This is a WebAIM Short Form Task Group Instruction (TGI) for shipboard maintenance work on the USS Rafael Peralta (DDG-115). The document outlines requirements for the installation and removal of scaffolding supporting assessment work on the AS-3851/SPY-1D Antenna Array system.
The work involves erecting and hanging four lots of scaffolding assemblies in four separate locations on the vessel: between 02 and 04 Level Weather at frames 125-142 on both port and starboard sides, and between 03 and 05 Level Weather at frames 158-174 on both port and starboard sides. The contractor work is scheduled to commence on July 22, 2026, and be completed by September 11, 2026. Scaffolding installation must comply with Title 29 CFR Part 1915.71 (Scaffolding or Staging standards) and MP PM 240-0049 SURF (AEGIS Radar SPY Antenna Array Scaffolding specifications). The Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) will provide supporting services including crane and crane rigger service, safety inspection for employees, and QA inspection for applicable symbols. The work authorization references JCN CF01-ZA64, with the planner designated as Code 231B N. Kurokawa and the Work Integration Manager as Code 333 T. Yaginuma. No government-furnished materials are identified for this task, and there is no security classification requirement.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
21-JAN-2026 1609
20.15.6.0.9333 (July 2025) ICN: 38K6145601 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPY ANT STAGING AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM AS-3851/SPY-1D ANT ARRAY
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
CF01ZA64
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
KUROKAWA, NAOKI 231B 3152430108 30-SEP-2025
APPROVED BY: CODE: PHONE: DATE:
TAKEISHI, TAKAYUKI 231B 3152436704 30-SEP-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
CF01-ZA64
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
SAITO, KAZUNOBU
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
456A0101
1. SCOPE/PURPOSE:
1.1 Title: Scaffolding for Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC) Work; install and remove
1.2 Location of Work:
1.2.1 Between 02 Level and 04 Level Weather, Frames between 125 and 142, Port
1.2.2 Between 02 Level and 04 Level Weather, Frames between 125 and 142, Starboard (Stbd)
1.2.3 Between 03 Level and 05 Level Weather, Frames between 158 and 174, Port
1.2.4 Between 03 Level and 05 Level Weather, Frames between 158 and 174, Stbd
1.3 Identification:
1.3.1 Quantity (4 Lot), Scaffolding Assembly
TGI Short Form
21-JAN-2026 1609
20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6145601 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPY ANT STAGING AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM AS-3851/SPY-1D ANT ARRAY
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
Location: 1.2.1 through 1.2.4 Remarks: Assessment work of AS-3851/SPY-1D Antenna Array will be accomplished by SRF-JRMC.
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor Work start date:
1.7 Contractor Work completion date:
2. PROCEDURE:
2.1 Erect/hang scaffolding listed in 1.3.1 in accordance with Ref. No. 3 and Ref. No. 4.
2.2 Remove scaffolding listed in 1.3.1 upon completion of the work in accordance with Ref. No. 3 and Ref. No. 4 when requested by SRF-JRMC via Code 333.
2.3 Notes:
2.3.1 Planner: Code 231B N. Kurokawa, 243-0108
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
2.3.3 JCN CF01-ZA64 is related to this TGI.
2.4 Government Furnished Material (GFM): None.
2.5 SRF-JRMC will provide the following service work: (TGI No. 38K6145601S02)
2.5.1 [C740] Crane and crane rigger service.
2.5.2 [C106.1] Safety inspection for SRF-JRMC employees.
2.5.3 [C133] QA inspection for (G) symbol(s).
Kouichi.Yoshida.ja Typewritten Text 7/22/2026
Kouichi.Yoshida.ja Typewritten Text 9/11/2026
21-JAN-2026 1609
20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6145601 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPY ANT STAGING AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-115 USS RAFAEL PERALTA K61
CU PHASE TITLE: *F/O - INSTL & RMV SCAFFOLDING TO/FROM AS-3851/SPY-1D ANT ARRAY
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
3 TM 29 CFR PART
1915.71 Scaffolding or Staging - N
4 MP PM 240-0049,
SURF
AEGIS RADAR SPY ANTENNA
ARRAY SCAFFOLDING
A Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/