01_91_19.01_00_Amendment_10.pdf

PDF 27 KB Posted

Attached to
LRDR CP#1 Site Infrastructure, MCF, and Substation (CLR039a), Clear AFS, Alaska
Solicitation number
W911KB-17-R-0010
Issued by

About this file

Section 01 91 19.01 00

View the file

Other files

File Type Posted
J&A_17-2_Edwards_EST3_Fire_Panel_Redacted.pdf PDF
J&A_Intrusion_Detection-Vindicator_Redacted.pdf PDF
J&A_Siemans_Apogee_BACnet_Redacted.pdf PDF
W911KB-17-R-0010_AM_14.pdf PDF
W911KB-17-R-0010_AM_13.pdf PDF
W911KB-17-R-0010_AM_12.pdf PDF
13_27_54.01_10_AM_11.pdf PDF
Bidder_Inquiry_Report_W911KB-17-R-0010.pdf PDF
33_20_00.01_00_AM_11.pdf PDF
31_00_00.01_00_AM_11_17y01m25d.pdf PDF
W911KB-17-R-0010_AM_11.pdf PDF
07_42_63.01_00_AM_10.pdf PDF
CLR_LRDR_MCF_S-900549B_AM_10.pdf PDF
09_97_13.01_17.pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900402B.PDF PDF
M-100601A_-_SYSTEM_DIAGRAMS_-TEMPORARY_FUEL_TANK.pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900401B.PDF PDF
CLR_LRDR_LSUB_M-907503H_-_AM10.PDF PDF
01_50_00.01_00.pdf PDF
33_52_80.01_00.pdf PDF
09_97_13.01_27.pdf PDF
M-100502A_-_DETAILS_-_TEMPORARY_FUEL_TANK.pdf PDF
CLR_LRDR_LSUB_M-907600H_-_AM10.PDF PDF
08_34_49.01_20_AM_10_(2).pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900601B.PDF PDF
A-900005B_AM_10.pdf PDF
01_91_00.01_15_attachment_1_-_170123_LRDR_draft_CP-1_Cx_Master_Equipment_List.pdf PDF
CLR_LRDR_MCF_Z-900001B_AM_10.pdf PDF
W911KB-17-R-0010_AM_10.pdf PDF
33_52_10.01_00_-_AM10.pdf PDF
01_91_00.01_15_Amendment_10.pdf PDF
M-100301A_-_SECTIONS_-_TEMPORARY_FUEL_TANK.pdf PDF
A-900005B_AM_9.pdf PDF
23_05_93.01_00_AM_9.pdf PDF
06_20_00.01_00_AM_9.pdf PDF
22_05_48.00_20_AM_9.pdf PDF
Mechanical_Amendment_9_-_Sheet_-_MH900902B.pdf PDF
Revised_Plumbing_Sheets_-_Inquiry__6793897.pdf PDF
Mechanical_Amendment_9_-_Sheet_-_MP900703B.pdf PDF
26_08_01.01_00.pdf PDF
T-100601A_AM_09.pdf PDF
23_09_23.01_29_AM_9.pdf PDF
W911KB-17-R-0010_AM_9.pdf PDF
22_00_00.01_00_AM_9.pdf PDF
27_08_00.01_00.pdf PDF
33_20_01.01_00.pdf PDF
33_11_00.01_00_AM_9_17y01m18d.pdf PDF
09_97_13.01_17.pdf PDF
28_08_00.01_00.pdf PDF
E-100301A_Amendment__009.pdf PDF
Show 40 more

Latest 50 of 128 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AM#10 READY TO ADVERTISE CLR039a LRDR Construction Package #1 - Clear AFS, Alaska

SECTION 01 91 19.01 00

EXTERIOR ENCLOSURE COMMISSIONING

06/16

PART 1 GENERAL

1.1 SUMMARY

This Section includes building enclosure commissioning (Cx) process requirements for above- and below-grade systems and assemblies.

a. Horizontal and vertical waterproofing.

b. Opaque walls.

c. Roofs.

d. Openings.

e. Interfaces.

1.2 RELATED REQUIREMENTS

Section 01 91 00.01 15 COMMISSIONING for general requirements for Cx processes including definitions, Cx team membership, and responsibilities of Government, Contractor, Commissioning Specialists, and Contractor's Commissioning Representative.

Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS for Air Barrier Pressure Tests and Air Leakage Test Reports and Diagnostic Test Reports.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)

AAMA 501.1 (2005) Standard Test Method for Water Penetration of Windows, Curtain Walls and Doors Using Dynamic Pressure

AAMA 501.2 (2015) Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems

AAMA 501.5 (2007) Test Method for Thermal Cycling Of Exterior Walls

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 180 (2012) Standard Practice for Inspection and Maintenance of Commercial Building

SECTION 01 91 19.01 00 Page 1

READY TO ADVERTISE

HVAC Systems

ASHRAE 202 (2013) Commissioning Process for Buildings and Systems

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

ASTM INTERNATIONAL (ASTM)

ASTM C1153 (2010) Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging

ASTM C794 (2015a) Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants

ASTM D4541 (2009; E 2010) Pull-Off Strength of Coatings Using Portable Adhesion Testers

ASTM D5957 (1998; R 2013) Standard Guide for Flood Testing Horizontal Waterproofing Installations

ASTM E1014 (2012) Standard Guide for Measurement of Outdoor A-Weighted Sound Levels

ASTM E1105 (2000; R 2008) Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference

ASTM E1186 (2003; R 2009) Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems

ASTM E1332 (2010a) Standard Classification for Rating Outdoor-Indoor Sound Attenuation

ASTM E1503 (2014) Standard Test Method for Conducting Outdoor Sound Measurements Using a Digital Statistical Sound Analysis System

ASTM E1827 (2011) Standard Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door

ASTM E2359 (2013) Standard Test Method for Field Pull Testing of an In-Place Exterior Insulation and Finish System Clad Wall Assembly

ASTM E283 (2004; R 2012) Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen

SECTION 01 91 19.01 00 Page 2

ASTM E330/E330M (2014) Structural Performance of Exterior Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure Difference

ASTM E331 (2000; R 2009) Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference

ASTM E488/E488M (2015) Standard Test Methods for Strength of Anchors in Concrete and Masonry Elements

ASTM E699 (2009) Standard Practice for Evaluation of Agencies Involved in Testing, Quality Assurance, and Evaluating of Building Components

ASTM E779 (2010) Standard Test Method for Determining Air Leakage Rate by Fan Pressurization

ASTM E783 (2002; R 2010) Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors

ASTM E966 (2010e1) Standard Guide for Field Measurements of Airborne Sound Insulation of Building Facades and Facade Elements

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition

1.4 DEFINITIONS

1.4.1 Building Enclosure

Materials, components, systems, and assemblies intended to provide shelter and environmental separation between interior and exterior, or between two or more environmentally distinct interior spaces in a building or structure. The building enclosure includes, but is not limited to, exterior walls, above and below grade, and roof assemblies.

1.4.2 Cx

Commissioning, as defined in Section 01 91 00.01 15 COMMISSIONING.

1.4.3 CxA

Commissioning Authority, as defined in Section 01 91 00.01 15

SECTION 01 91 19.01 00 Page 3

COMMISSIONING.

1.4.4 CxG, CxC

Commissioning Specialists, as defined in Section 01 91 00.01 15

COMMISSIONING.

1.4.5 CCR

Contractor's Commissioning Representative, as defined in Section

01 91 00.01 15 COMMISSIONING.

1.4.6 Systems, Assemblies, Subsystems, Equipment, and Components

Where these terms are used together or separately, they shall mean "as-built" systems, assemblies, subsystems, equipment, and components.

1.4.7 Water Penetration

Visible evidence of uncontrolled water penetration on or adjacent to the test specimen in a location not intended to collect and drain water to the building exterior.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

Submittals with an "S" designation following the “G” are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.01 00 SUSTAINABILITY REPORTING. Other designations following the "G" designation identify the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.01 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Construction Checklist Review; G, C

SD-06 Test Reports

Building Enclosure Testing; G, C

SD-07 Certificates

Testing Agency Qualifications; G, C

SD-10 Operation and Maintenance Data

Building Envelope Systems and Components, to include operation and maintenance manuals; G, C

1.6 QUALITY ASSURANCE

1.6.1 Testing Agency Qualifications

Qualified according to ASTM E699 for testing indicated.

SECTION 01 91 19.01 00 Page 4

1.7 BUILDING ENVELOPE SYSTEMS AND COMPONENTS

1.7.1 Operations and Maintenance Data

Provide operations and maintenance information for exterior enclosure components and assemblies that undergo testing under this Section.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CONSTRUCTION CHECKLIST REVIEW

Review and provide written comments on draft Construction Checklists. CxG will create required draft Construction Checklists and provide them to Contractor.

Return draft Construction Checklist review comments within 10 days of receipt.

Download example Building Envelope Inspection Checklists, Construction Checklists, Functional Performance Test Checklists, and Integrated Systems Test Checklists at the following location:

http://wbdg.org/ccb/NAVGRAPH/graphtoc.pdf . The checklists provided for review will contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.

The Building Envelope Technical Commissioning Specialist must review the Template Building Envelope Inspection Checklists. Confirm that items in the Building Envelope Inspection Checklists are sufficient to verify the building materials and construction maintain the required thermal and moisture integrity and air tightness of the building envelope system.

When review comments have been resolved, CxG will provide final Construction Checklists marked "Approved for Use, (date)."

Use only Construction Checklists marked "Approved for Use, (date). "

3.2 GENERAL TESTING REQUIREMENTS

If tests cannot be completed because of a deficiency outside the scope of the building enclosure systems, document the deficiency and report it to the Contracting Officer. After deficiencies are resolved, reschedule tests.

If seasonal testing is specified, complete appropriate initial performance tests and documentation and schedule seasonal tests.

Coordinate schedule with, and perform Cx activities at, the direction of the CxG.

3.3 BUILDING ENVELOPE COMMISSIONING

Refer to and coordinate with Section 07 05 23.01 00 PRESSURE TESTING AN

AIR BARRIER SYSTEM FOR AIR TIGHTNESS.

Document building envelope inspection by the commissioning team using the approved Template Building Envelope Inspection Checklists. Indicate

SECTION 01 91 19.01 00 Page 5 commissioning team member inspection and acceptance of each Building Envelope Inspection Checklist item by initials at the time they are inspected and found to be in conformance with contract requirements.

Inspect checklist items before they become hidden as construction progresses.

a. Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklists items. Submit one hard copy and an electronic copy.

b. The Building Envelope Technical Commissioning Specialist must make at least two site visits to the site to observe construction of the building envelope in-progress. On each visit, the Building Envelope Commissioning Specialist must review the Contractor's in-progress checklists to ensure that the commissioning team is inspecting the building envelope as required.

c. The Building Envelope Technical Commissioning Specialist must witness the building envelope pressure tests and diagnostic tests specified in Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS. The Building Envelope Technical Commissioning Specialist must review the resulting reports and provide recommendations for correction of any deficiencies or further testing.

3.4 BUILDING ENCLOSURE TESTING

Perform testing before installation of interior finishes unless otherwise indicated.

3.4.1 Testing Agency

Engage a qualified testing agency to perform testing on laboratory mockups.

3.4.2 Building Enclosure Testing

Perform the following tests in the following order

No. Test Type Description Performance Requirements

1. Smoke Testing ASTM E1186 at a static-air-pressure differential of 1.57 lbf/sq. ft.

ASTM E1186

2. Opaque Wall Air Infiltration

ASTM E783 at a static-air-pressure differential of 1.57 lbf/sq. ft.

Maximum air leakage rate

3. Window Air Infiltration

ASTM E783 at a static-air-pressure differential of 1.57 lbf/sq. ft. ; perform a minimum of two tests

Maximum air leakage rate

SECTION 01 91 19.01 00 Page 6

No. Test Type Description Performance Requirements

4. Air Leakage Site Detection

ASTM E1186 Maximum air leakage rate

5. Water Penetration AM#10...at exterior doors ...AM#10

ASTM E1105 with minimum uniform and cyclic static-air-pressure differential of 6.24 lbf/sq. ft.

No evidence of water penetration

AM#10... ...AM#10

AM#10...6. Water-Spray Test at Curtain Wall...AM#10

AAMA 501.2 No evidence of water penetration

AM#10... ...AM#10

AM#10...7. ...AM#10 Location of Wet Insulation in Roofing Systems

ASTM C1153 No wet insulation

AM#10... ...AM#10

AM#10... 8. ...AM#10 Whole Building Air Leakage Rate by Fan Pressurization

ASTM E779 Maximum air leakage rate

AM#10... 9....AM#10 Whole Building Air Tightness Using an Orifice Blower Door

ASTM E1827 Maximum air leakage

-- End of Section --

SECTION 01 91 19.01 00 Page 7

File details come from the government source that posted it. Updated .