TGI_38K6151101A01_c0v0.pdf

PDF 1 MB Posted

Attached to
USS RAFAEL PERALTA (DDG-115) FY26 SIA BUNDLE #1
Solicitation number
N6264926RA036
Issued by

About this file

This is a Task Group Instruction (TGI) - a naval work authorization document issued by the U.S. Navy for maintenance work on the USS RAFAEL PERALTA (DDG-115). The document, dated January 21, 2026, authorizes the installation and removal of scaffolding in compartment 01-205-0-Q (Pallet Trunk Stowage/Battery Charging Room) to support Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) work involving replacement of a vent duct and heater. The work is scheduled to commence on July 22, 2026, and be completed by September 11, 2026, with responsibility assigned to Planner Code 231B S. Yamaoka and Work Integration Manager Code 333 T. Yaginuma.

The scope requires erection and hanging of scaffolding in accordance with 29 CFR Part 1915.71 (federal scaffolding standards), with removal to occur upon completion as directed by SRF-JRMC. The SRF-JRMC will provide supporting services including crane and crane rigging ([C740]), safety inspection for employees ([C106.1]), and QA inspection for quality-marked items ([C133]). No government-furnished material is specified, and there are no material lists or required procurement items documented in this instruction. The work references NAVSEA Standard Items and Local Standard Items, with a detailed sketch (Enclosure-01) identifying the specific location where the vent duct and heater replacement will occur.

View the file

Other files

File Type Posted
TGI_38K6186301A01_c0v0_rev2.pdf PDF
TGI_38K6113801A01_c1v0_REV2.pdf PDF
TGI_38K6112306A01_c0v1_REV2.pdf PDF
TGI_38K6169901A01_c0v0_REV2.pdf PDF
TGI_38K6152101A02_c0v0_REV2.pdf PDF
TGI_38K6164401A01_c1v2_REV2.pdf PDF
TGI_38K6154103A02_c0v0_REV2.pdf PDF
TGI_38K6145601A01_c0v0_REV2.pdf PDF
TGI_38K6113602A01_c0v0_REV2.pdf PDF
Attachment I Bundle_1_POP_LIST.xlsx XLSX spreadsheet
TGI_38K6113702A01_c0v0_REV1.pdf PDF
TGI_38K6112303A01_c0v0_REV1.pdf PDF
TGI_38K6113601A01_c0v0_REV1.pdf PDF
TGI_38K6113602A01_c0v0_REV1.pdf PDF
TGI_38K6112325A01_c0v0_REV1.pdf PDF
TGI_38K6154103A02_c0v0_REV1.pdf PDF
TGI_38K6144104A01_c0v0_REV1.pdf PDF
TGI_38K6151101A01_c0v0_REV1.pdf PDF
material info.pdf PDF
6220213_53711_-_0001_ R_-_0001.pdf PDF
38K6112318A01-Engrg Inst.pdf PDF
TGI 38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV1.pdf PDF
TGI_38K6113801A01_c1v0_REV1.pdf PDF
TGI_38K6152101A02_c0v0_REV1.pdf PDF
TGI_38K6145601A01_c0v0_REV1.pdf PDF
TGI_38K6164401A01_c1v2_REV1.pdf PDF
Attachment IV Request for Information Form.docx DOCX document
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
TGI_38K6154103A02_c0v0.pdf PDF
TGI_38K6112301A01_c0v0.pdf PDF
TGI 38K6158301A01_c0v0.pdf PDF
TGI_38K6112317A01_c0v0.pdf PDF
TGI_38K6112304A01_c0v0.pdf PDF
TGI 38K6152101A02_c0v0.pdf PDF
TGI 38K6154101A01_c1v1.pdf PDF
TGI 38K6165401A01_c0v0.pdf PDF
TGI 38K6164401A01_c1v2.pdf PDF
TGI 38K6154101T02_c0v0.pdf PDF
Attachment IV DDG-115_BUNDLE1_GFP_List.xlsx XLSX spreadsheet
Attachment VIII Contract data.pdf PDF
Solicitation - N6264926RA036.pdf PDF
TGI_38K6113801A01_c1v0.pdf PDF
TGI_38K6145601A01_c0v0.pdf PDF
TGI_38K6112318A01_c0v0.pdf PDF
TGI 38K6186301A01_c0v0.pdf PDF
TGI_38K6112320A01_c1v1.pdf PDF
TGI_38K6112305A01_c1v0.pdf PDF
TGI 38K6144104A01_c0v0.pdf PDF
Attachment III Request for Information Sheet (Fillable).pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

21-JAN-2026 1609

20.15.6.0.9333 (July 2025) ICN: 38K6151101 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM 01-205-0-Q FOR SRF-JRMC WORK

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

EE021817

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

YAMAOKA, SHINJI 231B 3152439882 19-NOV-2025

APPROVED BY: CODE: PHONE: DATE:

TAKEISHI, TAKAYUKI 231B 3152436704 19-NOV-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EE02-1817

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

SAITO, KAZUNOBU VARIOUS U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

511A1101

1. SCOPE/PURPOSE:

1.1 Title: Scaffolding for Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) Work; install and remove

1.2 Location of Work:

1.2.1 Pallet Trunk Stowage/Battery Charging Room (01-205-0-Q)

1.3 Identification:

1.3.1 Quantity (One Lot), Scaffolding Assembly for Removal and Installation of Vent Duct

Location: 1.2.1 Remarks: See Sketch Enclosure-01 for Location where Vent Duct and Heater will be replaced.

1.4 Security Classification: None.

TGI Short Form

21-JAN-2026 1609

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6151101 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM 01-205-0-Q FOR SRF-JRMC WORK

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. PROCEDURE:

2.1 Erect/hang scaffolding listed in 1.3.1 in accordance with Ref. No. 3.

2.2 Remove scaffolding listed in 1.3.1 upon completion of the work in accordance with Ref. Ref. No. 3 when requested by SRF- JRMC via Code 333.

2.3 Notes:

2.3.1 Planner: Code 231B S. Yamaoka, 243-9882

2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560

2.3.3 JCN EE02-1817 is related to this TGI.

2.4 Government Furnished Material (GFM): None.

2.5 SRF-JRMC will provide the following service work: (TGI No. 38K6151101S02)

2.5.1 [C740] Crane and crane rigging service.

2.5.2 [C106.1] Safety inspection for SRF-JRMC employees.

2.5.3 [C133] QA Inspection for (G) symbol(s).

Kouichi.Yoshida.ja Typewritten Text 7/22/2026

Kouichi.Yoshida.ja Typewritten Text 9/11/2026

21-JAN-2026 1609

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6151101 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SY TST A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86511

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM 01-205-0-Q FOR SRF-JRMC WORK

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 TM 29 CFR PART

1915.71 Scaffolding or Staging - N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38K6151101A01-Sketch.pdf 19-NOV-2025 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K6151101 KEY OP: A01

Sheet 1 of 1

SKETCH

ENCLOSURE-0138K6151101A01

LEG

EN

D

PLAN

1-A -Vend duct and heater w ill be replaced by

SR

F-JR

M

C