as defined in Section 01 91 00.01 15
SECTION 01 91 19.01 00 Page 3
COMMISSIONING.
1.4.4 CxG, CxC
Commissioning Specialists, as defined in Section 01 91 00.01 15
COMMISSIONING.
1.4.5 CCR
Contractor's Commissioning Representative, as defined in Section
01 91 00.01 15 COMMISSIONING.
1.4.6 Systems, Assemblies, Subsystems, Equipment, and Components
Where these terms are used together or separately, they shall mean "as-built" systems, assemblies, subsystems, equipment, and components.
1.4.7 Water Penetration
Visible evidence of uncontrolled water penetration on or adjacent to the test specimen in a location not intended to collect and drain water to the building exterior.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
Submittals with an "S" designation following the “G” are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.01 00 SUSTAINABILITY REPORTING. Other designations following the "G" designation identify the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.01 00
SUBMITTAL PROCEDURES:
SD-03 Product Data
Construction Checklist Review; G, C
SD-06 Test Reports
Building Enclosure Testing; G, C
SD-07 Certificates
Testing Agency Qualifications; G, C
SD-10 Operation and Maintenance Data
Building Envelope Systems and Components, to include operation and maintenance manuals; G, C
1.6 QUALITY ASSURANCE
1.6.1 Testing Agency Qualifications
Qualified according to ASTM E699 for testing indicated.
SECTION 01 91 19.01 00 Page 4
1.7 BUILDING ENVELOPE SYSTEMS AND COMPONENTS
1.7.1 Operations and Maintenance Data
Provide operations and maintenance information for exterior enclosure components and assemblies that undergo testing under this Section.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONSTRUCTION CHECKLIST REVIEW
Review and provide written comments on draft Construction Checklists. CxG will create required draft Construction Checklists and provide them to Contractor.
Return draft Construction Checklist review comments within 10 days of receipt.
Download example Building Envelope Inspection Checklists, Construction Checklists, Functional Performance Test Checklists, and Integrated Systems Test Checklists at the following location:
http://wbdg.org/ccb/NAVGRAPH/graphtoc.pdf . The checklists provided for review will contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.
The Building Envelope Technical Commissioning Specialist must review the Template Building Envelope Inspection Checklists. Confirm that items in the Building Envelope Inspection Checklists are sufficient to verify the building materials and construction maintain the required thermal and moisture integrity and air tightness of the building envelope system.
When review comments have been resolved, CxG will provide final Construction Checklists marked "Approved for Use, (date)."
Use only Construction Checklists marked "Approved for Use, (date). "
3.2 GENERAL TESTING REQUIREMENTS
If tests cannot be completed because of a deficiency outside the scope of the building enclosure systems, document the deficiency and report it to the Contracting Officer. After deficiencies are resolved, reschedule tests.
If seasonal testing is specified, complete appropriate initial performance tests and documentation and schedule seasonal tests.
Coordinate schedule with, and perform Cx activities at, the direction of the CxG.
3.3 BUILDING ENVELOPE COMMISSIONING
Refer to and coordinate with Section 07 05 23.01 00 PRESSURE TESTING AN
AIR BARRIER SYSTEM FOR AIR TIGHTNESS.
Document building envelope inspection by the commissioning team using the approved Template Building Envelope Inspection Checklists. Indicate
SECTION 01 91 19.01 00 Page 5 commissioning team member inspection and acceptance of each Building Envelope Inspection Checklist item by initials at the time they are inspected and found to be in conformance with contract requirements.
Inspect checklist items before they become hidden as construction progresses.
a. Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklists items. Submit one hard copy and an electronic copy.
b. The Building Envelope Technical Commissioning Specialist must make at least two site visits to the site to observe construction of the building envelope in-progress. On each visit, the Building Envelope Commissioning Specialist must review the Contractor's in-progress checklists to ensure that the commissioning team is inspecting the building envelope as required.
c. The Building Envelope Technical Commissioning Specialist must witness the building envelope pressure tests and diagnostic tests specified in Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS. The Building Envelope Technical Commissioning Specialist must review the resulting reports and provide recommendations for correction of any deficiencies or further testing.
3.4 BUILDING ENCLOSURE TESTING
Perform testing before installation of interior finishes unless otherwise indicated.
3.4.1 Testing Agency
Engage a qualified testing agency to perform testing on laboratory mockups.
3.4.2 Building Enclosure Testing
Perform the following tests in the following order
No. Test Type Description Performance Requirements
1. Smoke Testing ASTM E1186 at a static-air-pressure differential of 1.57 lbf/sq. ft.
ASTM E1186
2. Opaque Wall Air Infiltration
ASTM E783 at a static-air-pressure differential of 1.57 lbf/sq. ft.
Maximum air leakage rate
3. Window Air Infiltration
ASTM E783 at a static-air-pressure differential of 1.57 lbf/sq. ft. ; perform a minimum of two tests
Maximum air leakage rate
SECTION 01 91 19.01 00 Page 6
No. Test Type Description Performance Requirements
4. Air Leakage Site Detection
ASTM E1186 Maximum air leakage rate
5. Water Penetration AM#10...at exterior doors ...AM#10
ASTM E1105 with minimum uniform and cyclic static-air-pressure differential of 6.24 lbf/sq. ft.
No evidence of water penetration
AM#10... ...AM#10
AM#10...6. Water-Spray Test at Curtain Wall...AM#10
AAMA 501.2 No evidence of water penetration
AM#10... ...AM#10
AM#10...7. ...AM#10 Location of Wet Insulation in Roofing Systems
ASTM C1153 No wet insulation
AM#10... ...AM#10
AM#10... 8. ...AM#10 Whole Building Air Leakage Rate by Fan Pressurization
ASTM E779 Maximum air leakage rate
AM#10... 9....AM#10 Whole Building Air Tightness Using an Orifice Blower Door
ASTM E1827 Maximum air leakage
-- End of Section --
SECTION 01 91 19.01 00 Page 7