This document provides details for a federal solicitation seeking construction services. The solicitation will result in a single award contract to alter Building 400 at Truax Field in Madison, Wisconsin to accommodate F-35 operations for the 115th Fighter Wing. Scope of work includes demolishing and rebuilding administration and maintenance areas, adding two elevators, and upgrading electrical, HVAC, fire suppression and lightning protection systems. The project has a magnitude between $10-25 million and must meet USGBC standards. The solicitation closes May 5th, 2022 and includes a base CLIN for construction and optional CLINs for communications and aircraft power. The contracting agency is the Department of the Army National Guard.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
h:\prj\2020\20203320\08-submissions\2022_05_06_add 2\fsb2020-332-00_wi-ang_b400_add no. 02_2022.05.06_narrative.docx Page 1 of 4
5801 Broadway Extension, Suite 500 Oklahoma City, OK 73118-7436
405.840.2931 | fsb-ae.com
ADDENDUM NO. 02
Date: 6 May 2022
To: ALL BIDDERS OF RECORD
From: Frankfurt-Short-Bruza Associates, P.C.
5801 N. Broadway Ext., Suite 500 Oklahoma City, OK 73118
Subject: XGFG182009: F-35: Alter Building 400 AMXS, WI/ANG, Truax Field, Madison, WI
FSB Project No.: FSB2020-332-00
NOTE: This Addendum forms a part of the Contract Documents and modifies the Original Documents dated 21 January 2022.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.
ATTACHMENTS
Items in this addendum take precedence over the original bid documents. Items not specifically revised remain in effect. This addendum consists of (4) pages and the following attachments:
Specifications:
PROJECT TABLE OF CONTENTS
01 14 00 – WORK RESTRICTIONS
01 32 01.00 10 – PROJECT SCHEDULE
01 91 00.15 10 – TOTAL BUILDING COMMISSIONING
03 30 00 – CAST-IN-PLACE CONCRETE
09 65 00 – RESILIENT FLOORING
Drawings:
SB101 – FOUNDATION AND SLAB PLAN
SF102 – ROOF FRAMING PLAN
AD200 – BUILDING ELEVATIONS - DEMOLITION
A-500 – DOOR AND WINDOW DETAILS
A-501 – ROOF DETAILS
MD101 – MECHANICAL DEMOLITION PLAN-FIRST FLOOR-SECTOR-A
MD102 – MECHANICAL DEMOLITION PLAN-FIRST FLOOR-SECTOR-B
MD202 – MECHANICAL DEMOLITION PLAN-SECOND FLOOR-SECTOR-B
EP111 – ELECTRICAL FIRST FLOOR POWER PLAN – SECTOR A
EP601 – ELECTRICAL POWER ONE-LINE DIAGRAM
FSB | DefineDesignDeliver
MODIFICATIONS TO THE CONDITIONS OF THE CONTRACT
None.
MODIFICATIONS TO THE SPECIFICATIONS
ITEM 01.2-1 Refer to attached Project Table of Contents, dated 6 May 2022:
A. Project Table of Contents is hereby revised and re-issued in its entirety to incorporate changes noted as part of this Addendum related to specifications included on the project. Replace Project Table of Contents dated 2 May 2022 with attached revised Project Table of Contents dated 6 May 2022.
ITEM 01.2-2 Refer to attached Specification Section 01 14 00 – WORK RESTRICTIONS, dated 6 May 2022:
A. Specification Section 01 14 00 is hereby revised and re-issued in its entirety to reduce requirements for application of work outside regular hours from 15 calendar days to 5 calendar days in Subpart 1.3.3 Work Outside Regular Hours;
to strike last sentence related to utility cutovers in Subpart 1.3.3 Work Outside Regular Hours; and to revise list item ‘a’ in Subpart 1.3.4 Utility Cutovers and Interruptions. Replace Section 01 14 00 dated 2 May 2022 with attached revised Specification Section 01 14 00 dated 6 May 2022.
ITEM 01.2-3 Refer to attached Specification Section 01 32 01.00 10 – PROJECT SCHEDULE, dated 6 May 2022:
A. Specification Section 01 32 01.00 10 is hereby revised and re-issued in its entirety to provide updated requirements for timing of the submission of Preliminary Project Schedule in Subpart 3.4.1. Replace Section 01 32 01.00 10 dated 2 May 2022 with attached revised Specification Section 01 32 01.00 10 dated 6 May 2022.
ITEM 01.2-4 Refer to Specification Section 01 91 00.15 – TOTAL BUILDING COMMISSIONING, dated 21 January 2022:
A. Specification Section 01 91 00.15 is hereby deleted in its entirety to strike all requirements included in this specification from the project. Remove Section 01 91 00.15 dated 21 January 2022 from the contract documents.
ITEM 01.2-5 Refer to attached Specification Section 01 91 00.15 10 – TOTAL BUILDING COMMISSIONING, dated 6 May 2022:
A. Specification Section 01 91 00.15 10 is hereby issued in its entirety to provide requirements for building commissioning on the project.
ITEM 01.2-6 Refer to attached Specification Section 03 30 00 – CAST-IN-PLACE CONCRETE, dated 6 May 2022:
A. Specification Section 03 30 00 is hereby revised and re-issued in its entirety to modify requirements for concrete mix design strength in Subpart 2.3.1.5; to provide an allowance for the use of Class C fly ash in place of Class F fly ash in Subpart 2.4.1.1; to provide an allowance for the use of Type 1L blended cement in Subpart 2.4.1.6; and to provide an allowance for the use of aggregates that meet WisDOT standards and requirements for expansion in Subpart 2.4.3.
Replace Section 03 30 00 dated 21 January 2022 with attached revised Specification Section 03 30 00 dated 6 May 2022.
ITEM 01.2-7 Refer to attached Specification Section 09 65 00 – RESILIENT FLOORING, dated 6 May 2022:
A. Specification Section 09 65 00 is hereby revised and re-issued in its entirety to provide updated requirement for wall-base type in Subpart 2.2 Wall Base. Replace Section 09 65 00 dated 21 January 2022 with attached revised Specification Section 09 65 00 dated 6 May 2022.
MODIFICATIONS TO THE DRAWINGS
ITEM 01.3-1 Refer to attached Sheet SB101 – FOUNDATION AND SLAB PLAN, dated 6 May 2022:
A. Sheet SB101 is hereby revised and re-issued in its entirety to remove “BY OTHERS” language from callout for antenna tower. Replace Sheet SB101 dated 2 May 2022 with attached revised Sheet SB101 dated 6 May 2022.
ITEM 01.3-2 Refer to attached Sheet SF102 – ROOF FRAMING PLAN, dated 6 May 2022:
A. Sheet SF102 is hereby revised and re-issued in its entirety to remove “BY OTHERS” language from callout for antenna tower. Replace Sheet SF102 dated 2 May 2022 with attached revised Sheet SF102 dated 6 May 2022.
ITEM 01.3-3 Refer to attached Sheet AD200 – BUILDING ELEVATIONS – DEMOLITION, dated 6 May 2022:
A. Sheet AD200 is hereby revised and re-issued in its entirety to provide additional clarification on mechanical components to be included in demolition and requirements for infill of areas affected by demolition of mechanical components. Replace Sheet AD200 dated 21 January 2022 with attached revised Sheet AD200 dated 6 May 2022.
ITEM 01.3-4 Refer to attached Sheet A-500 – DOOR AND WINDOW DETAILS, dated 6 May 2022:
A. Sheet A-500 is hereby revised and re-issued in its entirety to provide Detail C4/A-500 that includes requirements for infill of areas affected by demolition of mechanical components. Replace Sheet A-500 dated 2 May 2022 with attached revised Sheet A-500 dated 6 May 2022.
ITEM 01.3-5 Refer to attached Sheet A-501 – ROOF DETAILS, dated 6 May 2022:
A. Sheet A-501 is hereby revised and re-issued in its entirety to provide Detail C3/A-501 that includes requirements for skylight curbs. Replace Sheet A-501 dated 21 January 2022 with attached revised Sheet A-501 dated 6 May 2022.
ITEM 01.3-6 Refer to attached Sheet MD101 – MECHANICAL DEMOLITION PLAN-FIRST FLOOR-SECTOR-A, dated
A. Sheet MD101 is hereby revised and re-issued in its entirety to provide additional clarification on mechanical components to be included in demolition. Replace Sheet MD101 dated 2 May 2022 with attached revised Sheet MD101 dated 6 May 2022.
ITEM 01.3-7 Refer to attached Sheet MD102 – MECHANICAL DEMOLITION PLAN-FIRST FLOOR-SECTOR-B, dated
A. Sheet MD102 is hereby revised and re-issued in its entirety to provide additional clarification on mechanical components to be included in demolition. Replace Sheet MD102 dated 2 May 2022 with attached revised Sheet MD102
ITEM 01.3-8 Refer to attached Sheet MD202 – MECHANICAL DEMOLITION PLAN-SECOND FLOOR-SECTOR-B, dated
A. Sheet MD202 is hereby revised and re-issued in its entirety to provide additional clarification on mechanical components to be included in demolition. Replace Sheet MD202 dated 2 May 2022 with attached revised Sheet MD202
ITEM 01.3-9 Refer to attached Sheet EP111 – ELECTRICAL FIRST FLOOR POWER PLAN – SECTOR A, dated
A. Sheet EP111 is hereby revised and re-issued in its entirety to provide additional clarification on Optional Line Item (OLI) #2 included in Sheet Keynote 8. Replace Sheet EP111 dated 2 May 2022 with attached revised Sheet EP111
ITEM 01.3-10 Refer to attached Sheet EP601 – ELECTRICAL POWER ONE-LINE DIAGRAM, dated 6 May 2022:
A. Sheet EP601 is hereby revised and re-issued in its entirety to provide additional clarification on Optional Line Item
(OLI) #2 included in Sheet Keynote 6. Replace Sheet EP601 dated 2 May 2022 with attached revised Sheet EP601
BIDDER RFI RESPONSES
ITEM 01.4-1 Refer to attached document – BID RFI QUESTIONS AND RESPONSES, dated 6 May 2022, for responses to Bid RFI Questions received by the A/E as of 4 May 2022.
SUSTITUTION REQUESTS
None.
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
GENE O.
BROWN
E-47748
OKLAHOMA CITY
OK
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
JOHN B.
SEMTNER
E-47742
OKLAHOMA CITY
OK
5/6/2022
W
IS C O NS IN
P R
O F
E
S S I O N A L
E N G
I N E
E R
JOHN T
LITTLE
E-47833
EDMOND
OK
W
IS C O NS IN
A R C H I T E C T
JASON T.
HOLUBY
A-13101
OKLAHOMA CITY
OK
File details come from the government source that posted it. Updated .