AM#10 READY TO ADVERTISE CLR039a LRDR - Construction Package #1 -Clear AFS, Alaska
SECTION 01 50 00.01 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
FOUNDATION FOR CROSS-CONNECTION CONTROL AND HYDRAULIC RESEARCH
(FCCCHR)
FCCCHR List (continuously updated) List of Approved Backflow Prevention Assemblies
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.01 00 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.01 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan; G
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval will not be acceptable.
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by
SECTION 01 50 00.01 00 Page 2
READY TO ADVERTISE
the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with any company participating in any other phase of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Immediately upon beginning of work, provide a weatherproof glass-covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer.
2.1.2 Project and Safety Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 00.01 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this contract. Construct with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic are be avoided. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.2.3 Fencing
Provide fencing along the construction site at all open excavations and
SECTION 01 50 00.01 00 Page 3 tunnels to control access by unauthorized people.
a. The safety fencing must be a high visibility orange colored, high density polyethylene grid or approved equal, a minimum of 48 inches high and maximum mesh size of 2 inches, supported and tightly secured to steel posts located on maximum 10 foot centers, constructed at the approved location. Install fencing to be able to restrain a force of at least 250 pounds against it.
b. The Contractor may choose to fence portions of the laydown area or worksite. Remove the fence upon completion and acceptance of the work.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Employee parking is limited. Contractors will limit POVs at Clear AFS.
Vehicle entering Clear AFS must comply with the process and the restrictions described in 01 19 03.01 29 SPECIAL ITEMS.
3.2 TEMPORARY BULLETIN BOARD
Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.
3.3 AVAILABILITY AND USE OF UTILITY SERVICES
3.3.1 Temporary Utilities
The Contractor will provide temporary utilities required for construction, construction job site trailers, and laydown area. Materials may be new or used, must be adequate for the required usage, will not create an unsafe condition, and will not violate applicable codes or standards.
The Contractor is responsible for extending power from the point of connection at pole 7-2 to service CP#1, CP#2, CP#3, CP#5 project office locations, providing a transformer and distribution panel that is capable of serving 13 construction trailers with the capability to expand. The Contractor is also responsible for AM#10... providing a three-phase load break disconnect to be manually operated from grade between Pole 8 and first construction/laydown area power use, fuse protection if reduction in line size downstream of Pole 8, and ...AM#10 extending power from the point of connection at pole 8 to CP#1, CP#2, CP#3, & CP#5 laydown areas, and LRDR CP#1, CP#2, CP#3, CP#5 construction power. The Contractor shall terminate each power location for future contracts with a disconnect. The installation shall follow the general layout on sheet E-100101A and sheet G-100005A. The LRDR CP#1, CP#2, CP#3, CP#5 (construction, job site trailers, laydown areas) temporary power shall be turned over to the Government 1 May 2018. The Contractor shall provide a one-year warranty on the installation, parts, and materials from the date the power is turned over to the Government. CP#2 and CP#5 contractors will jointly use the construction, project office, and laydown area power after 1 May 2018.
The power at pole 7-1 and 8 is overhead and is a 4160/2400V, 3 phase, 4 wire line. The available demand load for LRDR CP#1, CP#2, CP#3, CP#5 contractors is 350 kVA. The Contractor shall provide all overhead/underground lines, transformers, panels, fusible disconnects switches to protect the overhead line. AM#006... The Government is metering electrical demand and total energy usage of the entire temporary
SECTION 01 50 00.01 00 Page 4 feeder from the existing Clear Air Force Substation as shown on sheet E-100101A. Additional metering of the construction power extensions from the existing line is not required. ...AM#006
The Contractor shall provide fuel to heat the MCF during commissioning and until the facility is turned over to the Government.
3.3.2 AM#006...Availability ...AM#006 and Payment for Utility Services
a. Base Utilities are not available except for Power. The Government will make reasonable amounts of power available at no charge.
b. The contractor may install water wells to establish a well point for dust control, batch plant, or material processing. Locations are identifies on the plans. Wells will be decommissioned at the completion of work in accordance with base and State guidance.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times within the composite area. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
d. The CP#1 Contractor will establish a one-way traffic pattern at a date when significant construction traffic begins, NLT 30 July 17. "B" Street will become one-way East and traffic routed clockwise along Loop Road and "E" Street. The CP#1 Contractor will provide necessary signage and coordinate through the contracting officer or resident engineer to the 213th SWS Security Forces.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.
3.4.3 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Treat dust abatement on access roads with applications of calcium chloride, water sprinklers, or similar methods or treatment.
SECTION 01 50 00.01 00 Page 5
3.5 CONTRACTOR'S TEMPORARY FACILITIES
3.5.1 Safety
Protect the integrity of any installed safety systems or personnel safety devices. If entrance into systems serving safety devices is required, the Contractor must obtain prior approval from the Contracting Officer. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.5.2 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.5.3 Storage Area/Laydown Area
Contractor Laydown Area is designated on the contract plans. The contractor may choose to construct a temporary fence around trailers and materials to delineate and secure materials.
3.5.4 Appearance of Trailers
a. Trailers utilized by the Contractor for administrative or material storage purposes must present a clean and neat exterior appearance and be in a state of good repair. Trailers which, in the opinion of the Contracting Officer, require exterior painting or maintenance will not be allowed on installation property.
3.5.5 Maintenance of Storage Area
a. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles; gravel gradation will be at the Contractor's discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.
b. Cut grass (or annual weeds) within the construction and storage sites to a maximum 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around fences at time of grass cutting. Maintain grass or weeds on stockpiled earth as descried above.
3.6 GOVERNMENT FIELD OFFICE
3.6.1 Government Field Office
Provide and install a furnished Government Field Office adjacent to the Contractor's job offices at the location indicated. Furnishings and quality will be similar to those of the contractor. The Government Field
SECTION 01 50 00.01 00 Page 6
Office may be a single or multiple relocatable units. If multiple units are used, an enclosed walkway will be provided. The Government Field Office may be connected to the contractor office complex but will be separate and securable. Minimum requirements will include:
a. One securable hard Office with adjustable height desk, ergonomic chair, 3'x4' white board, filing cabinet, bookshelf.
b. One Conference Room - w/12 person conference table, overhead projector screen, white board, data outlets.
c. One Small Conference Room - 4 person conference table, white board, data outlet.
d. Eight Work Stations with acoustic dividers, adjustable height desk, ergonomic chair, and 3' x 4' white board, filing cabinet, and bookshelf.
e. Wired to support government furnished and installed IT equipment.
Contractor responsible for internet service.
f. File Storage/Drawing Area with Plan Table.
g. Break Area with fridge/microwave/sink.
h. Space and data connection for government furnished multi-functional printers and supply storage.
i. Dedicated Restroom Facilities of a style and type similar to the contractor.
j. Parking for eight Government owned vehicles parking with head bolt heater outlets.
i. Arctic Entry
The contractor shall maintain, repair and provide custodial service for Government Field Office. Location to be coordinated with and approved by the Contracting Officer prior to Contractor mobilizing to site. The Contractor shall be responsible for utility services throughout the Contract.
At completion of the project, the office will remain the property of the Contractor and be removed from site. Exterior power connections, lighting and site improvements may remain at the description of the contracting officer.
3.6.2 Trailer-Type Mobile Office
The Contractor may, at its option, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer and providing as a minimum the facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds.
AM#006... ...AM#006
3.7 DUMPSTERS
Equip dumpsters with a secure cover and paint the standard installation
SECTION 01 50 00.01 00 Page 7 color. Keep dumpster closed, except when being loaded with trash and debris. Locate dumpsters behind the construction fence or out of the public view. Empty site dumpsters at least once a week, or as needed to keep the site free of debris and trash.
3.8 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.9 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence that will become the property of the Contractor.
Restore areas used by the Contractor for the storage of equipment or material, or other use to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --