Questions and Answers 3.pdf
PDF 225 KB Posted
- Attached to
- CONSTRUCT F-35 ALTER BUILDING 400 AMXS Federal contract opportunity
- Solicitation number
- W50S9F-22-R-0006
- Issued by
- Department of the Army National Guard
About this file
This document contains a questions and answers file and a federal contract opportunity notice for construction services. The federal contract opportunity is to construct and alter Building 400 at Dane County Regional Airport - Truax Field in Madison, Wisconsin to accommodate F-35 operations for the 115th Fighter Wing. Scope of work includes demolishing and rebuilding administration and maintenance areas, adding two elevators, upgrading power, HVAC, fire suppression, and fall protection systems. The project has a magnitude between $10-25 million, a 450 day performance period, and NAICS code 236220. The pre-proposal conference will be on April 7, 2022, and the solicitation closing date is May 5, 2022. The source selection will evaluate technical, past performance, and price factors. The government intends to award without discussions to vendors registered in the System for Award Management.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # W50S9F22R0006 Posted to SAM.Gov 21 Mar 22
Questions & Responses #3
1. Question: Is this job taxable?
Response: No, Prime Contractor will be provided with supporting documentation
2. Question: Please clarify discrepancy. Slides 14 and 16 of the pre-proposal conference slides indicate to include the Performance Relevancy Questionnaire in Volume I as well as Volume II. However, the response to question 8 in “Questions & Response #1” indicate to only place the Performance Relevancy Questionnaire in Volume II.
Response: Follow guidance from Q&A response.
3. Question: There were discussions at the Site Walk that updated drawings would be issued as the Fire
Suppression System would be changing. Please advise on the timeline of the amendment and due date.
Response: Fire Suppression drawings are being finalized and will be posted to SAM as soon as possible.
Due Date is TBD.