Questions and Answers 03.pdf

PDF 180 KB Posted

Attached to
Construct Medical Readiness Facility Federal contract opportunity
Solicitation number
W50S9F22R0001
Issued by
Department of the Army National Guard

About this file

This document outlines a solicitation for construction services. The 115th Fighter Wing at Dane County Regional Airport -Truax Field, Madison, WI is seeking proposals to construct an 18,650 square foot Medical Readiness facility for $5-10 million under a single firm fixed-price contract. The scope of work includes site utilities, grading, erecting precast concrete panels, and new mechanical, electrical, plumbing and technology systems. Offerors may also bid on 9 separate options such as permeable pavers, asphalt, interior finishes, and demolition of existing buildings. The contract period is 450 days from notice to proceed. A pre-proposal conference will be held on March 31st and proposals are due by May 5th. The evaluation criteria are technical, past performance, and price. The source selection will be conducted according to FAR Part 15.3 and DFARS Part 215.3.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Medical Readiness Facility, newest first.
File Type Posted
SECTION 26 0573.19 ARC FLASH HAZARD ANALYSIS.pdf PDF
074213 23 compo wall panel.pdf PDF
Questions and Answers 05 R1.pdf PDF
Questions and Answers 04 R1.pdf PDF
60613250_WIANG_TRUAX-MED-E_v19 - Sheet - E-601 - ELECTRICAL SCHEDULES.pdf PDF
W50S9F-22-R-0001_0004.pdf PDF
Questions and Answers 05.pdf PDF
Questions and Answers 04.pdf PDF
W50S9F-22-R-0001_0003.pdf PDF
Bldg_311 Floor Layout.pdf PDF
Photograph Log.docx DOCX document
Bldg_307 Floor Layout.pdf PDF
DEMO PLAN BLDG 311.pdf PDF
Questions and Answers 01.pdf PDF
Questions and Answers 02.pdf PDF
W50S9F-22-R-0001_0002.pdf PDF
Site Visit Sign In Log.pdf PDF
Pre-Proposal Slides - Medical Readiness.pdf PDF
Pre-Proposal Conference Minutes.pdf PDF
W50S9F-22-R-0001_0001.pdf PDF
ATTACHMENT 03_DRAWINGS Project No. XGFG139001 dated 14 MAY 2021.pdf PDF
ATTACHMENT 05_B307 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019.pdf PDF
ATTACHMENT 09_SAP SINGLE SOURCE DETERMINATION MONACO.pdf PDF
ATTACHMENT 10_SAP SINGLE SOURCE DETERMINATION MARSHALL BEST.pdf PDF
ATTACHMENT 12 PRE PROPOSAL SITE VISIT_DROP OFF INSTRUCTIONS.pdf PDF
EXHIBIT D PAST PERFORMANCE REFERENCE QUESTIONNAIRE.docx DOCX document
EXHIBIT E SMALL BUSINESS PARTICIPATION PLAN FORMAT.docx DOCX document
ATTACHMENT 01_PLANS AND SPECIFICATIONS Vol 1 Project No. XGFG139001 dated 08 Jul 2021.pdf PDF
ATTACHMENT 02_PLANS AND SPECIFICATIONS Vol 2 Project No. XGFG139001 dated 08 Jul 2021.pdf PDF
ATTACHMENT 04_GEOTECHNICAL ENGINEERING REPORT Project No. XGFG139001 dated 08 Nov 2019.pdf PDF
ATTACHMENT 06_B311 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019.pdf PDF
ATTACHMENT 07_SAP SINGLE SOURCE DETERMINATION ADVANTOR.pdf PDF
ATTACHMENT 11_SFS FORM 12.xlsx XLSX spreadsheet
EXHIBIT A PERFORMANCE RELEVANCY QUESTIONNAIRE AND SPECIALIZED COMPANY EXPERIENCE.docx DOCX document
EXHIBIT C LETTER OF COMMITMENT.docx DOCX document
W50S9F-22-R-0001.pdf PDF
ATTACHMENT 08_SAP SINGLE SOURCE DETERMINATION ANDOVER.pdf PDF
EXHIBIT B SUBCONTRACTOR TEAM KEY PERSONNEL INFORMATION AND CONSENT FORM.doc DOC document
EXHIBIT F SUBCONTRACTING PLAN FORMAT.docx DOCX document
EXHIBIT G PROPOSAL PRICE SCHEDULE.docx DOCX document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Medical Readiness Q&A #03

38. Please reference specification section 01 1000 paragraphs 1.06, 1.07, and 1.08. These paragraphs intend to convey work performed by the Government versus the Contractor. Some of the descriptions are vague such as paragraph 1.06.D.1 Installation of furniture and equipment. What is the definition of equipment? Please provide a responsibility matrix for all scopes of work so that the Contractor can determine costs accurately.

A. See drawing A-401 and A-402 for matrix and identification of accessories and equipment. In general any

Government Furnished Government Installed items shown on drawings are noted as “GFGI”.

39. Please reference the Attachment 5 B307 Asbestos Report and Attachment 6 B311 Asbestos Report. These documents do not include drawings of the sample locations. Please provide drawings showing the sample locations.

A. Attached is a drawing and photograph log for Building 311, identifying the locations where samples containing more than >1% asbestos and considered asbestos-containing materials (ACMs) per EPA regulatory requirements. A plan indicating all sample locations is not available. There is no plan for Building 307, as there were no ACM identified in the sampling that was performed.

40. The RFP documents do not include as-built drawings for Buildings B307 or B311. Please provide the as-built drawings for each building along with site, civil, and utility drawings so that the Contractor can determine costs and scopes accurately.

A. Given the age/status of these facilities, the Government cannot provide accurate as-builts. Please reference the provided floor plans. Additional site visits may be requested.

41. The Question and Answers 02 was uploaded to SAM on April 7, posting questions from #27 onward. However, the Q&A #01 has not been uploaded to Sam yet. Please post questions 1-26.

A. Thank you for the catch. It is posted.

42. The Pre-proposal conference slides indicate to include the Performance Relevancy Questionnaire Exhibit A in

Volume 2. However, the response to question 30 indicates that Exhibit A is to be submitted with Volume 1 Technical. Please clarify this discrepancy and indicate which Volume the offeror shall place Exhibit A in.

A. Slide 14 shows that Exhibit A is to be in Volume 1, Technical. Slide 16 refers to using Exhibit A IF you are using non-employee or subs as past performance. Slide 18 addresses this.

43. Please reference the Solicitation 1442 Form Section 7 where it prescribes the mandatory performance period of 450 calendar days after receipt of the NTP. Due to current and unknown future economic impacts to costs, material and manpower availability, manufacturer lead times, etc, we request that the Government allow for the performance period to be negotiated. This will allow for the Contractor to provide a best value for the Government. The Contractor would then provide the actual performance period in the bid schedule.

A. The period of performance will not be negotiated.

44. Please confirm that the design documents will be updated based on Contractor questions and Government responses.

A. If questions lead to a change in design documents, they would be updated accordingly.

File details come from the government source that posted it. Updated .