TGI_38K6112303A01_c0v0.pdf

PDF 2 MB Posted

Attached to
USS RAFAEL PERALTA (DDG-115) FY26 SIA BUNDLE #1
Solicitation number
N6264926RA036
Issued by

About this file

This is a WebAIM Short Form Task Group Instruction (TGI) for maintenance and repair work on the USS RAFAEL PERALTA (DDG-115), a naval destroyer. The document, dated 21-JAN-2026, provides detailed instructions for repair of an incompleted weld on a bimetallic transition joint for an engine removal rail located in compartment 02-174-1-Q (Intake Engine Room No. One, Starboard).

The work scope requires accomplishing weld repair of the existing bimetallic transition joint in accordance with referenced drawing DWG 234-6218562 and maintenance procedure MP LM19-K6112303-ES01NA54. The repair must comply with gas turbine maintenance procedures and specific welding requirements outlined in sections 009-012 and 009-032 of referenced standards. The work is located at frames 184-185 on the starboard side and includes associated areas in the Intake Trunk (A) Engine Room and Engine Room No. One. The contractor work period is scheduled from 7/27/2026 through 9/4/2026. Supporting services to be provided by SRF-JRMC include crane and rigging services, electrical and utility support (low pressure air, water, and steam), safety and gas-free inspections for employees, and Quality Assurance inspections for welding symbols. The document references CCIMS report No. CCIMS-G1N6-DDG115-049-24 as the trigger for this repair work. Key contacts include Planner Code 231B T. Ashina and Work Integration Manager Code 333 T. Yaginuma. No government-furnished materials are required, and the security classification is None.

View the file

Other files

File Type Posted
TGI_38K6113702A01_c0v0_REV2.pdf PDF
TGI_38K6144104A01_c0v0_REV2.pdf PDF
TGI_38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6171101A01_c0v0_REV2.pdf PDF
TGI_38K6113601A01_c0v0_REV2.pdf PDF
TGI_38K6112321A01_c0v0_REV2.pdf PDF
Solicitation Amendment N6264926RA0360005 SF 30.pdf PDF
TGI_38K6186301A01_c0v0_rev2.pdf PDF
TGI_38K6113801A01_c1v0_REV2.pdf PDF
TGI 38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV1.pdf PDF
TGI_38K6113801A01_c1v0_REV1.pdf PDF
TGI_38K6152101A02_c0v0_REV1.pdf PDF
TGI_38K6145601A01_c0v0_REV1.pdf PDF
TGI_38K6164401A01_c1v2_REV1.pdf PDF
Solicitation Amendment N6264926RA0360002 SF 30.pdf PDF
TGI_38K6113702A01_c0v0_REV1.pdf PDF
TGI_38K6112303A01_c0v0_REV1.pdf PDF
TGI_38K6113601A01_c0v0_REV1.pdf PDF
TGI_38K6113602A01_c0v0_REV1.pdf PDF
TGI_38K6112325A01_c0v0_REV1.pdf PDF
TGI_38K6154103A02_c0v0_REV1.pdf PDF
TGI_38K6144104A01_c0v0_REV1.pdf PDF
TGI_38K6151101A01_c0v0_REV1.pdf PDF
material info.pdf PDF
6220213_53711_-_0001_ R_-_0001.pdf PDF
38K6112318A01-Engrg Inst.pdf PDF
Attachment IV Request for Information Form.docx DOCX document
Attachment II Proposal Sheet Generator v1.2.xlsx XLSX spreadsheet
TGI_38K6113801A01_c1v0.pdf PDF
TGI_38K6145601A01_c0v0.pdf PDF
TGI_38K6112318A01_c0v0.pdf PDF
TGI 38K6186301A01_c0v0.pdf PDF
TGI_38K6112320A01_c1v1.pdf PDF
TGI_38K6112305A01_c1v0.pdf PDF
TGI 38K6144104A01_c0v0.pdf PDF
Attachment III Request for Information Sheet (Fillable).pdf PDF
TGI_38K6154103A02_c0v0.pdf PDF
TGI_38K6112301A01_c0v0.pdf PDF
TGI 38K6158301A01_c0v0.pdf PDF
TGI_38K6112317A01_c0v0.pdf PDF
TGI_38K6112304A01_c0v0.pdf PDF
TGI 38K6152101A02_c0v0.pdf PDF
TGI 38K6154101A01_c1v1.pdf PDF
TGI 38K6165401A01_c0v0.pdf PDF
TGI 38K6164401A01_c1v2.pdf PDF
TGI 38K6154101T02_c0v0.pdf PDF
Attachment IV DDG-115_BUNDLE1_GFP_List.xlsx XLSX spreadsheet
Attachment VIII Contract data.pdf PDF
Solicitation - N6264926RA036.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

21-JAN-2026 1541

20.15.6.0.9333 (July 2025) ICN: 38K6112303 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MTG BRKT 02-174-1-Q AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O - RPR INCOMPLETED WELD OF BMTLC TRNSN JT FOR ENG REMOVAL RAIL IN 02-174-1-Q

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

ES01NA54

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

ASHINA, TAKAAKI 231B 3152434370 03-NOV-2025

APPROVED BY: CODE: PHONE: DATE:

OOSERA, TATSUYA 231B 3152439935 03-NOV-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-NA54

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

SAITO, KAZUNOBU

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A2103

1 SCOPE/PURPOSE:

1.1 Title: Incompleted Weld of Bimetallic Transition Joint for Engine Removal Rail in 02-174-1-Q; repair

1.2 Location of Work:

1.2.1 Intake Engine Room No. One, Starboard (Stbd) (02-174-1-Q)

1.2.2 Intake Trunk (A) Engine Room No. One (1-174-5-Q)

1.2.3 Engine Room No. One (4-174-0-E)

1.3 Identification:

1.3.1 Quantity (One Lot), Bimetallic Transition Joint for Engine Removal Rail in 02-174-1-Q, Frames between 184 and 185, Stbd

Remarks: See Detail 3J-8F of Ref. No. 4 for base material and Sketch Enclosure-01 for location detail

TGI Short Form

21-JAN-2026 1541

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112303 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MTG BRKT 02-174-1-Q AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O - RPR INCOMPLETED WELD OF BMTLC TRNSN JT FOR ENG REMOVAL RAIL IN 02-174-1-Q

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2 PROCEDURE:

2.1 Accomplish the requirements of Ref. No. 3.

(V)(G) “GAS TURBINE MAINTENANCE PROCEDURE”

2.2 Accomplish weld repair of incompleted weld of each existing bimetallic transition joint listed in 1.3.1 in accordance with Ref.

No. 4.

2.2.1 Accomplish the requirements of 009-012 of Ref. No. One, including Table 2, Column(s) D, Lines One through 7.

2.3 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.

2.4 Notes:

2.4.1 Planner: Code 231B T. Ashina, 243-4370

2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560

2.4.3 This TGI is in response to CCIMS report No. CCIMS-G1N6-DDG115-049-24 from TGI No. 3815C11003I10.

2.4.4 JCN ES01-NA54 is related to this TGI.

2.5 Government Furnished Material (GFM): None.

2.6 SRF-JRMC will provide the following service work: (TGI No. 38K6112303S02).

2.6.1 [C740] Crane and crane rigging service.

2.6.2 [X99E] Utility service, electrical.

2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.6.6 [C133] QA inspection for (G) symbol(s).

2.6.7 [C285] Inspection for (G) symbol(s).

Kouichi.Yoshida.ja Typewritten Text 7/27/2026

Kouichi.Yoshida.ja Typewritten Text 9/4/2026

21-JAN-2026 1541

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112303 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MTG BRKT 02-174-1-Q AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O - RPR INCOMPLETED WELD OF BMTLC TRNSN JT FOR ENG REMOVAL RAIL IN 02-174-1-Q

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

21-JAN-2026 1541

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6112303 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MTG BRKT 02-174-1-Q AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61

CU PHASE TITLE: *F/O - RPR INCOMPLETED WELD OF BMTLC TRNSN JT FOR ENG REMOVAL RAIL IN 02-174-1-Q

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 MP LM19-K6112303-

ES01NA54

1A GTM INTK SYS FOD

PROTN FOR REPAIR ENG

REMOVAL RAIL BRKT &

BIMETALIC JOINT

- Y ALL

4 DWG 234-6218562 GTRB REMOVAL ENGINE

ROOM NO. ONE

R Y 3J, 5M

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38K6112303A01-Sketch.pdf 01-NOV-2025 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K6112303 KEY OP: A01

Takaaki.Ashina.ja Text Box

LOCATION DETAIL FOR WELD REPAIR

Takaaki.Ashina.ja_1 Text Box

PLAN VIEW

02 LVL FR 158 - 199

STABOARD

Takaaki.Ashina.ja_2 Line

Takaaki.Ashina.ja_3 Line

Takaaki.Ashina.ja_4 Line

Takaaki.Ashina.ja_5 Line

Takaaki.Ashina.ja_6 Text Box

EL 2-A

Takaaki.Ashina.ja_7 Line

Takaaki.Ashina.ja_8 Text Box

INTAKE ENGINE RM NO.1 (STBD)(02-174-1-Q)

Takaaki.Ashina.ja_9 Line

Takaaki.Ashina.ja_10 Text Box

FWD

Takaaki.Ashina.ja_11 Text Box

Takaaki.Ashina.ja_12 Text Box

Takaaki.Ashina.ja_13 Text Box 38K6112303A01

Takaaki.Ashina.ja_14 Text Box

SKETCH

ENCLOSURE-01

Takaaki.Ashina.ja_15 Text Box Sheet 1 of 2

Takaaki.Ashina.ja_16 Rectangle

Takaaki.Ashina.ja_17 Line

Takaaki.Ashina.ja_18 Line

Takaaki.Ashina.ja_19 Text Box

INTAKE ENGINE

RM NO.1 (Port) (02-174-0-Q)

Takaaki.Ashina.ja_20 Text Box

PASSAGE

(02-166-5-L)

Takaaki.Ashina.ja_21 Text Box

LINEN LOCKER (02-166-3-A)

Takaaki.Ashina.ja_22 Text Box

UPTAKE ENGINE

RM NO.1 (02-186-0-Q)

Takaaki.Ashina.ja_23 Text Box

Takaaki.Ashina.ja_24 Line

Takaaki.Ashina.ja_25

ELEVATION 2-A

02 LEVEL, STBD

LKG INBOARD

Takaaki.Ashina.ja_26 Line

Takaaki.Ashina.ja_27 Line

Takaaki.Ashina.ja_28 Line

Takaaki.Ashina.ja_29 Line

Takaaki.Ashina.ja_30 Line

Takaaki.Ashina.ja_31 Text Box

PLAN 2-B

Takaaki.Ashina.ja_32 Line

Takaaki.Ashina.ja_33 Line

Takaaki.Ashina.ja_34 Line

Takaaki.Ashina.ja_35 Text Box

INCOMPLETEDWELD,

11LG

Takaaki.Ashina.ja_36 Text Box 38K6112303A01

Takaaki.Ashina.ja_37 Text Box

SKETCH

ENCLOSURE-01

Takaaki.Ashina.ja_38 Line

Takaaki.Ashina.ja_39 Text Box Sheet 2 of 2

Takaaki.Ashina.ja_40 Text Box

PLAN 2-B

BIMETALLIC TRANSITION JOINT

02 LEVEL, STBD

Takaaki.Ashina.ja_41

Takaaki.Ashina.ja_42 Rectangle

Takaaki.Ashina.ja_43 Rectangle

Takaaki.Ashina.ja_44 Line

Takaaki.Ashina.ja_45 Line

Takaaki.Ashina.ja_46 Text Box

:INCOMPLETED WELD

Takaaki.Ashina.ja_47 Text Box

DETAIL 2-C

Takaaki.Ashina.ja_48 Text Box

Takaaki.Ashina.ja_49 Text Box

BIMETALLIC TRNSITION JOINT

Takaaki.Ashina.ja_50 Line

Takaaki.Ashina.ja_51 Rectangle

Takaaki.Ashina.ja_52 Text Box

DETAIL 2-C

BIMETALLIC TRANSITION JOINT

Takaaki.Ashina.ja_53

Takaaki.Ashina.ja_54

ENGINE REMOVAL RAIL