This document is a Questions and Answers (Q&A) file containing Requests for Information (RFIs) and Government responses for solicitation W50S8R-26-R-A005, as of June 9, 2026.

RFI 01 addresses four clarifications regarding solicitation requirements. First, the Government confirmed the solicitation is UNRESTRICTED, with "Small Business" references removed from the documentation. Second, the Government clarified that only Large Businesses are required to submit Subcontracting Plans; Small Businesses need only submit a statement confirming their understanding of subcontracting limitations as referenced in FAR 52.219-14. Third, regarding Exhibit A packages (3-5 documents), the Government confirmed that a single set serves both Technical Subfactor 1 evaluation and Past Performance evaluation purposes. Offerors should include Exhibit A's in Volume 2, Part 2 per section 2.3.3.1, and reference the relevant project information in a short summation within Volume 2, Part 1 to avoid duplicating paperwork. Fourth, the Government resolved a discrepancy between Section 00 21 16 (which specified 3-5 projects) and Exhibit A (which initially limited submissions to 3 projects) by revising Exhibit A to allow up to five (5) projects, establishing a consistent allowable range of 3-5 projects across all documentation.

View the file

Other files

File Type Posted
W50S8R26RA005 0005_B403 CYBER Repair (conformed version).pdf PDF
W50S8R26RA005 0005_B403 CYBER Repair.pdf PDF
RFI and Response Document (as of 07 July)_final.pdf PDF
W50S8R26RA005 0004_B403 CYBER Repair (conformed version).pdf PDF
RFI 04_question 6. attach._Geotech Report.pdf PDF
W50S8R26RA005 0004_B403 CYBER Repair.pdf PDF
RFI and Response Document (as of 03 July).pdf PDF
RFI 03_question 7. response attach. 01.pdf PDF
RFI 03_question 7. response attach. 02.pdf PDF
RFI and Response Document (as of 02 July).pdf PDF
RFI 02_question 8. response attachment.pdf PDF
W50S8R26RA005 0003_B403 CYBER Repair (conformed version).pdf PDF
W50S8R26RA005 0003_B403 CYBER Repair.pdf PDF
W50S8R26RA005 0002_B403 CYBER Repair.pdf PDF
EXHIBIT A rev01.pdf PDF
Pre-Proposal sign-in sheet.pdf PDF
Pre-Proposal Conference-slides.pptx PPTX presentation
W50S8R26RA005 0002_B403 CYBER Repair (conformed version).pdf PDF
Pre-Proposal Conference minutes_B403 CYBER.pdf PDF
ATTACHMENT 06_B403 Cyber_Drawings (Full size)_B3.pdf PDF
ATTACHMENT 05_B403 Cyber_Drawings (Half size)_B3.pdf PDF
ATTACHMENT 03_B403 Cyber_Specifications (Div 09-25)_B3.pdf PDF
ATTACHMENT 01_B403 Cyber_Narrative_B3.pdf PDF
W50S8R26RA005 0001_B403 CYBER Repair (conformed version).pdf PDF
ATTACHMENT 02_B403 Cyber_Specifications (Div 01-08)_B3.pdf PDF
ATTACHMENT 04_B403 Cyber_Specificatioins (Div 26-33)_B3.pdf PDF
ATTACHMENT 07_B403 Cyber_Interior Design Specs and Drawings_B3.pdf PDF
ATTACHMENT 06_B403 Cyber_Drawings (Full size)_B3.pdf PDF
W50S8R26RA005 0001_B403 CYBER Repair.pdf PDF
ATTACHMENT 08_IDS Justification and Approval.pdf PDF
ATTACHMENT 05_B403 Cyber_Drawings (Half size)_B3.pdf PDF
EXHIBIT A.docx DOCX document
EXHIBIT B.docx DOCX document
EXHIBIT D_Letter of Commitment.docx DOCX document
EXHIBIT C_Reference Questionnaire Package.docx DOCX document
W50S8R26RA005_B403 CYBER Repair.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Requests for Information (RFI’s) and Responses – Solicitation #: W50S8R-26-R-A005

(as of 09 Jun 26)

RFI 01

1. The SF 1442 cover page and Section 00 21 00 state the solicitation is UNRESTRICTED. However, Section 00 22 16, Paragraph 1.1 states: 'The Government intends to award a single contract to a qualified Small Business Offeror...'

Is this solicitation Unrestricted or is it restricted to Small Business concerns?

RESPONSE: Solicitation is UNRESTRICTED… “Small Business” has been removed from this text.

2. Section 00 21 16, Para. 2.3.2.3 opens with 'Offeror shall submit a subcontracting plan...' without initially distinguishing business size. The parenthetical '(for Large businesses only)' is added only in Section 00 22 16 headers. Further, Section 00 21 16 Para. 2.3.2.3 also states 'If you fail to provide a subcontracting plan your proposal will be found unacceptable' without a clear small business carve-out in that same paragraph—the small business alternative is in a starred note below.

Please confirm: (1) Large businesses MUST submit a Subcontracting Plan or face elimination; (2) Small businesses are NOT required to submit a Subcontracting Plan;

and (3) the starred statement on company letterhead at Para. 2.3.2.3 is the ONLY required substitute for small businesses.

RESPONSE: Only Large Businesses are required to submit Subcontracting Plans as part of their proposal. The FAR is clear on this requirement, and that is does not apply to Small businesses. Putting the “for Large Businesses only” in the text was for reminder purposes only. Small businesses only need to submit the statement as referenced in the solicitation, as it relates to FAR 52.219-14 and their confirmation of understanding the requirements related to subcontracting limitations for Small businesses.

3. Para. 2.3.2.1.1 states: 'The Government intends to use Exhibit A Part 1 information in the evaluation of experience for Subfactor 1..' Para. 2.3.3.4 separately instructs offerors to 'Prepare not more than 3-5 of these documents' as part of Past Performance. It is unclear whether one set of 3-5 Exhibit A packages serves BOTH Technical (Subfactor 1) and Past Performance purposes, or whether separate Exhibit A packages must be prepared for each.

Please confirm: (1) Is a single set of Exhibit A packages (3-5) used for both Subfactor 1 Technical evaluation and Past/Present Performance evaluation? (2) Or must the offeror submit separate Exhibit A packages—one set for Technical and a separate set for Past Performance? (3) If a single set, should they be included in Volume 2, Part 2 only, with a cross-reference in Volume 2, Part 1?

RESPONSE: As stated 2.3.3.1., contractor shall provide Exhibit A’s as part of that volume and part requirement. 2.3.2.1.1. is simply stating that those Exhibit A’s submitted in that part of proposal (2.3.3.1.), will also be utilized in evaluating Subfactor 1; therefore, submitting the same information in detail for Subfactor 1 is not necessary (simply duplicating paperwork). In further reading the 3rd paragraph of section 2.3.2.1.1., it states the Offeror should simply reference the information (i.e.

project, contract, etc.) in a short summation (document) of their relevant experience and capabilities in meeting Subfactor 1. (instead of submitting the entire exhibits in both Part 1 and Part 2).

4. Section 00 21 16, 2.2.3 provides for 3-5 projects. Exhibit A says to submit no more than 3.

Please confirm the minimum and total allowable projects to be submitted.

RESPONSE: “three (3)” has been changed to “five (5)” in Exhibit A. Revised document is attached.

(End of RFI’s and Responses)