This federal contract opportunity document describes a solicitation for construction services. The 115th Fighter Wing of the Wisconsin Air National Guard is seeking proposals to construct a new 18,650 square foot, two-story Medical Readiness facility at Dane County Regional Airport - Truax Field in Madison, Wisconsin. The facility will include space for Reserve Forces medical training and administration as well as storage for expeditionary medical support equipment. The fixed-price contract awarded will have a period of performance of 450 days from notice to proceed and includes a base requirement for new construction plus nine options related to finishes, mechanical systems, and demolition. Brand name specifications are provided for security, building automation, and fire alarm systems. The pre-proposal conference is scheduled for March 31st and proposals are due by May 5th. Evaluation will consider technical approach, past performance, price, and small business participation. The North American Industry Classification code is 236220 and the project value is between $5-10 million.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Medical Readiness Facility, newest first.
File Type Posted
SECTION 26 0573.19 ARC FLASH HAZARD ANALYSIS.pdf PDF
074213 23 compo wall panel.pdf PDF
Questions and Answers 05 R1.pdf PDF
Questions and Answers 04 R1.pdf PDF
60613250_WIANG_TRUAX-MED-E_v19 - Sheet - E-601 - ELECTRICAL SCHEDULES.pdf PDF
W50S9F-22-R-0001_0004.pdf PDF
Questions and Answers 05.pdf PDF
Questions and Answers 04.pdf PDF
W50S9F-22-R-0001_0003.pdf PDF
Bldg_311 Floor Layout.pdf PDF
Questions and Answers 03.pdf PDF
Photograph Log.docx DOCX document
Bldg_307 Floor Layout.pdf PDF
DEMO PLAN BLDG 311.pdf PDF
Questions and Answers 01.pdf PDF
Questions and Answers 02.pdf PDF
W50S9F-22-R-0001_0002.pdf PDF
Site Visit Sign In Log.pdf PDF
Pre-Proposal Slides - Medical Readiness.pdf PDF
Pre-Proposal Conference Minutes.pdf PDF
W50S9F-22-R-0001_0001.pdf PDF
ATTACHMENT 03_DRAWINGS Project No. XGFG139001 dated 14 MAY 2021.pdf PDF
ATTACHMENT 05_B307 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019.pdf PDF
ATTACHMENT 09_SAP SINGLE SOURCE DETERMINATION MONACO.pdf PDF
ATTACHMENT 10_SAP SINGLE SOURCE DETERMINATION MARSHALL BEST.pdf PDF
ATTACHMENT 12 PRE PROPOSAL SITE VISIT_DROP OFF INSTRUCTIONS.pdf PDF
EXHIBIT D PAST PERFORMANCE REFERENCE QUESTIONNAIRE.docx DOCX document
EXHIBIT E SMALL BUSINESS PARTICIPATION PLAN FORMAT.docx DOCX document
ATTACHMENT 01_PLANS AND SPECIFICATIONS Vol 1 Project No. XGFG139001 dated 08 Jul 2021.pdf PDF
ATTACHMENT 02_PLANS AND SPECIFICATIONS Vol 2 Project No. XGFG139001 dated 08 Jul 2021.pdf PDF
ATTACHMENT 04_GEOTECHNICAL ENGINEERING REPORT Project No. XGFG139001 dated 08 Nov 2019.pdf PDF
ATTACHMENT 06_B311 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019.pdf PDF
ATTACHMENT 07_SAP SINGLE SOURCE DETERMINATION ADVANTOR.pdf PDF
ATTACHMENT 11_SFS FORM 12.xlsx XLSX spreadsheet
EXHIBIT A PERFORMANCE RELEVANCY QUESTIONNAIRE AND SPECIALIZED COMPANY EXPERIENCE.docx DOCX document
EXHIBIT C LETTER OF COMMITMENT.docx DOCX document
ATTACHMENT 08_SAP SINGLE SOURCE DETERMINATION ANDOVER.pdf PDF
EXHIBIT B SUBCONTRACTOR TEAM KEY PERSONNEL INFORMATION AND CONSENT FORM.doc DOC document
EXHIBIT F SUBCONTRACTING PLAN FORMAT.docx DOCX document
EXHIBIT G PROPOSAL PRICE SCHEDULE.docx DOCX document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construct Medical Readiness Facility, Project Number XGFG139001 located at Truax Field Air National Guard Base (ANGB), 3110 Mitchell Street, Madison, WI 53704

This project is being solicited as unrestricted. The North American Industry Classif ication (NAICS) Code is 236220-Commercial and institutional buildings. The size standard is $39.5M average annual revenue for the past three (3) years. Project Magnitude Range is betw een $5M and $10M. Persons intending on offering a proposal should attend the Pre-Proposal Conference/Site Visit on 31 March 2022 at 1000 CST. See Section 00100 for specif ic details. In accordance w ith FAR Clause 52.228-1 Bid Guarantee, a bid bond is required w ith the proposal.

Funds are not presently available for this contract. The Govt anticipates funds w ill become available prior to but no later than midnight 30 Sep 2022. This action has been identif ied on the NGB priority list for aw ard if funds become available and the prices received are w ithin an aw ardable range. Aw ard w ill be made to the offeror w ho represents the best value to the Government as outlined in accordance w ith the criteria set forth w ithin the solicitation.

Solicitation and all information notices, amendments for this solicitation w ill be posted at https://sam.gov/.

KATHERINE I. FOX 608-245-4524

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

21-Mar-2022

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______30 calendar days and complete it w ithin ________450 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________2 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 May 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USPFO WI 115 MISSION SUPPORT CONTRACTING

3110 MITCHELL ST BLDG 500

MADISON WI 53704-2591

W50S9F

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W50S9F22R0001 103

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W50S9F22R0001

Section 00010 - Solicitation Contract Form

TABLE OF CONTENTS

SOLICITATION, OFFER, AND AWARD SF 1442 and SF 1442 BACK

SECTION 00010 – PRICING SCHEDULE, NOTES

SECTION 00100 – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

SECTION 00600 – REPRESENTATIONS & CERTIFICATIONS

SECTION 00700 – CONTRACT CLAUSES

SECTION 00800 – WAGE DETERMINATION

SECTION 01000 – DIVISION 01 GENERAL REQUIREMENTS AND SPECIAL CONTRACT

REQUIREMENTS

ATTACHMENT 01 – PLANS AND SPECIFICATIONS Vol 1 Project No. XGFG139001 dated 08 Jul 2021 ATTACHMENT 02 – PLANS AND SPECIFICATIONS Vol 2 Project No. XGFG139001 dated 08 Jul 2021 ATTACHMENT 03 – DRAWINGS Project No. XGFG139001 dated 14 MAY 2021 ATTACHMENT 04 – GEOTECHNICAL ENGINEERING REPORT Project No. XGFG139001 dated 08 Nov 2019 ATTACHMENT 05 – B307 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019 ATTACHMENT 06 – B311 ASBESTOS REPORT Project No. XGFG139001 dated 25 Nov 2019

ATTACHMENT 07 – SAP SINGLE SOURCE DETERMINATION, ADVANTOR

ATTACHMENT 08 – SAP SINGLE SOURCE DETERMINATION, ANDOVER

ATTACHMENT 09 – SAP SINGLE SOURCE DETERMINATION, MONACO

ATTACHMENT 10 – SAP SINGLE SOURCE DETERMINATION, MARSHALL BEST

ATTACHMENT 11 – SFS FORM 12

ATTACHMENT 12 – PRE-PREPOSAL SITE VISIT/DROP OFF INSTRUCTIONS

EXHIBIT A – Performance Relevancy Questionnaire EXHIBIT B – Subcontractor Information and Consent Form EXHIBIT C – Letter of Commitment of Key Subcontractor and/or Key Personnel Past Performance Reference Questionnaire EXHIBIT D – Past Performance Reference Questionnaire EXHIBIT E – Small Business Participation Plan Format EXHIBIT F – Small Business Subcontracting Plan Format EXHIBIT G – Proposal Price Schedule

SECTION 00010 NOTES

1. Instructions for the preparation of proposals are located in Sections 00100, 00110 and 00120.

2. Offeror’s attention is invited to the insurance requirement contained in this solicitation (FAR Clause 52.228-5 Insurance – Work on a Government Installation). Certification of the required coverage for the prime contractor shall be furnished prior to beginning work on this contract, and the Contracting Officer may request evidence of the required insurance at any time during the life the contract.

3. Reference DFARS Provision 252.236-7008, Contract Prices – Bidding Schedules. The term “Bidding Schedule” shall also be construed to mean “Offer Schedule” or “Schedule”. The terms “bid” and “offer”, and “bidder” and “offeror” shall be construed as having the same meaning in this solicitation and resulting contract.

4. Line items 0002 through 0010 are Option Line Items. See FAR Provision 52.217-5 Evaluation of Options, Section 00100. See FAR Clause 52.217-7 in Section 00700. Option lines items are shown in plans and specifications as Alternate, Alternate Bid Item and Bid Options. The Schedule of Alternates is presented in volume 1 of the specifications (pg 104-106). Each respective specification section references this section if an alternate is probable. Line Item 0002, Option 1 is Alternate 1; Line item 0003, Option 2 is Alternate 2; Line Item

0004 is Alternate 3; Line item 0005, Option 4 is Alternate 4; Line item 0006, Option 5 is Alternate 5; Line item 0007, Option 6 is Alternate 6; Line item 0007, Option 6 is Alternate 6; Line item 0008, Option 7 is Alternate 7;

Line item 0009, Option 8 is Alternate 8; Line item 0010, Option 9 is Alternate 9.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Medical Readiness Facility - Base

FFP

Provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary to construct the Medical Readiness building. This project seeks to construct the two-story 18,650 SF facility that includes 15,250 SF for Reserve Forces Medical Training/Admin and 3,400 SF for Expeditionary Medical Support - Consequence Management (EMEDS-CM) storage. Typical work includes, but is not be limited to: site utilities/grading/landscaping; erecting load-bearing insulated precast concrete panels, new mechanical, electrical, plumbing, and technology systems; and demolition of Buildings 311 and 307. All work will be in accordance with design requirements, specifications, and drawings provided within the master specifications.

FOB: Destination

SIGNAL CODE: A

PSC CD: Y1AZ

NET AMT

0002 1 Job OPTION Option 1: Permeable Concrete Pavers

FFP

FOB: Destination

0003 1 Job OPTION Option 2: Asphalt Bypass Drive

0004 1 Job OPTION Option 3: Glazed Interior Storefront

0005 1 Job OPTION Option 4: Laminated Wall Panels

0006 1 Job OPTION Option 5: Tubular Daylighting System

0007 1 Job OPTION Option 6: Motorized Roller Blinds

0008 1 Job OPTION Option 7: Poured Epoxy Terrazzo Flooring

0009 1 Job OPTION Option 8: Spiral Supply Ducts

0010 1 Job OPTION Option 9: Demolition of Buildings

FFP

Buildings 307 and 311

FOB: Destination

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 450 dys. ANP 1 115 CE - F7P3CE

BASE CIVIL ENGINEER

3110 MITCHELL STREET

BLDG 1200

MADISON WI 53704

608-245-4563

F7P3CE

0002 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0003 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0004 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0005 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0006 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0007 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0008 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0009 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

0010 450 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

Section 00100 - Bidding Schedule/Instructions to Bidders

Section 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. SCOPE

1.1. You are invited to submit a proposal in response to our Request for Proposal W50S9F-22-R-0001 for Project No. XGFG139001at 115 FW, Truax Field, Madison, WI 53704. As a result of this solicitation, the Government intends to award a single Firm Fixed Price (FFP) contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

1.2. This solicitation is Unrestricted.

2. NOTICE OF PRE-PROPOSAL CONFERENCE

2.1. A pre-proposal conference will be conducted on 31 March 2022 at 1000 CST for the purposes of briefing on the proposal requirements and answering questions regarding this solicitation. This conference will be held at 115 FW, Truax Field, Madison, WI 53704. Interested Contractors are highly encouraged to attend the pre-proposal conference. The site visit will be held following the conference.

2.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email attachment 11, SFS Form 12, for all attendees to katherine.fox@us.af.mil.

2.3. This information must be provided in advance, not later than 5 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.

2.4. Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival. You will be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Driver’s License, (3) Proof of Insurance for Vehicle, and/or (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

2.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

2.6. A record of the conference shall be made and furnished to all prospective offerors via posting to SAM.gov.

The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS

3.1. Submit all questions via email to the contracting office at the address shown below. Do NOT contact the A-E or Engineering personnel directly. Doing so will only delay the response to your question.

Subject Line: Reference No. W50S9F-22-R-0001 Email: katherine.fox@us.af.mil

INQUIRIES SHALL BE SUBMITTED VIA EMAIL AND INCLUDE THE FOLLOWING INFORMATION:

Date of Proposal Inquiry:

From: ______________________________

Company Name: ___________________________

Phone Number: ____________________________

Email address: _____________________________

Proposal Inquiry: Be specific as to part of solicitation you are questioning.

3.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their offer.

3.3. The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing. OFFERORS ARE STRONGLY ENCOURAGED

TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.

3.4. Any interpretations made will be in the form of an amendment of the solicitation, drawings, specifications, etc., and will be furnished to all prospective offerors via posting to https://www.sam.gov.

3.4.1. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective offerors via the web site.

3.4.2. For security reasons, all technical and engineering data related to this solicitation will be distributed using the https://www.sam.gov. Sam.gov is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Plans and specifications are uploaded and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA.

3.4.2.2. Interested offerors must be registered in the System for Award Management (SAM). To register go to:

www.sam.gov. You will need your Unique Entity Identifier (UEI). Instructions for registering are on the web page.

(Please note the registration for access to the secure site takes approximately 15 business days, so plan accordingly.)

4. AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS

4.1. The right is reserved, as the interest of the Government may require, to revise or amend, the specifications or drawings or both prior to and/or after the date set for receipt of proposals as necessary. Such amendments, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and information prior to the date set for receipt of proposals will be posted at https://www.sam.gov.

4.2. Offerors are strongly cautioned to check this site frequently and to “refresh” their web page to ensure they have the lasted information.

5. HAND CARRIED PROPOSALS/INVITATIONS

5.1. Hand carried proposals can be hand carried to the small parking lot outside of base on the proposal due date. See attachment 12 - Pre-Proposal Site Visit Instructions/Drop-off Instructions.

5.2. Hand carried proposals must be received prior to the time established for receipt of proposals.

5.3. Offerors are cautioned that approval to enter the base must be obtained prior to the closing date for receipt of proposals. Follow the procedures outlined above in paragraph 2.1.2. for entry. Delays are probable at the entry point and should be accounted for. Late receipt of proposals due to base entry delays may not be deemed excusable and the Contracting Officer may declare the proposal late and remove it from consideration.

6. WAGE DETERMINATION

6.1. The Construction Wage Rate Requirements formerly known as Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are WI20220005 03/18/2022, Mod 5 for Dane County, Wisconsin.

In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of the solicitation, the most current wage determination is in effect. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors that have not been eliminated from the competition. If applicable, these offerors/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes.

If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404- 5(c)(4) will apply.

6.2. Applicable wage rates can be found at SAM.gov.

7. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.

8. REMOVAL OF SECTIONS AT TIME OF AWARD

Sections 00100, 00110, 00120, 00600 and all exhibits will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.

9. DISPOSITION OF UNSUCCESSFUL PROPOSALS

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.

10. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all reasonable amounts of electrical and water, where/if physically available, used in connection with this project will be furnished to contractor without cost. The offerors will take this into consideration when computing its offer. (FAR Clause 52.236-14, Availability and Use of Utility Services)

11. BID BONDS

A copy of Bid Bonds and Power of Attorney can be submitted electronically with the proposal if proposal is being submitted via Solicitation Portal on Procurement Integrated Enterprise Environment (PIEE), with the original signed copy with Seal to be submitted no later than 5 days after proposal close date. Bid bond must be on the most current

SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4, Noncompliance with bid guarantee requirements.

12. EXCEPTIONS

If the offeror takes exception to any of the requirements specified in this solicitation, the offeror shall clearly identify each such exception and include a complete explanation of why the exception was taken and what benefit accrues to the Government. All exceptions to the solicitation requirements (Sections 00010 through 00800) and supporting rationale shall be included in an addendum to the proposal and clearly labeled "Exceptions". An addendum is only required if the offeror takes exception to any requirement in the solicitation. (The Addendum does not have a page limitation, but shall only include information relevant to exceptions taken to the solicitation requirements.) The Government will assume an offeror takes no exceptions to any solicitation requirement if the offeror does not submit an Addendum identifying exceptions. Offerors are advised that solicitation requirements are not necessarily negotiable and such exceptions may render an offeror's proposal unacceptable and ineligible for award.

13. CLAUSES

12.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

12.2. Clauses and provisions in this document may not appear in consecutive order.

14. BRAND NAME REQUIREMENTS

Advantor Security System, Andover DDC Software, Marshall Best Security Corp. premium YB series keys and cores and Monaco fire system.

End of Section 00100

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.236-28 Preparation of Proposals--Construction OCT 1997 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.215-7008 Only One Offer JUL 2019

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of provision)

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

2.2% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is State of Wisconsin, Dane County, City of Madison.

52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (MAY 2014) ALTERNATE II (JUN 2009)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act-- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3M, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

National Guard Bureau Office of the Director of Acquisitions

ATTN: NGB-AQ-O

111 S. George Mason Dr.

Arlington, VA 22204 Email: ng.ncr.ngb-arng.mbx.ngb-task-order-ombudsman@mail.mil

Protest to the Contracting Officer Shall be filed at:

Katherine I. Fox Contracting Officer

WI ANG

3110 Mitchell Street Madison, WI 53704 Katherine.fox@us.af.mil

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least fifteen (15) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of clause)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for Thursday, March 31, 2022 at 10:00AM Central Standard Time.

Individuals interested in attending the site visit must email the SFS Form 12, soliciation attachment 11, to MSgt Katherine Fox, katherine.fox@us.af.mil, no later than not later than 5 business days prior to the meeting. See soliciation section 00100 and soliciation attachment 12 for more information.

(c) Participants will meet at—

115th Fighter Wing Building 500, Dining Facility 3110 Mitchell Street

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows: NONE

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (DFARS) (48 CFR Chapter 2)provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

252.204-7019 NOTICE OF NIST SP 800-171 DOD ASSESSMENT REQUIREMENTS (NOV 2020)

(a) Definitions.

Basic Assessment, Medium Assessment, and High Assessment have the meaning given in the clause 252.204-7020, NIST SP 800-171 DoD Assessments.

Covered contractor information system has the meaning given in the clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, of this solicitation.

(b) Requirement. In order to be considered for award, if the Offeror is required to implement NIST SP 800-171, the Offeror shall have a current assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) (see 252.204-7020) for each covered contractor information system that is relevant to the offer, contract, task order, or delivery order. The Basic, Medium, and High NIST SP 800-171 DoD Assessments are described in the NIST SP 800-171 DoD Assessment Methodology located at https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800- 171.html.

(c) Procedures.

(1) The Offeror shall verify that summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) are posted in the Supplier Performance Risk System (SPRS) (https://www.sprs.csd.disa.mil/) for all covered contractor information systems relevant to the offer.

(2) If the Offeror does not have summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) posted in SPRS, the Offeror may conduct and submit a Basic Assessment to webptsmh@navy.mil for posting to SPRS in the format identified in paragraph (d) of this provision.

(d) Summary level scores. Summary level scores for all assessments will be posted 30 days post-assessment in SPRS to provide DoD Components visibility into the summary level scores of strategic assessments.

(1) Basic Assessments. An Offeror may follow the procedures in paragraph (c)(2) of this provision for posting Basic Assessments to SPRS.

(i) The email shall include the following information:

(A) Cybersecurity standard assessed (e.g., NIST SP 800-171 Rev 1).

(B) Organization conducting the assessment (e.g., Contractor self-assessment).

(C) For each system security plan (security requirement 3.12.4) supporting the performance of a DoD contract--

(1) All industry Commercial and Government Entity (CAGE) code(s) associated with the information system(s) addressed by the system security plan; and

(2) A brief description of the system security plan architecture, if more than one plan exists.

(D) Date the assessment was completed.

(E) Summary level score (e.g., 95 out of 110, NOT the individual value for each requirement).

(F) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(ii) If multiple system security plans are addressed in the email described at paragraph (d)(1)(i) of this section, the Offeror shall use the following format for the report:

Brief CAGE codes description of Date of Total Date score of System security plan supported by this the plan assessment score 110 will plan architecture achieved

(2) Medium and High Assessments. DoD will post the following Medium and/or High Assessment summary level scores to SPRS for each system assessed:

(i) The standard assessed (e.g., NIST SP 800-171 Rev 1).

(ii) Organization conducting the assessment, e.g., DCMA, or a specific organization (identified by Department of Defense Activity Address Code (DoDAAC)).

(iii) All industry CAGE code(s) associated with the information system(s) addressed by the system security plan.

(iv) A brief description of the system security plan architecture, if more than one system security plan exists.

(v) Date and level of the assessment, i.e., medium or high.

(vi) Summary level score (e.g., 105 out of 110, not the individual value assigned for each requirement).

(vii) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(3) Accessibility.

(i) Assessment summary level scores posted in SPRS are available to DoD personnel, and are protected, in accordance with the standards set forth in DoD Instruction 5000.79, Defense-wide Sharing and Use of Supplier and Product Performance Information (PI).

(ii) Authorized representatives of the Offeror for which the assessment was conducted may access SPRS to view their own summary level scores, in accordance with the SPRS Software User's Guide for Awardees/Contractors available at https://www.sprs.csd.disa.mil/pdf/SPRS_Awardee.pdf.

(iii) A High NIST SP 800-171 DoD Assessment may result in documentation in addition to that listed in this section.

DoD will retain and protect any such documentation as "Controlled Unclassified Information (CUI)" and intended for internal DoD use only. The information will be protected against unauthorized use and release, including through the exercise of applicable exemptions under the Freedom of Information Act (e.g., Exemption 4 covers trade secrets and commercial or financial information obtained from a contractor that is privileged or confidential).

SECTION 00110 SUBMISSION REQUIREMENTS AND INSTRUCTIONS

1. PROPOSAL SUBMISSION REQUIREMENTS (Section 00110)

1.1. The instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposal data. They are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals. Carefully review this section prior to commencing proposal preparation. All solicitation amendments must be acknowledged in accordance with Section 00100, FAR Provision 52.215-1, and Instructions to Offerors- Competitive Acquisition.

1.1.1. Offerors are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete proposal. Failure to furnish a complete proposal, at the time of proposal submission, may result in the proposal being unacceptable to the Government and eliminated from consideration for award.

1.1.2. Each volume shall be submitted electronically on CD/DVD saved in Microsoft Word format or Adobe

Acrobat or submitted through the Solicitation Portal on Procurement Integrated Enterprise Environment (PIEE).

Any portion of the proposal that is changed (as a result of negotiations or proposal revisions) should be annotated and dated. Each volume shall be clearly labeled with its Title and a copy number (e.g., copy 1 of 5).

1.1.3. Each paragraph should be single spaced, and shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Tables and illustrations may use a reduced font size no less than 8-point and may be produced in landscape mode.

1.1.4. The following volumes of material shall be submitted:

Volume Title Digital Copies Maximum Pages

I Technical 2 50

II Past Performance 2 25 Plus 5 for Each

Major Subcontractor

III Small Business Participation 2 25

IV Cost/Price 2 No Page Limit

V Solicitation, Offer and Award Documents, and Certifications / Representations

2 No Page Limit

NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages over the maximum allowed will be removed or not read and will not be evaluated by the Government.

1.2. After compiling all required information, submit original and specified number of copies to the following office:

ATTN: MSgt Katherine Fox 115th Fighter Wing Contracting Office 3110 Mitchell Street

Or submit through the Solicitation Portal on Procurement Integrated Enterprise Environment (PIEE) (https://piee.eb.mil/)

Mark the front of the envelope/box with the following: “PROPOSAL NO. W50S9F-22-R-0001, DO NOT OPEN—Competitive Acquisition.”

2. PROPOSAL FILES

2.1. Purpose: These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposed data. The proposal shall include all of the information requested in the specific instructions. Failure to include all information requested may adversely affect the evaluation.

2.1.1. A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

2.1.2. Offerors are cautioned to submit enough information to enable the evaluation committee to fully ascertain each offeror’s capability to perform all of the requirements contemplated by this solicitation. All commitments made in the proposal may become a part of the resultant contract. The data submitted with each proposal should be complete and concise, but not overly elaborate. Excessive reliance on promotional brochures is discouraged.

2.1.3. Written proposals shall be prepared on standard 8.5 x 11 inch paper (charts may be landscaped but must be on 8.5 x 11 inch paper) and shall be in a legible font size (10 min.). All pages of each proposal shall be appropriately numbered, and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required. Type size for graphics, charts, diagrams and tables shall be of an appropriate font and size for the application, and must be clearly readable without magnification assistance to the normal eye. Text lines shall be no less than single-space. Unless otherwise stated, tabs, indexes and dividers do not count in the page count.

2.1.4. Indexing: Each volume will contain a “Table of Contents”. The “Table of Contents” will identify major areas, paragraphs and subparagraphs by number and title, as well as by page number and volume locations. Tab indexing will be used to identify sections as appropriate.

2.1.5. Electronic Copy: Provide one (1) electronic copy of all volumes. Electronic copies shall be submitted on

CD/DVD or through the Solicitation Portal on Procurement Integrated Enterprise Environment (PIEE), saved in Microsoft Word format or Adobe Acrobat. (“Read Only” files are acceptable).

2.1.6. The offeror shall be held responsible for the validity of all information supplied in his/her proposal, including that provided by potential subcontractors. Should subsequent investigation disclose that the facts and conditions were not as stated, the proposal may be rejected.

3. PROPOSAL VOLUME CONTENTS

3.1. The offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each file of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion. The Summary Section shall contain a brief abstract of the file. Proprietary information shall be clearly marked. The following shall be included in the Narrative discussion:

3.1.1. VOLUME I, OFFEROR TECHNICAL CAPABILITY PROPOSAL

3.1.1.1. Volume 1 is comprised of four subfactors. Subfactor 1 Experience and Capability; Subfactor 2

Construction Schedule; Subfactor 3 Commissioning Approach and Subfactor 4 Quality Control.

3.1.1.2. Government acknowledges that the technical proposal will involve discussion of some of the same projects/contracts discussed in the Past Performance volume. While Past Performance examines how an offeror performed in the past, so as to determine the probability of success on future projects, this subfactor examines the offeror’s experience with complex multidiscipline project management and execution and how the offeror demonstrates an understanding of the contract’s requirements taking this experience into consideration.

Government intends to use Performance Relevance Questionnaire & Company Specialized Experience Part 1 (Exhibit A) information in the evaluation of experience for Subfactor 1. A reiteration of the information provided in Exhibit A is neither required nor desired. Offeror should reference this information by providing a short summation of their relevant experience to meet the submission requirements of this subfactor.

3.1.1.3. Sub-Factor 1: Experience & Capability. The Experience and Capability Proposal is limited to 10 single pages and resumes to 2 pages each, exclusive of table of contents, tabs, and dividers. Pages in excess of the limit will not be evaluated.

3.1.1.3.1. Demonstrate offerors technical experience and capability to perform a project of this magnitude and complexity. Discuss and provide experience of key construction personnel including, but not limited to, Project Manager, Site Superintendent(s), Quality Control Manager (on site) and Safety Manager. Refer to Section 01000, Part 36, for the minimum qualification requirements for key personnel. Discuss any previous projects that are similar to this project in terms of scope, size and complexity. Specifically discuss experience with DoD Government contracting, erecting precast insulated concrete panel structures, and medical facilities. If no experience, state and indicate in detail how you plan to overcome this lack of experience for both personnel and project. The onus is solely on the offeror to indicate in detail how the offeror plans to overcome this lack of experience. (Resumes or experience cut sheets are limited to 2 pages each and are not part of the page count.) In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” is also required or the information will not be considered. Exhibit C, Consent form or Letter of Intent, is required for the Subcontractor to be considered.

3.1.1.4. Sub-Factor 2: Construction Schedule is obtained for the purposes of evaluating an offerors understanding of the requirements of the schedule.