Section 01 91 00.01 15

View the file

Other files

File Type Posted
J&A_17-2_Edwards_EST3_Fire_Panel_Redacted.pdf PDF
J&A_Intrusion_Detection-Vindicator_Redacted.pdf PDF
J&A_Siemans_Apogee_BACnet_Redacted.pdf PDF
W911KB-17-R-0010_AM_14.pdf PDF
W911KB-17-R-0010_AM_13.pdf PDF
W911KB-17-R-0010_AM_12.pdf PDF
13_27_54.01_10_AM_11.pdf PDF
Bidder_Inquiry_Report_W911KB-17-R-0010.pdf PDF
33_20_00.01_00_AM_11.pdf PDF
31_00_00.01_00_AM_11_17y01m25d.pdf PDF
W911KB-17-R-0010_AM_11.pdf PDF
07_42_63.01_00_AM_10.pdf PDF
CLR_LRDR_MCF_S-900549B_AM_10.pdf PDF
09_97_13.01_17.pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900402B.PDF PDF
M-100601A_-_SYSTEM_DIAGRAMS_-TEMPORARY_FUEL_TANK.pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900401B.PDF PDF
CLR_LRDR_LSUB_M-907503H_-_AM10.PDF PDF
01_50_00.01_00.pdf PDF
33_52_80.01_00.pdf PDF
09_97_13.01_27.pdf PDF
M-100502A_-_DETAILS_-_TEMPORARY_FUEL_TANK.pdf PDF
01_91_19.01_00_Amendment_10.pdf PDF
CLR_LRDR_LSUB_M-907600H_-_AM10.PDF PDF
08_34_49.01_20_AM_10_(2).pdf PDF
Mechanical_Amendment_10_-_Sheet_-_MP900601B.PDF PDF
A-900005B_AM_10.pdf PDF
01_91_00.01_15_attachment_1_-_170123_LRDR_draft_CP-1_Cx_Master_Equipment_List.pdf PDF
CLR_LRDR_MCF_Z-900001B_AM_10.pdf PDF
W911KB-17-R-0010_AM_10.pdf PDF
33_52_10.01_00_-_AM10.pdf PDF
M-100301A_-_SECTIONS_-_TEMPORARY_FUEL_TANK.pdf PDF
A-900005B_AM_9.pdf PDF
23_05_93.01_00_AM_9.pdf PDF
06_20_00.01_00_AM_9.pdf PDF
22_05_48.00_20_AM_9.pdf PDF
Mechanical_Amendment_9_-_Sheet_-_MH900902B.pdf PDF
Revised_Plumbing_Sheets_-_Inquiry__6793897.pdf PDF
Mechanical_Amendment_9_-_Sheet_-_MP900703B.pdf PDF
26_08_01.01_00.pdf PDF
T-100601A_AM_09.pdf PDF
23_09_23.01_29_AM_9.pdf PDF
W911KB-17-R-0010_AM_9.pdf PDF
22_00_00.01_00_AM_9.pdf PDF
27_08_00.01_00.pdf PDF
33_20_01.01_00.pdf PDF
33_11_00.01_00_AM_9_17y01m18d.pdf PDF
09_97_13.01_17.pdf PDF
28_08_00.01_00.pdf PDF
E-100301A_Amendment__009.pdf PDF
Show 40 more

Latest 50 of 128 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AM#10 READY TO ADVERTISE CLR039a LRDR Construction Package #1 - Clear AFS, Alaska

SECTION 01 91 00.01 15

COMMISSIONING

05/16

PART 1 GENERAL

Provide the services of a Contractor's Commissioning Representative (CCR) who coordinates and directs all Contractor activities in support of the Government's third-party commissioning process. Support commissioning of the facility systems listed and referenced herein. Conform to the commissioning procedures outlined in this specification.

The requirements of this Section apply to, and are a component part of, each section of the specifications.

This Section includes:

a. General requirements for coordinating and scheduling commissioning.

b. Commissioning meetings.

c. Commissioning reports.

d. Use of test equipment, instrumentation, and tools for commissioning.

e. Construction checklists, including, but not limited to, installation checks, startup, and performance tests.

f. Commissioning (functional) tests.

g. Adjusting, verifying, and documenting identified systems and assemblies.

h. Facility commissioning of the systems listed and referenced in Part 3 of this specification and related technical commissioning specifications. AM#10 See attached Draft of the Master Equipment List for this project....AM#10

i. Facility commissioning activities and documentation in support of the U.S. Green Building Council (USGBC) LEED BD+C™ rating program.

Commissioning activities and documentation include the section on the "Energy and Atmosphere" prerequisite of "Fundamental Building Systems Commissioning" and the section on "Additional Commissioning."

The Government, Architect/Engineer, or Commissioning Specialists (CxG, CxD, or CxC) are not responsible for construction means, methods, job safety, or management function related to commissioning on the job site.

The commissioning process does not take away from or reduce the responsibility of the system designers or installing contractors to provide a finished and fully functioning product.

This specification requires the preparation of a Systems Manual for specific assets designed and constructed as part of this contract, for inclusion into a complete Facility Systems Operation and Maintenance

SECTION 01 91 00.01 15 Page 1

READY TO ADVERTISE

Manual (FSOMM). Provide a Systems Manual as defined in this specification. See Sections 01 33 00.01 00 SUBMITTAL PROCEDURES and 01 78 00.01 00 CLOSEOUT SUBMITTALS for additional Facility Data delivery requirements.

Overall intent is to deliver complete FSOMMs for the entire LRDR facility, which is made up of multiple independent construction projects. Each construction project contributes documentation for the FSOMMs made up of the following components:

a. Systems Manual: Documentation of system concepts, operation intent, testing procedures, and re-testing schedules. Prepared as part of commissioning process. Systems Manual covers facility-wide topics, and must be configured to accept additional or revised information as each future construction phase is completed.

b. Facility Document Set (FDS): Electronic assembly of complete project record documents, including O&M Manuals made up of data packages from Section 01 78 23.01 00 OPERATION AND MAINTENANCE and Record Drawings from Section 01 78 00.01 00 CLOSEOUT SUBMITTALS. Assembly of the FDS is described in Section 01 78 24.01 10 OPERATIONS AND MAINTENANCE FACILITY DATA REQUIREMENTS. The FDS must be structured to accept revised information and data from subsequent construction projects.

c. Facility Data Workbook (FDW): Specific O&M data for each piece of equipment, entered in separate spreadsheet forms, for streamlined documentation and entry into electronic asset management software.

Refer to Section 01 78 24.01 10 OPERATIONS AND MAINTENANCE FACILITY DATA REQUIREMENTS. Sets of FDW documents must be organized so each subsequent construction project can easily add new information.

1.1 RELATED REQUIREMENTS

The following Sections are an integral part of this project Commissioning

b. Section 01 33 00.01 00 SUBMITTAL PROCEDURES.

c. Section 01 45 04.01 29 CONTRACTOR QUALITY CONTROL.

d. Section 01 45 35.01 00 SPECIAL INSPECTIONS.

e. Section 01 57 20.01 29 ENVIRONMENTAL PROTECTION.

f. Section 01 75 00.01 40 STARTING AND ADJUSTING.

g. Section 01 78 00.01 00 CLOSEOUT PROCEDURES.

h. Section 01 78 23.01 00 OPERATION AND MAINTENANCE DATA.

i. Section 01 78 24.01 00 OPERATIONS AND MAINTENANCE FACILITY DATA

REQUIREMENTS.

j. Section 22 00 00.01 00 PLUMBING, GENERAL PURPOSE.

k. Section 23 00 00.01 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND

EXHAUST SYSTEMS.

l. Section 23 03 00.01 20 BASIC MECHANICAL MATERIALS AND METHODS.

SECTION 01 91 00.01 15 Page 2

n. Section 01 91 19.01 00 EXTERIOR ENCLOSURE COMMISSIONING for technical commissioning requirements for exterior enclosure.

p. Section 13 08 00.01 00 COMMISSIONING OF SPECIAL CONSTRUCTION for technical commissioning requirements for special construction.

q. Section 21 08 00.01 00 COMMISSIONING OF FIRE SUPPRESSION for technical commissioning requirements for fire suppression.

r. Section 22 08 00.01 00 COMMISSIONING OF PLUMBING for technical commissioning requirements for plumbing.

s. Section 23 08 00.01 10 COMMISSIONING OF HVAC for technical commissioning requirements for HVAC.

t. Section 25 08 00.01 00 COMMISSIONING OF POWER CONTROL AND MONITORING

SYSTEMS.

u. Section 26 08 01.01 00 COMMISSIONING OF ELECTRICAL SYSTEMS for technical commissioning requirements for electrical systems.

v. Section 27 08 00.01 00 COMMISSIONING OF COMMUNICATION SYSTEMS for technical commissioning requirements for communications systems.

w. Section 28 08 00.01 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS for technical commissioning requirements for electronic safety and security systems.

x. Section 33 08 55.01 00 COMMISSIONING OF POL FACILITY SYSTEMS.

1.2 SYSTEMS TO BE COMMISSIONED

At minimum, systems and equipment in this project will be commissioned to comply with ASHRAE 189.1 as applicable to this project. Refer to individual discipline commissioning specifications referenced in Related Requirements, and to the Master Equipment List in the Commissioning Plan for comprehensive lists of systems to be commissioned. AM#10...A draft of the MEL for this project is attached to this specification....AM#10 The Commissioning Plan will be made available after contract has been awarded.

Provide commissioning support for Integrated Systems as described in this section and related specifications. Integrated Systems include the following:

a. Battleshort mode.

b. Utility power failure.

c. Radar call for power.

d. Radar call for cooling.

e. Water well system modes.

f. HEMP mode.

g. Load Shed mode.

h. Freeze protection mode.

SECTION 01 91 00.01 15 Page 3

i. Others as identified.

Refer to Part 3 Execution, paragraph INTEGRATED SYSTEM TESTS, for a description of testing criteria for integrated systems.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY FOR QUALITY (ASQ)

ANSI/ASQ Z1.4 (2008; R 2013) Sampling Procedures and Tables for Inspection by Attributes

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 180 (2012) Standard Practice for Inspection and Maintenance of Commercial Building HVAC Systems

ASHRAE 189.1 (2014; Errata 1-2 2015) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings

ASHRAE 202 (2013) Commissioning Process for Buildings and Systems

ASHRAE Guideline 0 (2013) The Commissioning Process

ASHRAE Guideline 1.1 (2007) The HVAC Commissioning Process

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

ASTM INTERNATIONAL (ASTM)

ASTM D6245 (2012) Using Indoor Carbon Dioxide Concentrations to Evaluate Indoor Air Quality and Ventilation

ASTM D6345 (2010) Selection of Methods for Active, Integrative Sampling of Volatile Organic Compounds in Air

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1429 (1994) HVAC Systems Commissioning Manual, SECTION 01 91 00.01 15 Page 4

1st Edition

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED BD+C (2009; R 2010) Leadership in Energy and Environmental Design(tm) Building Design and Construction (LEED-NC)

LEED GBDC Ref Guide (2009; R 2010) LEED Reference Guide for Green Building Design, Construction and Major Renovations of Commercial and Institutional Buildings including Core & Shell and K-12 Projects

1.4 DEFINITIONS

1.4.1 Acceptance Criteria

Threshold of acceptable work quality or performance specified for a commissioning activity, including, but not limited to, construction checklists, performance tests, and commissioning tests.

1.4.2 Basis-of-Design Document

A document prepared by Architect/Engineer or Commissioning Authority that records concepts, calculations, decisions, and product selections used to comply with Facility Requirements Documents (FRD) and to suit applicable regulatory requirements, standards, and guidelines.

1.4.3 Commissioning

A quality-focused process for verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, and tested to comply with the Facility Requirements Document (FRD). The requirements specified here are limited to the construction phase commissioning activities.

Commissioning is a comprehensive and systematic process to verify that the facility systems perform as designed to meet the requirements.

Commissioning during the construction, acceptance, and warranty phases intends to achieve the following specific objectives:

a. Verify and document that equipment is installed and started per manufacturer's recommendations, industry accepted minimum standards, and the Contract Documents.

b. Verify and document that equipment and systems receive complete operational checkout by the installing contractors.

c. Verify and document equipment and system performance.

d. Verify the completeness of Operations and Maintenance materials.

e. Ensure that the operating personnel are adequately trained on the operation and maintenance of the facility equipment.

1.4.4 Commissioning Authority (CxA)

The commissioning authority (CxA) is defined as the person(s) or entity

SECTION 01 91 00.01 15 Page 5 responsible, on the Government's behalf, for assuring the commissioning process is properly carried out according to FRD and BoD during the life of the project. This includes witnessing functional performance tests and verifying acceptable performance of the Commissioning Process. The CxA assures the required documentation is produced and in the context of the overall total facility commissioning process. The primary role of the CxA is to verify achievement of the Facility Requirements Document (FRD) and validate the Basis of Design (BoD) throughout the phases of the project, from Pre-Design Phase through Occupancy and Operations Phase. The CxA does not perform testing; it assures the execution of the commissioning process that includes testing and assures the recording and documenting of the process and its results. The CxA participates as a member of the PDT in the planning and oversees of the Total Building Commissioning process and its activities to verify achievement of the FRD and validation of the BoD. For this project, USACE, as the Army's Design and Construction Agent, is the CxA. With respect to commissioning, USACE as the CxA specifically represents the Government's interests.

1.4.5 Commissioning Plan

A document, initially prepared by Commissioning Authority and subsequently updated by CxC and CCR, that outlines the organization, schedule, allocation of resources, and documentation requirements of commissioning.

1.4.6 Commissioning Specialist for Construction (CxC)

A Cx professional hired by the Government to support the CxG role. The CxC coordinates the Government's Cx process during construction, writes test forms, and observes performance tests, among other support duties.

1.4.7 Commissioning Specialist for the Government (CxG)

For the purpose of meeting industry's "enhanced" Cx requirements (e.g., USGBC's LEED Rating system, EA Credit 3), the CxG is considered the CxA and is the entity responsible for Government oversight of the commissioning process. The CxG is an entity having expertise in the commissioning of facilities of a scope and complexity comparable to the individual project, and employed regularly in facility commissioning. The CxG may be person(s) employed by the Design and Construction Agent (USACE), or an entity directly contracted by the Design and Construction Agent, but not affiliated with the construction contractor. The CxG shall provide management and oversight of the Commissioning process through the design, construction, and warranty phases to ensure it is effectively and thoroughly implemented.

1.4.8 Commissioning Test

See definition for Functional Performance Test.

1.4.9 Construction Checklist

A list of items to inspect and elementary component tests to conduct to verify proper installation of equipment, provided by the CCR to the contractor. Construction checklists are primarily static inspections and procedures to prepare the equipment or system for initial operation (e.g., belt tension, oil levels OK, labels affixed, gages in place, sensors calibrated, etc.). However, some construction checklist items entail simple testing of the function of a component, a piece of equipment, or system (such as measuring the voltage imbalance on a three-phase pump

SECTION 01 91 00.01 15 Page 6 motor of a chiller system). The word "Construction" refers to before functional testing. Construction checklists augment and are combined with the manufacturer's start-up checklist.

1.4.10 Construction Phase Commissioning Completion

The stage of completion and acceptance of commissioning when resolution of deficient conditions and issues discovered during commissioning and retesting until acceptable results are obtained has been accomplished.

The Government will establish in writing the date Construction Phase Commissioning Completion is achieved. See Section 01 78 00.01 00 CLOSEOUT SUBMITTALS and this specification for closeout submittal requirements.

Commissioning is complete when the work specified in this Section and related Sections has been completed and accepted, including, but not limited to, the following:

a. Completion of tests and acceptance of test results.

b. Resolution of issues, as verified by retests performed and documented with acceptance of retest results.

c. Completion of Demonstration and Training requirements.

d. Completion and acceptance of submittals and reports.

1.4.11 Contractor's Commissioning Representative (CCR)

The CCR must be a certified commissioning provider with the experience and expertise in the commissioning of facilities of a scope and complexity comparable to the individual project. The CCR must be employed regularly in facility commissioning and is the individual responsible for coordinating the commissioning activities during the construction and post-occupancy phases. The CCR shall be an employee of a commissioning firm hired as a first-tier subcontractor by the prime construction contractor.

The CCR shall be responsible for scheduling and coordinating all construction phase commissioning activities, refinement of Construction Checklists and Functional Performance Tests to match the specific purchased equipment, development of the systems manual (to be augmented with design phase commissioning documentation by the CxG), and direct oversight and reporting/documenting of the execution of the Commissioning process.

The CCR provides assistance to the CxC for development of the detailed construction phase commissioning plan (to augment the design phase Cx plan).

1.4.12 Deficiency

A condition in the installation or function of a component, piece of equipment or system that is not in compliance with the Contract Documents, does not perform properly, or is not complying with the Project Requirements.

1.4.13 Facility Requirements Document (FRD)

A document written by the Government that details the functional

SECTION 01 91 00.01 15 Page 7 requirements of a project and the expectations of how it will be used and operated, including Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.

1.4.14 Functional Performance Test (Commissioning Test)

Test of the dynamic function and operation of equipment and systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic testing of systems (rather than just components) under full operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump ramps up and down to maintain the differential pressure setpoint). Systems are tested under various modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. The systems are run through all the control system's sequences of operation and components are verified to be responding as the sequences state. Traditional air or water test and balancing (TAB) is not functional testing, in the commissioning sense of the word.

1.4.15 Government's Witness

Commissioning Authority, Government's Project Manager, or Government-designated witness authorized to authenticate test data and to sign completed test data forms.

1.4.16 Integrated Systems

Integrated systems are combinations of multiple systems and control sequences which interface and require integration to achieve the desired sequence of operation. Integrated systems typically involve multiple specifications, Divisions, and subcontractors.

1.4.17 Manual Test

Using hand-held instruments, immediate control system readouts, or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the "observation").

1.4.18 Monitoring

The recording of parameters (flow, current, status, pressure, etc.) of equipment operation using data loggers or the trending capabilities of control systems.

1.4.19 Owner's Representative, Owner's Witness

See Government's Witness.

1.4.20 Performance Verification Tests

Operational tests documenting readiness for functional testing. Tests are described in individual technical commissioning specifications.

1.4.21 Project Requirements

See definition for Facility Requirements Document.

SECTION 01 91 00.01 15 Page 8

1.4.22 Seasonal Performance Tests

Functional Performance Tests that are deferred until the system(s) will experience conditions closer to their design conditions.

1.4.23 "Systems," "Assemblies," "Subsystems," "Equipment," and "Components"

Where these terms are used together or separately, they shall mean "as-built" systems, assemblies, subsystems, equipment, and components.

1.4.24 Test

Performance tests and commissioning tests.

1.4.25 Warranty Period

Warranty period for entire project, including equipment components.

Warranty begins at Beneficial Occupancy Date (BOD) and extends for at least one year, unless specifically noted otherwise in the Contract Documents and accepted submittals.

1.5 COMMUNICATION WITH THE GOVERNMENT

The Contractor's Commissioning Representative (CCR) provides submittal documentation directly to the Contracting Officer Representative concurrent with submission to the CQC System Manager . The CCR communicates directly with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the CCR.

1.6 SEQUENCING AND SCHEDULING

1.6.1 Sequencing

Complete the following prior to starting Functional Performance Tests of mechanical and BMS systems:

a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

b. Performance Verification Tests of the controls systems have been completed and the Performance Verification Test Report has been submitted and approved in accordance with Specification Section

23 09 23.01 29 DIRECT DIGITAL CONTROL FOR HVAC, BACNET.

c. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report, and all TAB and DALT related submittals prerequisite to the TAB Report, have has been submitted and approved in accordance with Specification Section 23 05 93.01 00

TESTING, ADJUSTING, AND BALANCING FOR HVAC.

d. The building envelope is commissioned according to Section

01 91 19.01 00 EXTERIOR ENCLOSURE COMMISSIONING.

e. The Construction Checklists have been submitted and approved.

f . The Certificate of Readiness for mechanical systems has been submitted and approved.

SECTION 01 91 00.01 15 Page 9

Complete the following prior to starting Functional Performance Tests of the electrical and PCMS systems:

a. All electrical, power generation, and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

b. The building envelope is enclosed according to contract documents with final construction completed.

c. Ceiling tiles, floor coverings, and window coverings are in place.

d. The Certificate of Readiness for electrical systems has been submitted and approved.

e. Lamps have completed a minimum 100-hour burn-in period.

1.6.2 Project Schedule

Include the following tasks in the project schedule required by Section 01 32 01.01 10 PROJECT SCHEDULE. Ensure sufficient time is scheduled to accommodate the requirements of this specification section. The order of items listed below is not intended to imply a specified sequence:

a. Submission and approval of the Commissioning Firm and CCR.

b. Submission and approval of the Testing, Adjusting, and Balancing (TAB) Firm and TAB Specialist specified in Section 23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

c. Submission and approval of the Construction Phase Commissioning Plan.

d. Installation of permanent utilities (fuel oil, water, electric).

e. Building Envelope Construction.

f. Submission and approval of the Building Envelope Inspection Checklists.

g. Building Envelope Commissioning according to Section 01 91 19.01 00 EXTERIOR ENCLOSURE COMMISSIONING, including Air Barrier Pressure Tests specified in Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER

SYSTEM FOR AIR TIGHTNESS.

h. Drainage and Vent, Building Sewers, Water Supply Systems and Backflow Prevention Assembly Tests specified in Section 22 00 00.01 00

PLUMBING, GENERAL PURPOSE.

i. Factory Acceptance Testing for each of the systems to be commissioned as required by technical specifications. The Contractor shall notify the Government of factory testing for the equipment a minimum of 30 days in advance.

j. Manufacturer's Equipment Start-Up for each of the systems to be commissioned.

k. Potable Water System Flushing specified in Section 22 00 00.01 00

PLUMBING, GENERAL PURPOSE.

SECTION 01 91 00.01 15 Page 10

l. Operational Tests of the plumbing system specified in Section

22 00 00.01 00 PLUMBING, GENERAL PURPOSE.

m. Potable Water System Disinfection specified in Section 22 00 00.01 00

PLUMBING, GENERAL PURPOSE.

n. Submission and approval of the TAB Schematic Drawings, Report Forms, and Procedures specified in Section 23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

o. Submission and approval of Duct Air Leakage Test Procedures specified in Section 23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

p. Duct Air Leakage Test Execution specified in Section 23 05 93.01 00

TESTING, ADJUSTING, AND BALANCING FOR HVAC.

q. Submission and approval of the Final Duct Air Leakage Test Report specified in Section 23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING

FOR HVAC.

r. Testing, Adjusting, and Balancing (TAB) Field Work required by Section

23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

s. Submission and approval of the TAB Report specified in Section

23 05 93.01 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

t. TAB Field Acceptance Testing required by Section 23 05 93.01 00

TESTING, ADJUSTING, AND BALANCING FOR HVAC.

u. Submission and approval of the Start-Up Testing Report specified in Section 23 09 23.01 29 DIRECT DIGITAL CONTROL FOR HVAC, BACNET.

v. Submission and approval of the Performance Verification Test Procedures specified in Section 23 09 23.01 29 DIRECT DIGITAL CONTROL

FOR HVAC, BACNET.

w. Performance Verification Tests required by Section 23 09 23.01 29

DIRECT DIGITAL CONTROL FOR HVAC, BACNET.

x. Performance Verification Test Report specified in Section

23 09 23.01 29 DIRECT DIGITAL CONTROL FOR HVAC, BACNET.

y. Construction Checklist Submittal and activities, including:

(1) Installation checks.

(2) Startup, where required.

(3) Performance tests.

z. Functional Performance Testing for each system to be commissioned.

aa. Integrated Systems Tests.

bb. Post-Test Deficiency Correction for each system to be commissioned.

cc. Re-Testing.

dd. Endurance Tests.

SECTION 01 91 00.01 15 Page 11

ee. Training for each of the systems to be commissioned.

ff. Systems Manual, Maintenance Plan, and Service Life Plan submission and approval.

gg. Seasonal Testing.

hh. Submission and approval of the Start-Up Testing Report specified in Section 25 10 11.01 00 POWER CONTROL AND MONITORING SYSTEM (PCMS).

ii. Performance Verification Tests required by Section 25 10 11.01 00

POWER CONTROL AND MONITORING SYSTEM (PCMS).

jj. Performance Verification Test Report specified in Section

25 10 11.01 00 POWER CONTROL AND MONITORING SYSTEM (PCMS).

kk. Preliminary operation and maintenance manual submittals.

1.6.3 Phasing

See Section 01 11 00.01 00 SUMMARY OF WORK.

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

Submittals with an "S" designation following the “G” are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.01 00 SUSTAINABILITY REPORTING. Other designations following the "G" designation identify the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.01 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Commissioning Firm; G, C

Contractor's Commissioning Representative; G, C

Technical Commissioning Specialists; G, C

Overall Commissioning Schedule; G, C

Two-Week Look-Ahead Commissioning Schedules

SD-03 Product Data

Commissioning Plan Information; G, CS

SD-06 Test Reports

Construction Checklist Reviews; G, C

Issues Log; G, C

Instrumentation, Equipment, And Monitoring Devices; G, C

Test Results; G, C

SECTION 01 91 00.01 15 Page 12

SD-07 Certificates

Certificate of Readiness; G, C

SD-10 Operation and Maintenance Data

Training Plan; G, C

Training Attendance Rosters; G, C

Systems Manual; G, C

Maintenance and Service Life Plans; G, C

1.8 COMMISSIONING PLAN INFORMATION

Submit the following:

a. List of Contractor-appointed commissioning team members to include specific personnel and subcontractors to the performance of the various commissioning requirements.

b. Schedule of commissioning activities, integrated with the construction schedule. Comply with requirements in Section 01 32 01.01 10 PROJECT SCHEDULE for construction schedule general requirements for commissioning.

c. Contractor personnel and subcontractors to participate in each test.

d. List of instrumentation required for each test to include identification of parties that will provide instrumentation for each test.

e. Information and documentation in support of the creation and revision of the Construction Checklists and Functional Performance Test Checklists. Examples of the information required are described herein.

1.8.1 Commissioning Schedules

Provide an overall commissioning schedule and two-week look-ahead commissioning schedules.

1.9 COMMISSIONING FIRM

Provide a Commissioning Firm that is certified in commissioning by one of the following: the AABC Commissioning Group (ACG); the National Environmental Balancing Bureau (NEBB); the International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB), the Building Commissioning Association (BCA); the Association of Energy Engineers (AEE). The Commissioning Firm may employ a commissioning professional certified by the University of Wisconsin-Madison or the American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) as required in paragraph CONTRACTOR'S COMMISSIONING REPRESENTATIVE as an alternative to certification of the Commissioning Firm. The Commissioning Firm must be certified in all systems to be commissioned to the extent such certifications are available from the certifying body. Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed Commissioning Firm or Contractor's Commissioning

SECTION 01 91 00.01 15 Page 13

Representative in detail. Any firm or commissioning professional that has been the subject of disciplinary action by the certifying body within the five years preceding contract award is not eligible to perform any duties related to commissioning.

a. Submit the Commissioning Firm's certification of qualifications including the name of the firm and certifications no later than 30 calendar days after Notice to Proceed.

b. The Commissioning Firm's and Contractor's Commissioning Representative's certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the firm or a specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Firm or Commissioning Specialist for approval. All work specified in this specification section performed by the Commissioning Firm or associated Contractor's Commissioning Representative is invalid if the Commissioning Firm or Contractor's Commissioning Representative loses its certification prior to contract completion and must be performed by an approved successor.

c. The Commissioning Firm must oversee and assist the General or Prime Contractor with the work specified herein.

d. The Commissioning Firm may act as the Pressure Test Agency required by Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all qualification requirements of that specification section are met.

1.9.1 Contractor's Commissioning Representative

The Commissioning Firm must provide a Contractor's Commissioning Representative (CCR) that has a minimum of five years of commissioning experience, including two projects of similar size and complexity, and that is one of the following: a NEBB qualified Systems Commissioning Administrator (SCA); ACG Certified Commissioning Authority (CxA);

ICB/TABB Certified Commissioning Supervisor; BCA Certified Commissioning Professional (CCP); AEE Certified Building Commissioning Professional (CBCP); University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP); ASHRAE Commissioning Process Management Professional

(CPMP).

a. Submit the CCR's certification of qualifications including the name of the specialist and firm; certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed.

b. The CCR's certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another CCR for approval. All work specified in this specification section to be performed by the CCR is invalid if the CCR loses its certification prior to contract completion and must be performed by an approved successor.

c. The CCR must lead and oversee the commissioning work specified herein and be the primary point of contact for the Government regarding the commissioning work.

SECTION 01 91 00.01 15 Page 14

1.9.2 Technical Commissioning Specialists

Technical Commissioning Specialists, employed by the Commissioning Firm and that have the following qualifications, must perform the technical work specified herein associated with each system to be commissioned. The CCR may perform these roles if they are so qualified.

a. The technical work associated with mechanical systems including Heating, Ventilating, Air Conditioning, and Refrigeration Systems;

Building Automation System; Utility Monitoring and Control System;

Service Water Heating Systems; Plumbing Systems; Compressed Air and Vacuum Systems; Energy and Water Utility Metering Systems must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, AEE, University of Wisconsin-Madison, ASHRAE, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.

b. The technical work associated with low-voltage electrical systems including Lighting Systems; Power Distribution Systems; and Power Generation Systems must be performed by an engineering technician certified by the National Electrical Testing Association (NETA) or the National Institute for Certification in Engineering Technologies (NICET) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

c. The technical work associated with medium and high-voltage electrical systems including Power Distribution Systems and Power Generation Systems must be performed by an engineering technician certified by the National Electrical Testing Association (NETA) or the National Institute for Certification in Engineering Technologies (NICET) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices and having field experience with at least three prior projects dealing with medium-voltage or high-voltage switchgear and substations.

d. The technical work associated with telecommunications systems including Outside Plant Distribution Systems and Building Telecommunications Cabling Systems must be performed by cabling installers certified by the Building Industry Consulting Services International (BICSI) at the Technician level or have 5 years documented experience in the installation, inspecting, testing, and calibrating of the specified copper and fiber optic cables and components. Technical work associated with the Cable Television Premises Distribution System must be performed by cabling installers having 5 years documented experience in the installation, inspecting, testing, and calibrating of the specified cables and components.

e. The technical work associated with the Building Envelope system must be performed by a registered architect with five years of building envelope design or construction experience. The Commissioning Firm team member with the required experience related to the building envelope may act as the Air Barrier Inspector required by Section

07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR

TIGHTNESS provided that all qualification requirements of that specification section are met. The Commissioning Firm team member with the required experience related to the building envelope may act as the thermographer required by Section 07 05 23.01 00 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all of

SECTION 01 91 00.01 15 Page 15 the qualification requirements of that specification section are met.

f. Submit the Technical Commissioning Specialist's certification of qualifications including the name of the specialist and firm;

certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed.

1.9.3 Commissioning Standard

Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline , NEBB Commissioning Standard , SMACNA 1429, or ASHRAE 202. Comply with applicable NETA and NICET testing standards for electrical systems.

a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.

b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.

c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.

d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract .

e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.

f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.

1.10 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)

The CCR must execute and document the commissioning activities required of the Commissioning Authority for the purposes of complying with the Third Party Certification (TPC) requirements for the project in accordance with Section 01 33 29.01 00 SUSTAINABILITY REPORTING. Provide all commissioning documentation required to meet the TPC requirements.

1.11 CONSTRUCTION CHECKLIST REVIEWS

Draft construction checklists created by CxA will be provided for Contractor review prior to creation and distribution of the final Construction Checklists. Final versions will incorporate Contractor comments and information on approved submittals.

Provide comments on material, installation, and performance test checklists for systems, assemblies, subsystems, equipment, and components to be part of the Cx process and according to requirements in this Section.

SECTION 01 91 00.01 15 Page 16

Construction Checklists shall include, but are not limited to, installation checks, startup, performance test, and performance test demonstration as described in the technical specifications.

1.12 ISSUES LOG

The CCR must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through commissioning review, inspection, and testing. Include the date of final resolution of issues as confirmed by the CxC. Submit the Issues Log to the Contracting Officer's Representative on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the CCR for inclusion into the Issues Log.

Track construction deficiencies identified in the Issues Log using QCS as specified in Specification Section 01 45 00.01 10 QUALITY CONTROL SYSTEM

(QCS).

1.13 CERTIFICATE OF READINESS

Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness for the system certifying that the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Building Envelope Inspection Checklists; completed Construction Checklists; Testing, Adjusting, and Balancing (TAB) Report; BMS Start-Up Reports; and the Air Leakage Test Reports and Diagnostic Test Reports to the extent applicable to the system. The Contractor; the CCR; the applicable Commissioning Specialist; the Contractor's Quality Control Representative; the Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness. Submit the Certificate of Readiness for each system no later than 14 calendar days prior to Functional Performance Tests of that system. Do not schedule Functional Performance Tests for a system until the Certificate of Readiness for that system receives approval by the Government.

1.14 GENERAL TEST REPORTING REQUIREMENTS

Documentation of instrumentation, equipment, other tools, and results for commissioning tests to be submitted under other specification sections shall comply with the requirements below.

1.14.1 Instrumentation, Equipment, and Monitoring Devices

List test instrumentation, equipment, and monitoring devices. Include the following information:

a. Make, model, serial number, and application for each instrument, equipment, and monitoring device.

b. Brief description of intended use.

c. Calibration record showing the following:

(1) Calibration agency, including name and contact information.

SECTION 01 91 00.01 15 Page 17

(2) Last date of calibration.

(3) Range of values for which calibration is valid.

(4) Certification of accuracy.

(5) N.I.S.T. traceability certification for calibration equipment.

(6) Due date of the next calibration.

1.14.2 Test Results

1.14.2.1 Pre-Startup Report

Prior to startup of equipment or a system, submit signed, completed construction checklists.

1.14.2.2 Test Data Reports

At the end of each day in which tests are conducted, submit test data for tests performed.

1.14.2.3 Commissioning Issues Reports

Daily, at the end of each day in which tests are conducted, submit commissioning issue reports for tests for which acceptable results were not achieved.

1.14.2.4 Weekly Progress Report

Weekly, at the end of each week in which tests are conducted, submit a progress report.

1.14.2.5 Data Trend Logs

Submit data trend logs at the end of the trend log period.

1.14.2.6 System Alarm Logs

Daily, at the start of days following a day in which tests were performed, submit print-out of log of alarms that occurred since the last log was printed.

1.15 OPERATION AND MAINTENANCE DATA

Provide data for proprietary test equipment, instrumentation, and tools used in the commissioning process to include in operation and maintenance manuals as listed in each commissioning specification section.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

3.1 GENERAL EXECUTION REQUIREMENTS

Schedule and coordinate commissioning with the construction schedule.

Perform activities identified in construction checklists, including tests, SECTION 01 91 00.01 15 Page 18 and document results of actions as construction proceeds.

Perform tests in presence of Owner's witness. Unless otherwise indicated, Owner shall witness tests for 100 percent of work to which the test applies. Report test data and commissioning issue resolutions.

The Contractor shall notify the Government of factory testing for the below equipment at a minimum of 30 days in advance. A determination will be made at that time if a Government Representative will witness the factory testing.

a. Temporary generator module - complete.

b. Substation - complete.

c. 138kV transformer.

d. SSUPS.

e. HEMP filters (or a sample of the tests).

Schedule personnel to participate in and perform Commissioning-Process Work.

3.1.1 Commissioning Team

At the time of construction contract award, the Contractor shall provide the services of a Contractor's Commissioning Representative (CCR) with defined roles and responsibilities herein and as outlined in the Commissioning Plan (CP) consistent with Annex F of ASHRAE Guideline 0 .

The CCR shall be an employee of an independent subcontractor (Cx Firm).

The CCR will communicate and report directly to the Government's commissioning team in execution of commissioning activities.

Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. Provide additional commissioning technical support in the form of a Technical Commissioning Specialist for complex, specialized, and multi-discipline systems as required. Substitutes must be approved by the Contracting Officer's Representative .

The Government, in its capacity as the Commissioning Authority (CxA), shall oversee and assure the execution of commissioning process activities from design through post occupancy/warranty phase to assure the Facility Requirements (FRD) are achieved and the Basis of Design (BoD)is validated. The Contracting Officer's Representative (COR) will act as the Owner's representative in performance of duties spelled out under OWNER in Annex F of ASHRAE Guideline 0 and ASHRAE Guideline 1.1 .

The commissioning team comprises the following groups:

a. Members Appointed by Contractor(s):

(1) Contractor's Commissioning Representative (CCR): An employee of the Cx Firm who manages, schedules, and coordinates commissioning.

(2) Project superintendent and other employees relevant for a

SECTION 01 91 00.01 15 Page 19 particular portion of the commissioning.

(3) Subcontractors, installers, suppliers, and technical commissioning specialists relevant for a particular portion of the commissioning.

(4) Appointed team members shall have the authority to act on behalf of the entity they represent.

b. Members Appointed by the Government:

(1) Commissioning authority, plus consultants relevant for a particular portion of the commissioning.

(2) Government representative(s), facility operations and maintenance personnel, plus other employees, separate contractors, and consultants relevant for a particular portion of the commissioning.

(3) Architect/Engineer, plus employees and consultants relevant for a particular portion of the commissioning.

3.1.1.1 Example Construction Checklist Team

The following team members typically participate in Construction Checklist inspections:

Group Function

Contractor Contractor's Commissioning Representative (CCR)

Contractor Contractor's Commissioning Specialist for (Example) System

Contractor Installing Subcontractor for (Example) System

Contractor Manufacturer's Representative for (Example) System

Contractor Contractor's Quality Control Personnel

Government Contracting Officer's Quality Assurance Representative

Government Contracting Officer's Representative

Government CxA or Commissioning Specialist for Government (CxG)

Government Designer(s) of Record (DOR)

3.1.1.2 Example Functional Performance Test Checklist Team

The following team members typically participate in Functional Performance Testing:

Group Function

Contractor Contractor's Commissioning Representative (CCR)

SECTION 01 91 00.01 15 Page 20

Group Function

Contractor Contractor's Commissioning Specialist for (Example) System

Contractor Installing Subcontractor for (Example) System

Contractor Manufacturer's Representative for (Example) System

Contractor BMS or PCMS Contractor, as applicable

Government Contracting Officer's Quality Assurance Representative

Government Contracting Officer's Representative

Government CxA or Commissioning Specialist for Government (CxG)

Government Designer(s) of Record (DOR)

Government User Representatives

Government Facility Operators and Maintainers

3.1.2 Contractor's Commissioning Representative (CCR) Responsibilities

Manage, schedule, and coordinate commissioning, including, but not limited to, the following tasks:

a. Coordinate with subcontractors on their commissioning responsibilities and activities.

b. Obtain, assemble, and submit commissioning documentation.

c. Conduct periodic on-site commissioning meetings.

d. Develop and maintain the commissioning schedule. Integrate commissioning schedule into the construction schedule. Update schedule at specified intervals.

e. Review and comment on preliminary test procedures and data forms.

f. Report inconsistencies and issues in system operations.

g. Verify that performance tests have been completed and results comply with acceptance criteria, and that equipment and systems are ready, before scheduling functional tests.

h. Direct and coordinate tests.

i. Coordinate witnessing of tests by Owner's witness.

j. Coordinate and manage training. Be present during training sessions to direct video recording, present training and direct the training presentations of others.

k. Prepare and submit specified commissioning reports.

SECTION 01 91 00.01 15 Page 21

l. Track commissioning issues until resolution and retesting is successfully completed.

m. Retain original records of Commissioning-Process Work, organized as required for the commissioning report. Provide Owner's representative access to these records on request.

n. Assemble and submit materials for commissioning report.

3.1.3 Installing Contractor Responsibilities

Installing contractors' commissioning responsibilities include, but are not limited to, the following:

a. Operating the equipment and systems they install during tests.

b. Assisting as required in tests of equipment and systems with which their work interfaces.

c. Appoint a commissioning representative to be part of the commissioning team.

3.2 COMMISSIONING PLANS

3.2.1 Design Phase Commissioning Plan

A commissioning plan developed during design phase will be provided for information only. The design phase commissioning plan does not form a part of this contract and is provided for commissioning review purposes only.

3.2.2 Interim Construction Phase Commissioning Plan

The Commissioning Specialist for the Government (CxG) will prepare the Interim Construction Phase Commissioning Plan.

The Plan identifies the commissioning and testing standards and outlines the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, and documentation requirements for the construction phase of the project.

In addition, the following is included in the Interim Construction Phase Commissioning Plan:

a. Plan purpose

b. Commissioning scope

c. Systems to be commissioned

d. Examples and description…